Financier | Commitments |
---|---|
IDA Credit | 200.00 |
P161562
Closed
Eric Dickson , Barry Maher
Republic of Kenya
April 23, 2018
(as of board presentation)
June 21, 2018
November 27, 2018
US$ 200.00 million
National Treasury and Ministry of Planning
2018
US$ 200.00 million
N/A
September 22, 2022
September 30, 2021
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 200.00 |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2021 | IDA-62600 | Int Charges | 728,731.75 |
Aug 15, 2021 | IDA-62600 | Int Charges | 651,000.30 |
May 19, 2020 | IDA-62600 | Loan Disb | 112,181,912.00 |
Aug 15, 2020 | IDA-62600 | Int Charges | 443,029.53 |
Aug 15, 2020 | IDA-62600 | Int Charges | 495,928.60 |
Aug 15, 2020 | IDA-62600 | Int Charges | 495,928.60 |
Feb 16, 2021 | IDA-62600 | Int Charges | 754,503.10 |
Feb 16, 2021 | IDA-62600 | Int Charges | 754,503.10 |
Feb 16, 2021 | IDA-62600 | Int Charges | 674,022.75 |
Dec 10, 2019 | IDA-62600 | Loan Disb | 69,955,816.00 |
Feb 18, 2020 | IDA-62600 | Int Charges | 92,518.24 |
Feb 18, 2020 | IDA-62600 | Int Charges | 92,518.24 |
Feb 18, 2020 | IDA-62600 | Int Charges | 82,649.62 |
Feb 15, 2023 | IDA-62600 | Int Charges | 664,349.75 |
Feb 15, 2023 | IDA-62600 | Int Charges | 664,349.75 |
Feb 15, 2022 | IDA-62600 | Int Charges | 703,735.60 |
Feb 15, 2022 | IDA-62600 | Int Charges | 703,735.60 |
Feb 15, 2022 | IDA-62600 | Int Charges | 628,670.50 |
Aug 15, 2022 | IDA-62600 | Int Charges | 632,903.10 |
Aug 15, 2022 | IDA-62600 | Int Charges | 632,903.10 |
Aug 15, 2022 | IDA-62600 | Int Charges | 565,393.44 |
Aug 15, 2021 | IDA-62600 | Int Charges | 728,731.75 |
Jun 21, 2018 | IDA-62600 | Loan Commitment | 200,000,000.00 |
Aug 15, 2024 | IDA-62600 | Int Charges | 589,948.10 |
Aug 15, 2024 | IDA-62600 | Loan Repay | 3,004,875.50 |
Aug 15, 2024 | IDA-62600 | Int Charges | 660,389.70 |
Aug 15, 2024 | IDA-62600 | Int Charges | 660,389.70 |
Feb 15, 2024 | IDA-62600 | Int Charges | 585,055.70 |
Feb 15, 2024 | IDA-62600 | Loan Repay | 2,929,961.80 |
Feb 15, 2024 | IDA-62600 | Int Charges | 654,913.00 |
Feb 15, 2024 | IDA-62600 | Int Charges | 654,913.00 |
Feb 15, 2023 | IDA-62600 | Int Charges | 593,485.75 |
Aug 15, 2023 | IDA-62600 | Loan Repay | 2,983,998.00 |
Aug 15, 2023 | IDA-62600 | Int Charges | 678,181.40 |
Aug 15, 2023 | IDA-62600 | Int Charges | 678,181.40 |
Aug 15, 2023 | IDA-62600 | Int Charges | 605,842.00 |
Name | Review | Date |
---|---|---|
Program Management | Moderately Unsatisfactory | 2021-11-16 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2021-11-16 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2021-11-16 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2021-11-16 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-28-2022 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 04-28-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Disaster risk profiles produced to inform implementation of County Integrated Development Plans | Value | 0.00 | 6.00 | 5.00 |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
Urban resilience strategies prepared to enhance city management | Value | 0.00 | 0.00 | 3.00 |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
Establishment of a national climate finance mechanism to support mobilization, coordination and tracking of climate finance from both internal and external sources | Value | No | No | Yes |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
County level emergency and/or contingency plans adopted that strengthens response capacity | Value | 0.00 | 2.00 | 8.00 |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
New Building Code approved that incorporates multi-hazard resilient design standards | Value | No | No | Yes |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
National Disaster Risk Management Strategy that strengthens government coordination for climate resilience and DRM adopted | Value | No | No | Yes |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
Physical Planning Handbook is revised to incorporate DRM and climate change adaptation considerations | Value | 0.00 | 0.00 | 1.00 |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
Number of households eligible for disaster relief through financial protection instruments | Value | 407877.00 | 369024.00 | 510241.00 |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
National Water Harvesting and Storage Authority established for improved water resource and drought management | Value | No | Yes | Yes |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |
Reports on consolidated post-disaster expenditure produced annually and submitted to the Budget Department within National Treasury | Value | 0.00 | 5.00 | 3.00 |
Date | November 27, 2018 | September 30, 2021 | September 30, 2021 | |
Comment |