Citizens' Charter Afghanistan Project

Abstract*

The development objective for the Citizens’ Charter Afghanistan Project is to improve the delivery of core infrastructure and social services to participating communities through strengthened Community Development Councils (CDCs). These services are part of a minimum service standards package that the Government is committed to delivering to the citizens of Afghanistan. Citizens’ Charter Afghanistan Project will seek to address key limitations of...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective for the Citizensâ?? Charter Afghanistan Project is to improve the delivery of core infrastructure, emergency support, and social services to participating communities through strengthened Community Development Councils (CDCs).

Key Details

Project Details

  • P160567

  • Active

  • Susan Wong

  • MINISTRY OF FINANCE

  • Afghanistan

  • May 30, 2016

  • (as of board presentation)

    October 27, 2016

  • January 23, 2017

  • US$ 717.23 million

  • Independent Directorate of Local Governance,Ministry of Rural Rehabilitation and Development

  • South Asia

  • 2017

  • US$ 677.23 million

  • B

  • May 1, 2024

  • June 30, 2025

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 40.00
Afghanistan Resilience Trust Fund 444.30
IDA Grant 232.93

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 232.93
IBRD + IDA Commitment 232.93
Lending Instrument
Grant Amount 444.30
Total Project Cost** 717.23

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 16, 2021 IDA-D2130 Loan Disb 868,307.50
Dec 9, 2020 IDA-D2130 Loan Disb 519,800.00
Sep 23, 2019 IDA-D1390 Loan Disb 31,406,490.00
Apr 13, 2020 IDA-D2130 Loan Disb 7,677,146.50
May 4, 2020 IDA-D2130 Loan Disb 4,900,000.00
Aug 31, 2017 IDA-D1390 Loan Disb 15,000,000.00
Aug 30, 2018 IDA-D2130 Loan Disb 25,000,024.00
Jun 4, 2018 IDA-D2130 Loan Disb 7,496,174.00
Dec 10, 2018 IDA-D1390 Loan Disb 34,000,000.00
Apr 10, 2019 IDA-D2130 Loan Disb 6,485,190.00
Sep 24, 2019 IDA-D2130 Loan Disb 2,264,176.50
Oct 27, 2016 IDA-D1390 Loan Commitment 100,000,000.00
Jun 13, 2017 IDA-D2130 Loan Commitment 127,700,000.00
Dec 11, 2020 IDA-D7520 Loan Commitment 35,000,000.00
Feb 15, 2022 IDA-D2130 Loan Disb 297.68
Feb 15, 2022 IDA-D2130 Loan Disb 10,314.37
Feb 15, 2022 IDA-D2130 Loan Disb 21,399.30
Feb 15, 2022 IDA-D2130 Loan Disb 11,752.15
Feb 15, 2022 IDA-D2130 Loan Disb 16,748.01
Feb 15, 2022 IDA-D2130 Loan Disb 899.75
Feb 15, 2022 IDA-D2130 Loan Disb 85,439.02
Feb 15, 2022 IDA-D2130 Loan Disb 2,311.40
Feb 15, 2022 IDA-D2130 Loan Disb 55,572.49
Feb 15, 2022 IDA-D2130 Loan Disb 989.26
Feb 15, 2022 IDA-D2130 Loan Disb 139,139.39
Feb 15, 2022 IDA-D2130 Loan Disb 68,456.40
Feb 15, 2022 IDA-D2130 Loan Disb 140,009.34
Feb 15, 2022 IDA-D2130 Loan Disb 303,058.00
Feb 15, 2022 IDA-D2130 Loan Disb 427,217.50
Apr 8, 2020 IDA-D2130 Loan Disb 3,731,952.80
Apr 8, 2020 IDA-D2130 Loan Disb -3,731,952.80
Feb 16, 2022 IDA-D2130 Loan Disb 877,589.94
Feb 16, 2022 IDA-D2130 Loan Disb 104,454.76
Feb 16, 2022 IDA-D2130 Loan Disb 32,900.00
Feb 16, 2022 IDA-D2130 Loan Disb 56,916.19
Feb 16, 2022 IDA-D2130 Loan Disb 29,922.62
Feb 16, 2022 IDA-D2130 Loan Disb 70,542.60
Feb 16, 2022 IDA-D2130 Loan Disb 282,827.00
Jun 25, 2021 IDA-D2130 Loan Disb 60,719.99
May 27, 2021 IDA-D2130 Loan Disb -349,439.47
Apr 12, 2021 IDA-D2130 Loan Disb 108,790.00
Apr 21, 2021 IDA-D2130 Loan Disb 69,923.39
Jun 24, 2021 IDA-D2130 Loan Disb 2,218,371.80
Apr 28, 2021 IDA-D2130 Loan Disb 72,220.00
Apr 28, 2020 IDA-D2130 Loan Disb 5,000,000.00
Jul 9, 2020 IDA-D2130 Loan Disb 1,625,578.60
Dec 29, 2020 IDA-D2130 Loan Disb 103,960.00
Dec 15, 2020 IDA-D2130 Loan Disb 425,935.70
Dec 15, 2020 IDA-D2130 Loan Disb 317,975.00
Dec 15, 2020 IDA-D2130 Loan Disb 52,307.89
Dec 15, 2020 IDA-D2130 Loan Disb 151,750.38
Dec 15, 2020 IDA-D2130 Loan Disb 333,500.00
Dec 15, 2020 IDA-D2130 Loan Disb 145,590.00
Dec 29, 2020 IDA-D2130 Loan Disb 656,995.00
Dec 17, 2020 IDA-D2130 Loan Disb 303,025.00
Dec 17, 2020 IDA-D2130 Loan Disb 194,160.81
Dec 17, 2020 IDA-D2130 Loan Disb 98,900.00
Mar 10, 2021 IDA-D2130 Loan Disb 37,014.73
Dec 15, 2020 IDA-D2130 Loan Disb 89,700.00
Dec 15, 2020 IDA-D2130 Loan Disb 342,971.88
Dec 15, 2020 IDA-D2130 Loan Disb 12,085.16
Dec 18, 2020 IDA-D7520 Loan Disb 5,000,000.00
Dec 15, 2020 IDA-D2130 Loan Disb 142,738.25
Dec 15, 2020 IDA-D2130 Loan Disb 284,625.00
Feb 16, 2022 IDA-D2130 Loan Disb 282,942.50
Feb 16, 2022 IDA-D2130 Loan Disb 169,637.52
Feb 16, 2022 IDA-D2130 Loan Disb 9,900.01
Dec 30, 2020 IDA-D2130 Loan Disb -155,278.66
Dec 28, 2020 IDA-D2130 Loan Disb 168,994.73
Dec 28, 2020 IDA-D2130 Loan Disb 440,047.50
Dec 28, 2020 IDA-D2130 Loan Disb 147,545.00
Dec 28, 2020 IDA-D2130 Loan Disb 155,328.66
Dec 28, 2020 IDA-D2130 Loan Disb 516,350.00
Feb 10, 2021 IDA-D7520 Loan Disb 15,000,000.00
Dec 23, 2020 IDA-D2130 Loan Disb -194,110.81
Jun 11, 2021 IDA-D2130 Loan Disb 90,390.00
May 19, 2021 IDA-D2130 Loan Disb 426,573.00
May 19, 2021 IDA-D2130 Loan Disb 287,061.10
May 19, 2021 IDA-D2130 Loan Disb 7,270,991.00
Apr 30, 2021 IDA-D2130 Loan Disb 341,665.00
May 13, 2021 IDA-D2130 Loan Disb 344,139.94
Apr 16, 2021 IDA-D2130 Loan Disb 625,600.00
Apr 16, 2021 IDA-D2130 Loan Disb 269,358.12
Apr 16, 2021 IDA-D2130 Loan Disb 241,154.98
Apr 16, 2021 IDA-D2130 Loan Disb 120,464.49
Apr 1, 2021 IDA-D2130 Loan Disb 112,709.90
Apr 1, 2021 IDA-D2130 Loan Disb 275,507.40
May 25, 2021 IDA-D1390 Loan Disb 1,576,971.60
May 25, 2021 IDA-D2130 Loan Disb 331,565.28
May 25, 2021 IDA-D2130 Loan Disb 349,489.47
Jun 21, 2021 IDA-D1390 Loan Disb 2,461,924.50
Jun 21, 2021 IDA-D1390 Loan Disb 4,518,156.00
Apr 20, 2021 IDA-D2130 Loan Disb 847,550.00
Apr 20, 2021 IDA-D2130 Loan Disb 173,925.00
Jun 16, 2021 IDA-D2130 Loan Disb -90,355.00
Jun 21, 2021 IDA-D2130 Loan Disb 143,751.75
Jun 21, 2021 IDA-D2130 Loan Disb 3,917,158.50
Jun 21, 2021 IDA-D2130 Loan Disb 628,037.40
Jun 23, 2021 IDA-D7520 Loan Disb 3,209,833.50
Apr 16, 2021 IDA-D2130 Loan Disb 86,480.00
May 13, 2021 IDA-D2130 Loan Disb 204,586.61

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2022-10-21
Progress towards achievement of PDO Moderately Satisfactory 2022-10-21
Procurement Moderately Satisfactory 2022-10-21
Counterpart Funding Moderately Unsatisfactory 2022-10-21
Project Management Moderately Satisfactory 2022-10-21
Financial Management Moderately Satisfactory 2022-10-21
Overall Implementation Progress (IP) Moderately Satisfactory 2022-10-21

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-07-2022
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-16-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityHighN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.0013790631.0010000000.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Female beneficiariesValue0.0049.0035.00
    DateJuly 1, 2016October 16, 2018
    Comment
  • Number of CDCs in rural and urban areas able to plan and manage their own development projectsValue0.008264.0010050.00
    DateOctober 1, 2016August 15, 2021December 31, 2022
    Comment
  • Rural CDCs able to plan and manage their own development projectsValue0.007414.009000.00
    DateOctober 1, 2016August 15, 2021December 31, 2022
    Comment
  • Urban CDCs able to plan and manage their own development projectsValue0.00850.001050.00
    DateOctober 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of communities meeting all minimum service standardsValue0.003152.003500.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Rural communities meeting all minimum service standardsValue0.002678.003000.00
    DateOctober 1, 2016August 15, 2021December 31, 2022
    Comment
  • Urban communities meeting all minimum service standardsValue0.00474.00500.00
    DateOctober 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of targeted high IDP/returnee communities provided with emergency supportValue0.002200.002200.00
    DateMay 31, 2017October 31, 2021December 31, 2022
    Comment
  • Number of rural targeted high IDP/returnee communities provided with emergency supportValue0.002000.002000.00
    DateMay 31, 2017October 31, 2021December 31, 2022
    Comment
  • Number of urban targeted high IDP/returnee communities provided with emergency supportValue0.00200.00200.00
    DateMay 31, 2017October 31, 2021December 31, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Rural areas - Number/Type of rural subprojects completed (for water points, roads, irrigation, electricity)Value0.006184.009000.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • % of CDCs initiating activities to benefit marginalized and vulnerable groups such as women, IDPs/returnees (in addition to servicestandards)Value0.0098.0035.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of evaluations and studies completedValue0.006.006.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • % of grievances received which are resolvedValue0.0094.6070.00
    DateOctober 27, 2016August 15, 2021December 31, 2022
    Comment
  • Number of vulnerable households receiving MCCG supportValue0.00115000.00115000.00
    DateMay 31, 2017October 31, 2021December 31, 2022
    Comment
  • Urban areas - Number/type of urban subprojects completed (drainage, streets, street lighting, parks)Value0.001195.00900.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of vulnerable IDP/R households receiving MCCG SupportValue0A total of 21,665 IDP/R households have so far rec
    DateMay 31, 2017
    Comment
  • % of rural CDC cross-visits that include women CDC membersValue0.0086.0040.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • % of sampled community respondents (male/female) satisfied with CDC's performance in their mandated rolesValue0.0073.0060.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of rural and urban CDCs reporting semi-annually on service standard targetsValue0.0012939.009600.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • % of urban CDC cross-visits that include women CDC membersValue0.00100.0070.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of communities in rural areas receiving MCCG grants within 6 months after AF effectiveness/COVID-19 outbreakValue0.00700.00700.00
    DateMay 31, 2017October 31, 2021December 31, 2022
    Comment
  • % of CDC members in rural areas who are womenValue0.0049.6040.00
    DateOctober 27, 2016August 15, 2021December 31, 2022
    Comment
  • Rural areas - Number of people (male/female) benefitting from each type of subproject (access to water, roads, irrigation and electricity)Value0Power supply = 87,485 Irrigation = 2,180,406 TraBased on actual beneficiary counts by sector
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of vulnerable households benefitting from social inclusion grantValue0.0020000.0020000.00
    DateMay 31, 2017October 31, 2021December 31, 2022
    Comment
  • % of CDC members in urban areas who are womenValue0.0049.9345.00
    DateOctober 27, 2016August 15, 2021December 31, 2022
    Comment
  • Urban areas - Number of urban residents (male/female) benefitting from each type of subproject (drainage, streets, street lighting,parks)Value0Power Supply = 73,533Water Supply and Sanitation Based on actual beneficiary counts by sector
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • % of sampled CDCs/communities whose CDPs include at least one women's priority activityValue0.0091.0060.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • % of sampled community respondents (male/female) satisfied with subproject/grant investmentsValue0.0072.0060.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of vulnerable IDP/R households benefitting from social inclusion grantValue0.03,333 HHs
    DateMay 31, 2017
    Comment
  • Number of districts/cities where Citizens' Charter coordination meetings are held between government authorities and CDC clusters/GozarsValue0.00127.00128.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of vulnerable disabled households benefitting from social inclusion grantValue0.00369 disabled HHs have benefitted from the social i
    DateMay 31, 2017
    Comment
  • Number of vulnerable female-headed households benefitting from social inclusion grantValue0.0010000.009000.00
    DateMay 31, 2017October 31, 2021December 31, 2022
    Comment
  • Number of rural districts where Citizens' Charter coordination meetings are held between government authorities and CDC clusters/GozarsValue0.00123.00124.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of cities where Citizens' Charter coordination meetings are held between government authorities and CDC clusters/GozarsValue0.004.004.00
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of government provincial and municipalities whose abilities are strengthened in engineering, project management, FM & procurementValueN/A3838
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of provinces whose abilities are strengthened in engineering, project management, FM and procurementValueN/A3434
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment
  • Number of municipalities whose abilities are strengthened in engineering, project management, FM and procurementValueN/A44
    DateJuly 1, 2016August 15, 2021December 31, 2022
    Comment