Trans-Anatolian Natural Gas Pipeline Project

Abstract*

The development objective of the Trans-Anatolian Natural Gas Pipeline (TANAP) Project for Azerbaijan and Turkey is to diversify Azerbaijan's gas export markets and improve the security of Turkey's and South East Europe's energy supply. This project has comprises three components. The first component, TANAP pipeline system will finance infrastructure investments for the TANAP Pipeline System. At 1,850 km, TANAP accounts for over one half of the 3,500...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project's Development Objective is to diversify Azerbaijan's gas export markets and improve the security of Turkey's and South East Europe's energy supply.

Key Details

Project Details

  • P157416

  • Closed

  • Abdulaziz Faghi

  • Southern Gas Corridor CJSC (SGC),Boru Hatlari Ile Petrol Tasima A.S. (BOTAS)

  • Europe and Central Asia

  • February 26, 2016

  • (as of board presentation)

    December 20, 2016

  • January 27, 2017

  • US$ 8600.00 million

  • TANAP Dogalgaz Iletim A.S. (TANAP)

  • Europe and Central Asia

  • 2017

  • US$ 3200.00 million

  • A

  • October 2, 2023

  • July 31, 2021

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
European Bank for Reconstruction and Development 500.00
Borrower/Recipient 2400.00
Asian Infrastructure Investment Bank 600.00
International Bank for Reconstruction and Development 800.00
Private Commercial Sources (identified) 2000.00
Foreign Private Commercial Sources (unidentified) 1000.00
EC: European Investment Bank 1300.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 800.00
IDA Commitment N/A
IBRD + IDA Commitment 800.00
Lending Instrument
Grant Amount 2400.00
Total Project Cost** 8600.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 1, 2017 IBRD-86790 Int Charges 4,358,097.00
Jun 1, 2024 IBRD-86810 Int Charges 12,886,029.00
Jun 1, 2024 IBRD-86810 Loan Repay 10,520,000.00
Jun 1, 2024 IBRD-86790 Int Charges 7,912,000.00
Jun 1, 2024 IBRD-86790 Loan Repay 8,000,000.00
Dec 20, 2016 IBRD-86790 Loan Commitment 400,000,000.00
Dec 20, 2016 IBRD-86810 Loan Commitment 400,000,000.00
Jun 1, 2023 IBRD-86790 Int Charges 8,256,000.00
Jun 1, 2023 IBRD-86790 Loan Repay 8,000,000.00
Jun 1, 2023 IBRD-86810 Int Charges 12,472,205.00
Jun 1, 2023 IBRD-86810 Loan Repay 10,520,000.00
Dec 1, 2023 IBRD-86790 Int Charges 8,084,000.00
Dec 1, 2023 IBRD-86790 Loan Repay 8,000,000.00
Dec 1, 2023 IBRD-86810 Int Charges 12,960,491.00
Dec 1, 2023 IBRD-86810 Loan Repay 10,520,000.00
Dec 1, 2022 IBRD-86810 Int Charges 6,672,117.00
Dec 1, 2022 IBRD-86810 Loan Repay 10,520,000.00
Dec 1, 2022 IBRD-86790 Int Charges 8,428,000.00
Dec 1, 2022 IBRD-86790 Loan Repay 8,000,000.00
Jun 1, 2022 IBRD-86790 Int Charges 8,600,000.00
Jun 1, 2022 IBRD-86790 Loan Repay 8,000,000.00
Dec 1, 2021 IBRD-86790 Int Charges 8,600,000.00
Dec 1, 2021 IBRD-86810 Int Charges 2,989,000.00
Jun 1, 2022 IBRD-86810 Int Charges 3,134,444.50
Jun 1, 2022 IBRD-86810 Loan Repay 10,520,000.00
Jun 1, 2020 IBRD-86790 Int Charges 8,600,000.00
Dec 1, 2020 IBRD-86810 Int Charges 3,700,666.80
Dec 1, 2020 IBRD-86790 Int Charges 8,600,000.00
Jun 1, 2021 IBRD-86810 Int Charges 3,154,666.80
Jun 1, 2021 IBRD-86790 Int Charges 8,600,000.00
Jun 1, 2019 IBRD-86790 Int Charges 8,600,000.00
Jun 1, 2019 IBRD-86810 Int Charges 8,473,111.00
Dec 1, 2019 IBRD-86790 Int Charges 8,600,000.00
Dec 1, 2019 IBRD-86810 Int Charges 7,808,000.00
Jun 1, 2020 IBRD-86810 Int Charges 6,506,666.50
Mar 2, 2018 IBRD-86810 Loan Disb 14,936,239.00
Jun 1, 2018 IBRD-86810 Int Charges 81,631.03
Dec 1, 2017 IBRD-86790 Int Charges 4,358,097.00
Dec 1, 2017 IBRD-86790 Loan Disb 400,000,000.00
Dec 1, 2017 IBRD-86790 Loan Disb -400,000,000.00
Jun 1, 2018 IBRD-86790 Int Charges 3,006.71
Jun 1, 2018 IBRD-86790 Int Charges 33,087.22
Jun 1, 2018 IBRD-86790 Int Charges 8,600,000.00
Jun 1, 2018 IBRD-86810 Int Charges 12,876.23
Jun 1, 2018 IBRD-86810 Int Charges 128,640.65
Dec 1, 2018 IBRD-86810 Int Charges 258,167.27
Dec 1, 2018 IBRD-86810 Int Charges 7,665,666.50
Dec 1, 2018 IBRD-86810 Int Charges 23,460.27
Dec 1, 2018 IBRD-86790 Int Charges 8,600,000.00
Jun 1, 2017 IBRD-86790 Int Charges 88,135.58
Jun 1, 2017 IBRD-86810 Int Charges 245,909.60
Jun 1, 2017 IBRD-86810 Int Charges 148,105.80
Jun 1, 2017 IBRD-86790 Int Charges 1,597,280.40
Mar 30, 2017 IBRD-86810 Loan Disb 30,757,076.00
Mar 30, 2017 IBRD-86790 Loan Disb 146,314,368.00
Jan 27, 2017 IBRD-86790 Loan Disb 1,000,000.00
Jan 27, 2017 IBRD-86790 Fee Charges 1,000,000.00
Feb 8, 2017 IBRD-86810 Loan Disb 1,000,000.00
Feb 8, 2017 IBRD-86810 Fee Charges 1,000,000.00
Aug 2, 2017 IBRD-86810 Loan Disb 31,071,084.00
Sep 5, 2017 IBRD-86810 Loan Disb 28,926,678.00
Oct 5, 2017 IBRD-86810 Loan Disb 22,446,936.00
Jul 14, 2017 IBRD-86810 Loan Disb 32,767,228.00
Jun 2, 2017 IBRD-86810 Loan Disb 29,053,620.00
Feb 23, 2017 IBRD-86790 Loan Disb 108,400,000.00
May 2, 2017 IBRD-86810 Loan Disb 28,750,000.00
Apr 4, 2018 IBRD-86810 Loan Disb 59,055,164.00
Jan 9, 2018 IBRD-86810 Loan Disb 33,005,602.00
Nov 7, 2017 IBRD-86810 Loan Disb 25,018,902.00
Nov 22, 2017 IBRD-86790 Loan Disb 48,775,584.00
Sep 27, 2017 IBRD-86790 Loan Disb 95,510,048.00
Feb 6, 2018 IBRD-86810 Loan Disb 25,731,228.00
Dec 1, 2017 IBRD-86790 Int Charges 135,322.86
Dec 1, 2017 IBRD-86810 Int Charges 2,049,376.40
Dec 1, 2017 IBRD-86810 Int Charges 56,384.13
Dec 1, 2017 IBRD-86810 Int Charges 302,026.60
Dec 1, 2017 IBRD-86810 Int Charges 5,907.54
Jun 1, 2018 IBRD-86810 Int Charges 4,724,215.00
Dec 1, 2017 IBRD-86790 Int Charges -135,322.86
Dec 1, 2017 IBRD-86790 Int Charges -4,358,097.00
Dec 7, 2017 IBRD-86810 Loan Disb 37,480,248.00
Dec 1, 2017 IBRD-86790 Int Charges 135,322.86

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2021-02-09
Overall Implementation Progress (IP) Satisfactory 2021-02-09
Progress towards achievement of PDO Satisfactory 2021-02-09
Procurement Satisfactory 2021-02-09
Financial Management Satisfactory 2021-02-09
Monitoring and Evaluation Satisfactory 2021-02-09
Project Management Satisfactory 2021-02-09

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-31-2022
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityHighN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Diversifying Azerbaijan's Gas Export MarketsValue0.007411563860.000.00
    DateJuly 1, 2016September 30, 2021
    Comment
  • Improving the Security of Turkey's Energy SupplyValue0.005693970558.000.00
    DateJuly 1, 2016September 30, 2021
    Comment
  • Improving the Security of Europe's Energy SupplyValue0.007411563860.000.00
    DateJuly 1, 2016September 30, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Availability of TANAP for Gas Supply to TurkeyValue0.005400000000.000.00
    DateJuly 1, 2016January 31, 2021
    Comment
  • Progress in registration of affected private land parcelsValue32.0099.6260.00
    DateJuly 1, 2016December 6, 2021
    Comment
  • Turkish Gas Consumers Benefitting from Gas SupplyValue11000.0015000.0012000.00
    DateJuly 1, 2016January 31, 2021
    Comment
  • Progress in registration of affected private land parcelsValue6072.0018542.000.00
    DateJuly 1, 2016November 8, 2018
    Comment
  • Registered grievances addressed within the stipulated time frameValue91.0098.7390.00
    DateJuly 1, 2016December 6, 2021
    Comment
  • Number of community consultations held as of the total number of communities along the actively worked sections of the pipelineValue100.00100.00100.00
    DateJuly 1, 2016January 31, 2021
    Comment
  • Number of community consultations held for women as of the total number of communities along the actively worked sections of the pipeline (and % of consultations held separately for women)Value18.0040.0030.00
    DateJuly 1, 2016January 31, 2021
    Comment
  • Share of women employed by construction contractors out of total employee numberValue5.005.005.00
    DateJuly 1, 2016January 31, 2021
    Comment