Financier | Commitments |
---|---|
IDA Credit | 200.00 |
P158194
Closed
Jolanta Kryspin-Watson , Sadig Aliyev, Simone Esler
Republic of the Union of Myanmar
Myanmar
June 3, 2016
(as of board presentation)
July 14, 2016
February 20, 2017
US$ 200.00 million
Ministry of Cooperative and Development of Rural Area,Ministry of Construction,Ministry of Planning and Finance
2017
US$ 200.00 million
B
November 30, 2023
December 31, 2021
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 200.00 |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 26, 2019 | IDA-58890 | Loan Disb | -2,624,150.20 |
Aug 2, 2019 | IDA-58890 | Loan Disb | 16,186.29 |
Jun 1, 2019 | IDA-58890 | Int Charges | 52,754.29 |
Jun 1, 2019 | IDA-58890 | Int Charges | 52,754.29 |
May 28, 2019 | IDA-58890 | Loan Disb | 47,250.00 |
May 24, 2019 | IDA-58890 | Loan Disb | 387,915.44 |
Jun 1, 2019 | IDA-58890 | Int Charges | 6,664.64 |
Jun 1, 2019 | IDA-58890 | Int Charges | 13,663.01 |
Jun 1, 2019 | IDA-58890 | Int Charges | 13,663.01 |
Jun 1, 2019 | IDA-58890 | Int Charges | 558.39 |
Jun 1, 2019 | IDA-58890 | Int Charges | 558.39 |
Jun 1, 2019 | IDA-58890 | Int Charges | 6,664.64 |
Sep 23, 2019 | IDA-58890 | Loan Disb | 1,477,096.90 |
Sep 12, 2019 | IDA-58890 | Loan Disb | 8,112.74 |
Sep 26, 2019 | IDA-58890 | Loan Disb | 566,193.00 |
Nov 20, 2019 | IDA-58890 | Loan Disb | 146,214.23 |
Jul 31, 2019 | IDA-58890 | Loan Disb | 74,506.01 |
Nov 4, 2019 | IDA-58890 | Loan Disb | 122,613.85 |
Oct 30, 2019 | IDA-58890 | Loan Disb | 63,775.00 |
Mar 12, 2020 | IDA-58890 | Loan Disb | 60,067.04 |
Mar 24, 2020 | IDA-58890 | Loan Disb | 50,748.37 |
Sep 25, 2019 | IDA-58890 | Loan Disb | 162,368.27 |
Nov 18, 2019 | IDA-58890 | Loan Disb | 592,760.40 |
Jan 17, 2020 | IDA-58890 | Loan Disb | 1,482,473.50 |
Dec 1, 2019 | IDA-58890 | Int Charges | 45,597.85 |
Dec 1, 2019 | IDA-58890 | Int Charges | 45,597.85 |
Dec 1, 2019 | IDA-58890 | Int Charges | 9,702.33 |
Dec 1, 2019 | IDA-58890 | Int Charges | 9,702.33 |
Dec 1, 2019 | IDA-58890 | Int Charges | 17,926.81 |
Dec 1, 2019 | IDA-58890 | Int Charges | 17,926.81 |
Dec 1, 2019 | IDA-58890 | Int Charges | 502.99 |
Dec 1, 2019 | IDA-58890 | Int Charges | 502.99 |
Jun 1, 2017 | IDA-58890 | Int Charges | 517.76 |
Jun 1, 2017 | IDA-58890 | Int Charges | 517.76 |
Jun 1, 2017 | IDA-58890 | Int Charges | 22.17 |
Jun 1, 2017 | IDA-58890 | Int Charges | 22.17 |
Mar 30, 2017 | IDA-58890 | Loan Disb | 17,488.33 |
Mar 24, 2017 | IDA-58890 | Loan Disb | 387,038.44 |
Dec 1, 2017 | IDA-58890 | Int Charges | 37.15 |
Apr 2, 2020 | IDA-58890 | Loan Disb | 31,092.36 |
Jun 29, 2020 | IDA-58890 | Loan Disb | 54,600.00 |
May 28, 2020 | IDA-58890 | Loan Disb | 190,000.00 |
Jun 12, 2020 | IDA-58890 | Loan Disb | 198,880.67 |
Jun 24, 2020 | IDA-58890 | Loan Disb | 150,871.78 |
Jun 1, 2020 | IDA-58890 | Loan Disb | 357,227.06 |
May 21, 2020 | IDA-58890 | Loan Disb | 38,281.68 |
Jun 11, 2020 | IDA-58890 | Loan Disb | 55,071.82 |
Jun 11, 2020 | IDA-58890 | Loan Disb | 270,263.56 |
Jun 1, 2020 | IDA-58890 | Int Charges | 43,472.31 |
Jun 1, 2020 | IDA-58890 | Int Charges | 43,472.31 |
Jun 1, 2020 | IDA-58890 | Int Charges | 891.27 |
Jun 1, 2020 | IDA-58890 | Int Charges | 891.27 |
Jun 1, 2020 | IDA-58890 | Int Charges | 30,885.51 |
Jun 1, 2020 | IDA-58890 | Int Charges | 30,885.51 |
Jun 1, 2020 | IDA-58890 | Int Charges | 10,444.21 |
Jun 1, 2020 | IDA-58890 | Int Charges | 10,444.21 |
Jun 26, 2020 | IDA-58890 | Loan Disb | 175,237.14 |
Aug 26, 2020 | IDA-58890 | Loan Disb | 370,651.90 |
Aug 10, 2020 | IDA-58890 | Loan Disb | 30,270.09 |
Sep 3, 2020 | IDA-58890 | Loan Disb | 268,774.10 |
Sep 25, 2020 | IDA-58890 | Loan Disb | 501,201.53 |
Sep 23, 2020 | IDA-58890 | Loan Disb | 437,742.12 |
Sep 23, 2020 | IDA-58890 | Loan Disb | 343,467.62 |
Sep 28, 2020 | IDA-58890 | Loan Disb | 23,315.58 |
Sep 28, 2020 | IDA-58890 | Loan Disb | 165,020.34 |
Sep 28, 2020 | IDA-58890 | Loan Disb | 679,348.60 |
Sep 28, 2020 | IDA-58890 | Loan Disb | 66,864.51 |
Jul 14, 2020 | IDA-58890 | Loan Disb | 87,000.00 |
Jul 9, 2020 | IDA-58890 | Loan Disb | 82,358.99 |
Aug 20, 2020 | IDA-58890 | Loan Disb | 72,268.71 |
Dec 28, 2023 | IDA-58890 | Loan Repay | 541,056.56 |
Dec 28, 2023 | IDA-58890 | Int Charges | 410.25 |
Dec 28, 2023 | IDA-58890 | Int Charges | 410.25 |
Dec 28, 2023 | IDA-58890 | Int Charges | 113,596.81 |
Dec 28, 2023 | IDA-58890 | Int Charges | 113,596.81 |
Jun 7, 2024 | IDA-58890 | Int Charges | 300.83 |
Jun 7, 2024 | IDA-58890 | Int Charges | 300.83 |
Jun 7, 2024 | IDA-58890 | Int Charges | 122,191.97 |
Jun 7, 2024 | IDA-58890 | Int Charges | 122,191.97 |
Jun 1, 2022 | IDA-58890 | Int Charges | 69,233.02 |
Jun 1, 2022 | IDA-58890 | Int Charges | 69,233.02 |
Jun 1, 2022 | IDA-58890 | Int Charges | 18,450.39 |
Jun 1, 2022 | IDA-58890 | Int Charges | 18,450.39 |
Apr 4, 2022 | IDA-58890 | Loan Disb | 115,039.72 |
Jul 18, 2022 | IDA-58890 | Loan Disb | -18,736.87 |
Dec 17, 2021 | IDA-58890 | Loan Disb | 21,069.94 |
Aug 18, 2022 | IDA-58890 | Loan Disb | -9.24 |
Aug 14, 2020 | IDA-58890 | Loan Disb | 39,070.00 |
Sep 4, 2020 | IDA-58890 | Loan Disb | 154,283.42 |
Jul 21, 2020 | IDA-58890 | Loan Disb | 98,328.39 |
Dec 1, 2020 | IDA-58890 | Int Charges | 45,167.70 |
Dec 1, 2020 | IDA-58890 | Int Charges | 45,167.70 |
Dec 4, 2020 | IDA-58890 | Loan Disb | 284,577.78 |
Dec 1, 2020 | IDA-58890 | Int Charges | 655.75 |
Dec 5, 2017 | IDA-58890 | Loan Disb | 35,777.00 |
Dec 1, 2017 | IDA-58890 | Int Charges | 1,515.72 |
Dec 1, 2017 | IDA-58890 | Int Charges | 1,515.72 |
Mar 20, 2018 | IDA-58890 | Loan Disb | 272,720.20 |
Jul 16, 2018 | IDA-58890 | Loan Disb | 50,894.00 |
Jun 1, 2018 | IDA-58890 | Int Charges | 26.03 |
Dec 1, 2020 | IDA-58890 | Int Charges | 655.75 |
Dec 1, 2020 | IDA-58890 | Int Charges | 14,549.65 |
Dec 1, 2020 | IDA-58890 | Int Charges | 14,549.65 |
Nov 20, 2020 | IDA-58890 | Loan Disb | 304,137.10 |
Dec 1, 2020 | IDA-58890 | Int Charges | 44,030.36 |
Dec 1, 2020 | IDA-58890 | Int Charges | 44,030.36 |
Dec 28, 2020 | IDA-58890 | Loan Disb | 178,508.34 |
Dec 28, 2020 | IDA-58890 | Loan Disb | 277,812.40 |
Jan 12, 2021 | IDA-58890 | Loan Disb | 76,082.86 |
Nov 25, 2020 | IDA-58890 | Loan Disb | 42,932.99 |
Nov 19, 2020 | IDA-58890 | Loan Disb | 50,000.01 |
Dec 2, 2020 | IDA-58890 | Loan Disb | 53,537.04 |
Dec 11, 2020 | IDA-58890 | Loan Disb | 345,844.72 |
Jan 19, 2021 | IDA-58890 | Loan Disb | 83,756.74 |
Dec 28, 2020 | IDA-58890 | Loan Disb | 445,414.50 |
Jun 1, 2021 | IDA-58890 | Int Charges | 1,471.98 |
Jun 1, 2021 | IDA-58890 | Int Charges | 1,471.98 |
Jun 1, 2021 | IDA-58890 | Int Charges | 45,188.66 |
Jun 1, 2021 | IDA-58890 | Int Charges | 45,188.66 |
Jun 1, 2021 | IDA-58890 | Int Charges | 16,548.95 |
Jun 1, 2021 | IDA-58890 | Int Charges | 16,548.95 |
Sep 21, 2021 | IDA-58890 | Loan Disb | 6,732.07 |
Jun 1, 2021 | IDA-58890 | Int Charges | 60,004.19 |
Jun 1, 2021 | IDA-58890 | Int Charges | 60,004.19 |
Sep 22, 2021 | IDA-58890 | Loan Disb | 344,200.72 |
Sep 21, 2021 | IDA-58890 | Loan Disb | 169,540.00 |
Dec 2, 2021 | IDA-58890 | Int Charges | 44,360.82 |
Dec 19, 2019 | IDA-58890 | Loan Disb | 27,952.63 |
Jan 3, 2020 | IDA-58890 | Loan Disb | 131,629.52 |
Dec 19, 2019 | IDA-58890 | Loan Disb | 36,668.40 |
Dec 17, 2019 | IDA-58890 | Loan Disb | 41,409.00 |
Apr 13, 2020 | IDA-58890 | Loan Disb | 50,000.00 |
Apr 21, 2020 | IDA-58890 | Loan Disb | 221,291.77 |
Jun 7, 2024 | IDA-58890 | Int Charges | 13,421.23 |
Jun 7, 2024 | IDA-58890 | Int Charges | 13,421.23 |
Jun 7, 2024 | IDA-58890 | Loan Repay | 540,674.94 |
Jul 14, 2016 | IDA-58890 | Loan Commitment | 200,000,000.00 |
Jul 18, 2022 | IDA-58890 | Loan Cancel | 153,250,736.00 |
Aug 18, 2022 | IDA-58890 | Loan Cancel | 9.24 |
Dec 1, 2022 | IDA-58890 | Loan Repay | 2,915.12 |
Jan 26, 2023 | IDA-58890 | Int Charges | 95,673.39 |
Jan 26, 2023 | IDA-58890 | Loan Repay | 548,274.50 |
Jan 26, 2023 | IDA-58890 | Int Charges | 95,673.39 |
Jul 7, 2023 | IDA-58890 | Int Charges | 36,164.14 |
Jul 7, 2023 | IDA-58890 | Int Charges | 36,164.14 |
Jul 7, 2023 | IDA-58890 | Loan Repay | 543,756.10 |
Jul 7, 2023 | IDA-58890 | Int Charges | 619.69 |
Jul 7, 2023 | IDA-58890 | Int Charges | 619.69 |
Jul 7, 2023 | IDA-58890 | Int Charges | 128,462.40 |
Jul 7, 2023 | IDA-58890 | Int Charges | 128,462.40 |
Dec 1, 2023 | IDA-58890 | Loan Repay | 5,888.19 |
Dec 2, 2021 | IDA-58890 | Int Charges | 44,360.82 |
Sep 23, 2021 | IDA-58890 | Loan Disb | 11,138.15 |
Sep 24, 2021 | IDA-58890 | Loan Disb | 47,634.85 |
Sep 20, 2021 | IDA-58890 | Loan Disb | 806,252.56 |
Sep 10, 2021 | IDA-58890 | Loan Disb | 135,818.56 |
Sep 10, 2021 | IDA-58890 | Loan Disb | 228,186.94 |
Sep 10, 2021 | IDA-58890 | Loan Disb | 1,220,081.50 |
Sep 10, 2021 | IDA-58890 | Loan Disb | 455,386.40 |
Sep 10, 2021 | IDA-58890 | Loan Disb | 647,813.20 |
Sep 17, 2021 | IDA-58890 | Loan Disb | 129,072.00 |
Jul 14, 2022 | IDA-58890 | Loan Disb | -16,529.86 |
Dec 2, 2021 | IDA-58890 | Int Charges | 2,394.89 |
Dec 2, 2021 | IDA-58890 | Int Charges | 2,394.89 |
Dec 2, 2021 | IDA-58890 | Int Charges | 65,681.16 |
Dec 2, 2021 | IDA-58890 | Int Charges | 65,681.16 |
Dec 1, 2021 | IDA-58890 | Int Charges | 17,708.76 |
Dec 1, 2021 | IDA-58890 | Int Charges | 17,708.76 |
Jun 29, 2022 | IDA-58890 | Loan Disb | -132.35 |
Jun 1, 2022 | IDA-58890 | Int Charges | 1,050.87 |
Jun 1, 2022 | IDA-58890 | Int Charges | 1,050.87 |
Jun 1, 2022 | IDA-58890 | Int Charges | 43,074.40 |
Jun 1, 2022 | IDA-58890 | Int Charges | 43,074.40 |
Jun 1, 2018 | IDA-58890 | Int Charges | 26.03 |
Jun 1, 2018 | IDA-58890 | Int Charges | 37,436.78 |
Jun 1, 2018 | IDA-58890 | Int Charges | 37,436.78 |
Jun 1, 2018 | IDA-58890 | Int Charges | 3.01 |
Jun 1, 2018 | IDA-58890 | Int Charges | 3.01 |
Jun 1, 2018 | IDA-58890 | Int Charges | 1,058.76 |
Jun 1, 2018 | IDA-58890 | Int Charges | 1,058.76 |
Dec 27, 2017 | IDA-58890 | Loan Disb | 43,843.56 |
Jan 19, 2018 | IDA-58890 | Loan Disb | 38,855.00 |
Dec 22, 2017 | IDA-58890 | Loan Disb | 60,000.00 |
Apr 9, 2018 | IDA-58890 | Loan Disb | 29,505.00 |
Apr 24, 2018 | IDA-58890 | Loan Disb | 66,108.00 |
Dec 7, 2017 | IDA-58890 | Loan Disb | 37,391.50 |
Apr 26, 2018 | IDA-58890 | Loan Disb | 808,701.60 |
Mar 29, 2018 | IDA-58890 | Loan Disb | 198,020.55 |
Feb 1, 2018 | IDA-58890 | Loan Disb | 15,000,000.00 |
Dec 1, 2017 | IDA-58890 | Int Charges | 32.30 |
Dec 1, 2017 | IDA-58890 | Int Charges | 32.30 |
Dec 1, 2017 | IDA-58890 | Int Charges | 37.15 |
Sep 18, 2018 | IDA-58890 | Loan Disb | 623,450.20 |
May 30, 2018 | IDA-58890 | Loan Disb | 35,470.00 |
Jun 1, 2018 | IDA-58890 | Int Charges | 1,619.90 |
Jun 1, 2018 | IDA-58890 | Int Charges | 1,619.90 |
Dec 3, 2018 | IDA-58890 | Loan Disb | 1,705,801.50 |
Nov 28, 2018 | IDA-58890 | Loan Disb | 54,791.99 |
Jan 31, 2019 | IDA-58890 | Loan Disb | 57,850.00 |
Jan 24, 2019 | IDA-58890 | Loan Disb | 15,729.99 |
Aug 26, 2020 | IDA-58890 | Loan Disb | 193,764.52 |
Sep 10, 2020 | IDA-58890 | Loan Disb | 50,000.01 |
Jul 13, 2020 | IDA-58890 | Loan Disb | 57,862.67 |
Sep 9, 2020 | IDA-58890 | Loan Disb | 18,899.99 |
Sep 16, 2020 | IDA-58890 | Loan Disb | 223,124.08 |
Sep 16, 2020 | IDA-58890 | Loan Disb | 137,923.60 |
Sep 21, 2020 | IDA-58890 | Loan Disb | 49,448.84 |
Sep 21, 2020 | IDA-58890 | Loan Disb | 583,327.90 |
Jan 25, 2019 | IDA-58890 | Loan Disb | 766,731.40 |
Feb 14, 2019 | IDA-58890 | Loan Disb | 123,004.51 |
Feb 5, 2019 | IDA-58890 | Loan Disb | 233,142.16 |
Dec 1, 2018 | IDA-58890 | Int Charges | 61,633.87 |
Dec 1, 2018 | IDA-58890 | Int Charges | 61,633.87 |
Dec 1, 2018 | IDA-58890 | Int Charges | 291.61 |
Dec 1, 2018 | IDA-58890 | Int Charges | 291.61 |
Dec 7, 2018 | IDA-58890 | Loan Disb | 50,000.00 |
Jul 10, 2019 | IDA-58890 | Loan Disb | 86,173.75 |
Mar 12, 2019 | IDA-58890 | Loan Disb | 74,971.00 |
Mar 15, 2019 | IDA-58890 | Loan Disb | 434,677.28 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2020-09-04 |
Procurement | Moderately Satisfactory | 2020-09-04 |
Project Management | Moderately Satisfactory | 2020-09-04 |
Financial Management | Moderately Satisfactory | 2020-09-04 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-09-04 |
Monitoring and Evaluation | Satisfactory | 2020-09-04 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2023 |
---|---|
Outcomes | Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 10-27-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 1154000.00 | 320000.00 |
Date | July 14, 2016 | December 31, 2021 | October 16, 2023 | |
Comment |
Female beneficiaries | Value | 0.00 | 0.00 | 50.00 |
Date | October 17, 2016 | April 20, 2018 | ||
Comment |
Length of road rehabilitated (rural/non-rural) | Value | 0.00 | 555.00 | 410.00 |
Date | July 14, 2016 | December 31, 2021 | October 16, 2023 | |
Comment |
Number of workdays generated | Value | 0.00 | 865000.00 | 613000.00 |
Date | July 14, 2016 | December 31, 2021 | October 16, 2023 | |
Comment |
Workdays generated by women | Value | 0.00 | 12.40 | 50.00 |
Date | October 17, 2016 | April 20, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehabilitated, Non-rural | Value | 0.00 | 155.00 | 150.00 |
Date | July 14, 2016 | December 31, 2021 | October 17, 2023 | |
Comment |
Roads rehabilitated, Rural | Value | 0.00 | 400.00 | 0.00 |
Date | July 14, 2016 | December 31, 2021 | October 17, 2024 | |
Comment |
Goods procured and distributed as outlined in the CERIP | Value | No | Yes | Yes |
Date | July 14, 2016 | December 31, 2021 | ||
Comment |
Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 95.00 | 95.00 |
Date | July 14, 2016 | December 31, 2021 | October 17, 2023 | |
Comment |
Improved disaster and climate resilient designs and standards for national roads developed | Value | No | Yes | Yes |
Date | July 14, 2016 | December 31, 2021 | October 17, 2023 | |
Comment |
Length of road maintained (rural) | Value | 0.00 | 300.00 | 89.00 |
Date | July 14, 2016 | December 31, 2021 | October 17, 2023 | |
Comment |