Clean Air and Sustainable Environment Project - Additional Financing

Development Objective

To improve air quality and safe mobility in Dhaka through the implementation of demonstration initiatives in urban transport and brick making

Key Details

Project Details

  • P160014

  • Closed

  • Harinath Appalarajugari , Lia Sieghart, Shigeyuki Sakaki

  • N/A

  • Bangladesh

  • October 19, 2016

  • (as of board presentation)

    January 13, 2017

  • N/A

  • US$ 36.58 million

  • N/A

  • South Asia

  • 2017

  • US$ 35.00 million

  • B

  • Not Applicable

  • March 31, 2019

  • TBD

  • BANK APPROVED

  • P098151

  • January 31, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 35.00
Borrower/Recipient 1.58

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 35.00
IBRD + IDA Commitment 35.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 36.58

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of brick kilns adopting cleaner technology and decreasing (i) particulate emissions by 20% and (ii) GHG emission by 20% by end of project periodValue0.0010.0012.00
    DateNovember 9, 2009January 31, 2016December 15, 2016
    Comment
  • Pedestrian using Foot Over Bridges in locations of interventionValue0.0079.0075.00
    DateNovember 9, 2009January 31, 2016December 15, 2016
    Comment
  • Pedestrian using sidewalks in locations of interventionValue0.0078.0075.00
    DateNovember 9, 2009January 31, 2016December 15, 2018
    CommentIndicator retained, but additional locations supported through AF will be monitored. At least four locations will be selected andaverage usage rate will be calculated
  • Increase of vehicular traffic in location of interventionsValue217700.00232000.00239500.00
    DateNovember 9, 2009January 31, 2016December 15, 2016
    Comment
  • Vehicular traffic increased at selected intersections with operational traffic signalsValue0.000.008.00
    DateDecember 15, 2018
    CommentBase line data will be collected after intersections are selectedAn 8 percent increase over base line traffic at the selected intersections. Includes additional locations supported throughadditional financing

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Construction of Foot Over BridgeValue02125
    DateNovember 9, 2009March 31, 2016December 15, 2016
    Comment
  • Corridors of separation of MV and NMV trafficValue0.002.002.00
    DateNovember 9, 2009January 31, 2016December 15, 2016
    Comment
  • At least 2 cities with updated source / emissions profilesValue0.002.002.00
    DateNovember 9, 2009December 31, 2015December 15, 2016
    Comment
  • Continuous air monitoring stations providing air quality data in BangladeshValue5.0011.0016.00
    DateNovember 9, 2009December 31, 2015December 15, 2018
    CommentEnd target has been revised by including the additional 5 stations proposed to be established through additional financing
  • Brick Burning Act drafted for Cabinet?s approvalValueNoneAct Approved by Parliament on November 20, 2013Brick Burning Act submitted to Cabinet
    DateDecember 31, 2015December 31, 2014
    Comment
  • Intersections Physically ImprovedValue0.0035.0040.00
    DateNovember 9, 2009January 31, 2016December 15, 2016
    Comment
  • Revised DTCB Act empowering DTCB presented to the Cabinet for approvalValueRevision initiatedPassed by Parliament and Published in the GazettePassed by Parliament and Published in the Gazette
    DateNovember 9, 2009January 31, 2016December 15, 2016
    Comment
  • Studies for (i) rationalization of bus route network (ii) BRT on a pilot corridorValue0.001.002.00
    DateNovember 9, 2009January 31, 2016December 15, 2016
    Comment
  • New sidewalks with surface drainage constructedValue0.0065.0088.00
    DateNovember 9, 2009January 31, 2016December 15, 2018
    CommentEnd target has been revised by including additional side walks proposed to be constructed through AF
  • Traffic safety campaignsValue0.003.003.00
    DateNovember 9, 2009January 31, 2016December 15, 2016
    Comment
  • Vehicular Emission Standards updatedValueNoneIncluded in ECRVehicle Emission Standards approved
    DateJanuary 31, 2016December 31, 2014
    Comment
  • Communication campaign implementedValueNoneCompletedCampaign continued
    DateDecember 31, 2015December 15, 2018
    CommentEnd Target continued through AF
  • Intersections with new traffic signals installed and operationalValue0.000.0029.00
    DateNovember 9, 2009January 31, 2016December 15, 2018
    CommentIndicator and targets modified to capture the output on new signals
  • Revised MVO Act for reduction in emissions submitted to CabinetValueNoneBRTA Act under review by Ministry of Law for vettiPresented to Cabinet for approval
    DateNovember 9, 2009January 31, 2016December 15, 2016
    Comment
  • Clean Air Act drafted with stakeholder consultations and recommended to GoB for adoptionValueNoNoYes
    DateSeptember 30, 2016September 30, 2016December 15, 2018
    Comment
  • Complete study and implement key recommendations for better mobility of disabled people in one selected location in DhakaValueNoNoYes
    DateSeptember 30, 2016September 30, 2016December 15, 2018
    Comment
  • Intersections with operational signals (including newly installed and existing fixed)Value0.000.0091.00
    DateSeptember 30, 2016September 30, 2016December 15, 2018
    CommentIndicator added to capture the output on both new and fixed signals.
  • Non-fired brick manufacturing technologies pilotedValueNoYes
    DateSeptember 30, 2016September 30, 2016December 15, 2018
    CommentResults of non-fired brick technology pilot to be measured to confirm effectiveness