Marshall Islands Maritime Investment Project

Abstract*

The development objective of Maritime Investment Project for Marshall Islands is to improve the safety, efficiency and climate resilience of maritime infrastructure and operations in the recipient's territory, and in the event of an eligible crisis or emergency, to provide an immediate response to the eligible crisis or emergency. This project has four components. 1) The first component, Maritime Infrastructure, aims to improve the safety and efficiency...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve the safety, efficiency and climate resilience of maritime infrastructure and operations in the Recipient's territory, and in the event of an Eligible Crisis or Emergency, to provide an immediate response to the Eligible Crisis or Emergency.

Key Details

Project Details

  • P161382

  • Closed

  • Keelye Hanmer , Toufiq Ahmed

  • Republic of the Marshall Islands

  • Marshall Islands

  • February 15, 2018

  • (as of board presentation)

    May 9, 2019

  • July 17, 2019

  • US$ 33.12 million

  • Republic of Marshall Islands Port Authority

  • East Asia and Pacific

  • 2019

  • US$ 33.12 million

  • B

  • April 2, 2024

  • August 1, 2024

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 33.12

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 33.12
IBRD + IDA Commitment 33.12
Lending Instrument
Grant Amount N/A
Total Project Cost** 33.12

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 14, 2022 IDA-D4520 Loan Disb 417,699.34
Dec 20, 2022 IDA-D4520 Loan Disb 299,534.94
Nov 9, 2021 IDA-D4520 Loan Disb 485,506.25
Jul 1, 2020 IDA-D4520 Loan Disb 227,954.78
Mar 16, 2021 IDA-D4520 Loan Disb 498,201.50
Jun 16, 2020 IDA-D4520 Loan Disb 363,467.00
Aug 19, 2019 IDA-D4520 Loan Disb 452,259.40
Sep 19, 2019 IDA-D4520 Loan Disb 500,000.00
Jul 25, 2024 IDA-D4520 Loan Cancel 3,191,764.50
May 9, 2019 IDA-D4520 Loan Commitment 33,120,000.00
Jul 8, 2024 IDA-D4520 Loan Disb 435,756.47
Jan 31, 2024 IDA-D4520 Loan Disb 497,147.60
Jan 31, 2024 IDA-D4520 Loan Disb 257,034.69
Oct 18, 2023 IDA-D4520 Loan Disb 440,128.50
Oct 18, 2023 IDA-D4520 Loan Disb 405,902.34
Oct 18, 2023 IDA-D4520 Loan Disb 499,032.84
Oct 18, 2023 IDA-D4520 Loan Disb 458,358.22
Oct 16, 2023 IDA-D4520 Loan Disb 280,226.38
Sep 28, 2023 IDA-D4520 Loan Disb 251,813.12
Jul 26, 2024 IDA-D4520 Loan Disb 371,702.62
Feb 29, 2024 IDA-D4520 Loan Cancel 16,063,476.00
Mar 18, 2024 IDA-D4520 Loan Disb 428,444.20
Jul 29, 2024 IDA-D4520 Loan Disb 489,388.30
May 8, 2024 IDA-D4520 Loan Disb 374,679.53
Sep 20, 2023 IDA-D4520 Loan Disb 379,812.00
Dec 20, 2022 IDA-D4520 Loan Disb 483,847.12
Dec 20, 2022 IDA-D4520 Loan Disb 495,200.53
May 10, 2022 IDA-D4520 Loan Disb 1,249,441.40

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Unsatisfactory 2024-06-27
Procurement Unsatisfactory 2024-06-27
Financial Management Unsatisfactory 2024-06-27
Overall Safeguards Rating Satisfactory 2024-06-27
Progress towards achievement of PDO Unsatisfactory 2024-06-27
Monitoring and Evaluation Unsatisfactory 2024-06-27
Overall Implementation Progress (IP) Unsatisfactory 2024-06-27

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Reduction in cargo vessel turnaround times at Delap DockValue1660.001660.001630.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Docks rehabilitated with at least one climate resilience measureValue0.000.003.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Project docks fully compliant with ISPS requirementsValue0.000.003.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Increase in container yard productivity at Delap DockValue0.000.0010.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Docks with sectoral and contingency planning tools that address natural disasters and climate changeValue0.003.003.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Grievances registered related to delivery of project benefits that are addressedValue0.000.00100.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Project docks with safety solutions implementedValue0.000.004.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Area of cargo yard paved at Delap DockValue0.000.0030000.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Adoption of a CERC manual given the risk of natural disasterValueNoYesYes
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • People with enhanced access to transportation servicesValue0.000.0042000.00
    DateAugust 1, 2023January 23, 2024August 1, 2024
    Comment
  • ISPS recommendations implemented against identified shortcomingsValue0.000.00100.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Measures implemented to improve drainage at Delap dockValueNoNoYes
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Repairs to the existing berth and facilities at Project docksValue0.000.004.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • RMIPA implementation of SOP on trafficking referral serviceValueNoNoYes
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Energy efficiency recommendations implementedValue0.000.002.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment
  • Percentage of contractor staff trained on GBV & Codes of ConductValue0.0066.00100.00
    DateFebruary 25, 2019January 23, 2024August 1, 2024
    Comment