Development Objective

The objective of the Project is to increase access to sustainable water services in selected urban areas within the Recipient's territory.

Key Details

Project Details

  • P157438

  • Closed

  • Madio Fall

  • N/A

  • Mali

  • May 16, 2016

  • (as of board presentation)

    June 28, 2016

  • N/A

  • US$ 50.00 million

  • B

  • Not Applicable

  • December 31, 2022

  • Yes

  • BANK APPROVED

  • P122826

  • October 17, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 30.00
IDA Grant 20.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 50.00
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 50.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of people in urban areas provided with access to Improved Water Sources under the projectValue0.000.00710000.00
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • Financial equilibrium of the urban water supply sub-sectorValueYesYesYes
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • People with access to enhanced water supply services under the projectValue0.000.00256000.00
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • Direct project beneficiariesValue0.000.00966000.00
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • Female beneficiariesValue0.000.0050.00
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Completion of technical auditsValueNoNoYes
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • Water storage capacity constructedValue0.000.0022000.00
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • Completion of the assessment of the execution of contractual arrangementsValueNoNoYes
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • Improved community water points constructed or rehabilitated under the projectValue0.000.00700.00
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • Transmission pipes constructedValue0.0011.3013.00
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • New piped household water connections that are resulting from the project interventionValue0.000.0050000.00
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • Distribution pipes constructedValue0.000.00957.00
    DateSeptember 24, 2013May 3, 2016December 31, 2021
    Comment
  • Production capacity installed under the projectValue0.000.007500.00
    DateMay 3, 2016December 31, 2021
    Comment
  • Beneficiaries who know at least two of their responsibilities regarding their access to waterValue0.000.0075.00
    DateMay 16, 2016May 16, 2016December 31, 2021
    Comment
  • Satisfactory complaint resolution by the service operatorValue80.0080.0092.00
    DateMay 16, 2016May 16, 2016December 31, 2021
    Comment