Skip to Main Navigation

Additional Financing Irrigation System Enhancement Project

Development Objective

The PDO is (i) to reduce the amount of energy used and to improve the irrigation conveyance efficiency in targeted irrigation schemes; and (ii) to improve the availability and reliability of important sector data and information for decision makers and other stakeholders.

Key Details

Project Details

  • P161538

  • Closed

  • Wilfried Hundertmark , Arusyak Alaverdyan

  • Ministry of Finance

  • Armenia

  • February 9, 2017

  • (as of board presentation)

    November 14, 2017

  • N/A

  • US$ 2.50 million

  • State Committee of the Water Economy,Water Sector Projects Implementation Unit State Agency

  • Europe and Central Asia

  • 2018

  • US$ 2.00 million

  • B

  • Not Applicable

  • December 31, 2019

  • Yes

  • BANK APPROVED

  • P127759

  • October 12, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 0.50
International Bank for Reconstruction and Development 2.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 2.00
IDA Commitment N/A
IBRD + IDA Commitment 2.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 2.50

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Water losses reduced in rehabilitated canalsValue0.000.7123.58
    DateNovember 30, 2012August 1, 2017June 30, 2019
    CommentIt was monitored by the old indicator. Lost liters per second per 100 meters in the targeted irrigation schemes (to measureimproved conveyance efficiency)
  • Amount of energy saved annually in operating the irrigation systemValue0.0016.5936.80
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Improvement in conveyance efficiency (liters / s / per 100 meters) in the targeted irrigation schemesValue0.000.710.71
    DateNovember 30, 2012August 1, 2017April 30, 2017
    Comment
  • Data about O&M and EM used by SCWM, WSAs and WUAs for decision makingValueNot availableIn progressData used for budgetary and investment planning pu
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Technical audit of irrigation agencies used by MOTA and SCWM for decision makingValueNot AvailableOn-goingData used for budgetary and investment planning pu
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Percentage of WUAs having water intakes tracked by SCWM in real time.Value0.00100.00100.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of Pump Stations shut downValue0.0019.004.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Length of outlet canals receiving water from pumping stations that have been rehabilitatedValue0.0057.2652.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Observation points equipped with Installation of limnographs and water measurement devices for the SCADA systemValue0.0083.0071.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Area provided with irrigation and drainage services (ha)Value0.009326.0012932.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Operational water user associations created and/or strengthened (number)Value0.0014.0037.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Water users provided with new/improved irrigation and drainage services (number)Value0.008286.0012336.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • WUAs staff trainedValue0.00387.00220.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Presence of women in WUAs' executive bodies (excluding water masters)Value4.0041.0010.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Number of site specific ESMPs preparedValue0.004.004.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Area provided with irrigation and drainage services - Improved (ha)Value0.009326.0012932.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • Water users provided with irrigation and drainage services - female (number)Value0.00331.00493.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • WUAs' women staff trained.Value0.0040.0080.00
    DateNovember 30, 2012August 1, 2017June 30, 2019
    Comment
  • % of grievances responded within 5 business daysValue0.000.00100.00
    DateSeptember 14, 2017June 30, 2019
    Comment
  • % beneficiaries who report that their needs have been reflected in project design (disaggregated by gender)Value0.000.0070.00
    DateSeptember 14, 2017June 30, 2019
    Comment