The Disaster Risk Management (DRM) Development Policy Financing with a Catastrophe Deferred Drawdown Option (DPF with Cat DDO), in the amount of Euro 165.4 million (US$200 million equivalent), will support the Government of Kenya’s (GoK) reform program to improve the country’s capacity to reduce disaster risks and improve management of the socioeconomic and fiscal impacts of disasters. The GoK has initiated a shift toward a more proactive approach...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The overall PDO is to strengthen the Government of Kenya’s institutional, technical, and financial capacities to manage the impact of climate and disaster risks.

Key Details

Project Details

  • P161562

  • Closed

  • Eric Dickson , Barry Maher

  • Republic of Kenya

  • Kenya

  • April 23, 2018

  • (as of board presentation)

    June 21, 2018

  • November 27, 2018

  • US$ 200.00 million

  • National Treasury and Ministry of Planning

  • Eastern and Southern Africa

  • 2018

  • US$ 200.00 million

  • N/A

  • September 22, 2022

  • September 30, 2021

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 200.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 200.00
IBRD + IDA Commitment 200.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 200.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 15, 2021 IDA-62600 Int Charges 728,731.75
Aug 15, 2021 IDA-62600 Int Charges 651,000.30
May 19, 2020 IDA-62600 Loan Disb 112,181,912.00
Aug 15, 2020 IDA-62600 Int Charges 443,029.53
Aug 15, 2020 IDA-62600 Int Charges 495,928.60
Aug 15, 2020 IDA-62600 Int Charges 495,928.60
Feb 16, 2021 IDA-62600 Int Charges 754,503.10
Feb 16, 2021 IDA-62600 Int Charges 754,503.10
Feb 16, 2021 IDA-62600 Int Charges 674,022.75
Dec 10, 2019 IDA-62600 Loan Disb 69,955,816.00
Feb 18, 2020 IDA-62600 Int Charges 92,518.24
Feb 18, 2020 IDA-62600 Int Charges 92,518.24
Feb 18, 2020 IDA-62600 Int Charges 82,649.62
Feb 15, 2023 IDA-62600 Int Charges 664,349.75
Feb 15, 2023 IDA-62600 Int Charges 664,349.75
Feb 15, 2022 IDA-62600 Int Charges 703,735.60
Feb 15, 2022 IDA-62600 Int Charges 703,735.60
Feb 15, 2022 IDA-62600 Int Charges 628,670.50
Aug 15, 2022 IDA-62600 Int Charges 632,903.10
Aug 15, 2022 IDA-62600 Int Charges 632,903.10
Aug 15, 2022 IDA-62600 Int Charges 565,393.44
Aug 15, 2021 IDA-62600 Int Charges 728,731.75
Jun 21, 2018 IDA-62600 Loan Commitment 200,000,000.00
Aug 15, 2024 IDA-62600 Int Charges 589,948.10
Aug 15, 2024 IDA-62600 Loan Repay 3,004,875.50
Aug 15, 2024 IDA-62600 Int Charges 660,389.70
Aug 15, 2024 IDA-62600 Int Charges 660,389.70
Feb 15, 2024 IDA-62600 Int Charges 585,055.70
Feb 15, 2024 IDA-62600 Loan Repay 2,929,961.80
Feb 15, 2024 IDA-62600 Int Charges 654,913.00
Feb 15, 2024 IDA-62600 Int Charges 654,913.00
Feb 15, 2023 IDA-62600 Int Charges 593,485.75
Aug 15, 2023 IDA-62600 Loan Repay 2,983,998.00
Aug 15, 2023 IDA-62600 Int Charges 678,181.40
Aug 15, 2023 IDA-62600 Int Charges 678,181.40
Aug 15, 2023 IDA-62600 Int Charges 605,842.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Program Management Moderately Unsatisfactory 2021-11-16
Progress towards achievement of PDO Moderately Unsatisfactory 2021-11-16
Monitoring and Evaluation Moderately Unsatisfactory 2021-11-16
Overall Implementation Progress (IP) Moderately Unsatisfactory 2021-11-16

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-28-2022
OutcomesModerately Unsatisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-28-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Disaster risk profiles produced to inform implementation of County Integrated Development PlansValue0.006.005.00
    DateNovember 27, 2018September 30, 2021September 30, 2021
    Comment
  • Urban resilience strategies prepared to enhance city managementValue0.000.003.00
    DateNovember 27, 2018September 30, 2021September 30, 2021
    Comment
  • Establishment of a national climate finance mechanism to support mobilization, coordination and tracking of climate finance from both internal and external sourcesValueNoNoYes
    DateNovember 27, 2018September 30, 2021September 30, 2021
    Comment
  • County level emergency and/or contingency plans adopted that strengthens response capacityValue0.002.008.00
    DateNovember 27, 2018September 30, 2021September 30, 2021
    Comment
  • New Building Code approved that incorporates multi-hazard resilient design standardsValueNoNoYes
    DateNovember 27, 2018September 30, 2021September 30, 2021
    Comment
  • National Disaster Risk Management Strategy that strengthens government coordination for climate resilience and DRM adoptedValueNoNoYes
    DateNovember 27, 2018September 30, 2021September 30, 2021
    Comment
  • Physical Planning Handbook is revised to incorporate DRM and climate change adaptation considerationsValue0.000.001.00
    DateNovember 27, 2018September 30, 2021September 30, 2021
    Comment
  • Number of households eligible for disaster relief through financial protection instrumentsValue407877.00369024.00510241.00
    DateNovember 27, 2018September 30, 2021September 30, 2021
    Comment
  • National Water Harvesting and Storage Authority established for improved water resource and drought managementValueNoYesYes
    DateNovember 27, 2018September 30, 2021September 30, 2021
    Comment
  • Reports on consolidated post-disaster expenditure produced annually and submitted to the Budget Department within National TreasuryValue0.005.003.00
    DateNovember 27, 2018September 30, 2021September 30, 2021