Dam Operational Improvement and Safety Project Phase 2

Development Objective

The new Project Development Objective is proposed to increase the safety and functionality of dams in selected locations and strengthen the operation and management capacity for dam safety.

Key Details

Project Details

  • P161514

  • Closed

  • Marcus Wishart , Ximing Zhang

  • Ministry of Finance

  • Indonesia

  • January 24, 2017

  • (as of board presentation)

    February 27, 2017

  • N/A

  • US$ 300.00 million

  • Ministry of Public Works and Housing

  • East Asia and Pacific

  • 2017

  • US$ 250.00 million

  • N/A

  • Not Applicable

  • December 31, 2023

  • Yes

  • BANK APPROVED

  • P096532

  • April 22, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 125.00
Asian Infrastructure Investment Bank 125.00
Borrower/Recipient 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 125.00
IDA Commitment N/A
IBRD + IDA Commitment 125.00
Lending Instrument
Grant Amount 125.00
Total Project Cost** 300.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue2.300.0011200000.00
    DateNovember 23, 2016June 30, 2023
    Comment
  • River Basin Organizations (Balai) with need based O&M budget and plan operationalized within a national dam asset management systemValue0.000.0013.00
    DateNovember 23, 2016June 30, 2023
    Comment
  • Issuance of regulation on dam safety (incl. Government/PP, Minister and/or DG Decree on dam safety assurance)Value03
    DateOctober 26, 2016November 11, 2016June 30, 2023
    Commentn/aOne PDO indicator consist of sub indicators that caused difficulty to conclude the achievement of PDO indicator. The O&M subindicator is modified and used as PDO indicator. Other sub-indicators are moved as intermediate indicators.
  • Female beneficiariesValue0.000.0050.00
    DateNovember 23, 2016June 30, 2023
    Comment
  • Overall risk reduction of all dams under projectValue4.000.0020.00
    DateNovember 23, 2016June 30, 2023
    Comment
  • Dams returned to improved operationValue0.000.0074.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • Number of dams with individual hazard reduced by > 20% of risk score.Value16.000.0098.00
    DateNovember 23, 2016June 30, 2023
    Comment
  • Dam portfolio risk assessmentsValue0.0022.0022.00
    DateMay 1, 2009June 2, 2016December 30, 2016
    Comment
  • DGWR Dam Portfolio Management Program establishedValue0.0056.0056.00
    DateMay 1, 2009June 2, 2016December 31, 2016
    Comment
  • DOISP Referable Dam Works and Field Inspection and Certification per DSU Priority PlanValue0.0094.0075.00
    DateMay 1, 2009June 2, 2016December 30, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Dams with emergency action plans updated and disseminatedValue56.000.00140.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • Number of dams with BDSF operationalValue10.000.00140.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • Land area under sustainable landscape management practicesValue10.000.00300.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • Communities joining catchment management activities (% of which female)**Value37.000.0050.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • Dams implementing at least 70% of catchment management activitiesValue0.000.0060.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • Dams providing real time dataValue30.000.0080.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • Dam Technology Center established and operationalizedValue0.000.001.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • INACOLD certification of dam professionalsValue40.000.00240.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • CDMU staff trainedValue0.000.005.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • DSU staff trainedValue0.000.0015.00
    DateDecember 16, 2016June 30, 2023
    Comment
  • Number of dams rehabilitatedValue0.0029.00140.00
    DateMay 1, 2009June 2, 2016June 30, 2023
    Comment
  • Number of 34 priority dams with SEOP operationalValue0.0056.0050.00
    DateMay 1, 2009June 2, 2016July 1, 2015
    Comment
  • Operating staff training took place for 63 dam.Value0.0064.0063.00
    DateMay 1, 2009June 2, 2016December 31, 2016
    Comment
  • Special studies for dams completedValue0.0023.0023.00
    DateMay 1, 2009June 2, 2016December 30, 2016
    Comment
  • O&M Manuals (including related training) for Dams completed.Value0.0051.00140.00
    DateMay 1, 2009June 2, 2016June 30, 2023
    Comment
  • Community-Dam Operator MOUs signed on Greenbelt ManagementValue0.003.0030.00
    DateMay 1, 2009November 23, 2016June 30, 2023
    Comment
  • Household joining catchment management activitiesValue0.0037.0025.00
    DateMay 1, 2009June 2, 2016December 30, 2016
    Comment
  • DOISP Reservoir Survey completedValue0.0031.0030.00
    DateMay 1, 2009June 2, 2016December 30, 2016
    Comment
  • Dam operational staff receiving annual trainingValue0.00100.0090.00
    DateMay 1, 2009June 2, 2016June 30, 2023
    Comment
  • INACOLD certification of Dam ProfessionalValue0.00100.0080.00
    DateMay 1, 2009June 2, 2016December 30, 2016
    Comment