Sao Tome and Principe Transport Sector Development and Coastal Protection Project

Abstract*

The development objective of the Transport Sector Development and Coastal Protection Project for Sao Tome and Principe is to improve connectivity, sustainability, safety, and climate resilience of selected roads. The project comprises of four components. The first component, road sector institutional strengthening will consolidate the road sector institutional set up and improve road asset management practices with a focus on climate resilience and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed PDOs is to improve connectivity, sustainability, safety and climate resilience of selected roads.

Key Details

Project Details

  • P161842

  • Active

  • Juan Miguel Velasquez , Mustapha Benmaamar

  • Democratic Republic of Sao Tome and Principe,Democratic Republic of Sao Tome and Principe

  • Sao Tome and Principe

  • June 20, 2018

  • (as of board presentation)

    March 22, 2019

  • July 8, 2019

  • US$ 29.00 million

  • AFAP (Agência Fiduciária de Administração de Projectos),AFAP (Agência Fiduciária de Administração de Projectos),INAE (Instituto Nacional de Estradas),INAE (Instituto Nacional de Estradas)

  • Eastern and Southern Africa

  • 2019

  • US$ 29.00 million

  • B

  • Not Applicable

  • June 30, 2027

  • Yes

  • Bank Approved

  • June 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 29.00
IDA Grant 29.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 29.00
IBRD + IDA Commitment 29.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 29.00

Summary Status of World Bank Financing (US$ Millions) as of October 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of October 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2025-05-15
Financial Management Satisfactory 2025-05-15
Monitoring and Evaluation Moderately Satisfactory 2025-05-15
Monitoring and Evaluation Moderately Satisfactory 2025-05-15
Overall Implementation Progress (IP) Moderately Satisfactory 2025-05-15
Overall Implementation Progress (IP) Moderately Satisfactory 2025-05-15
Procurement Moderately Satisfactory 2025-05-15
Procurement Moderately Satisfactory 2025-05-15
Progress towards achievement of PDO Moderately Satisfactory 2025-05-15
Progress towards achievement of PDO Moderately Satisfactory 2025-05-15
Project Management Moderately Satisfactory 2025-05-15
Project Management Moderately Satisfactory 2025-05-15

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average travel time to go from São Tome to Guadalupe by carValue19.0017.0017.00
    DateJanuary 1, 2019June 27, 2023December 29, 2023
    Comment
  • Average travel time to go from São Tome to Guadalupe by carValue19.0017.0017.00
    DateJanuary 1, 2019June 27, 2023December 29, 2023
    Comment
  • Length of roads made resilient to climate and disaster riskValue13.300.0013.30
    DateJune 27, 2023May 9, 2019December 29, 2023
    Comment
  • Length of roads made resilient to climate and disaster riskValue13.300.0013.30
    DateJune 27, 2023May 9, 2019December 29, 2023
    Comment
  • Percentage of road accident black spots corrected based on the number of small-scale road safety interventions on the road networkValue0.000.0050.00
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Percentage of road accident black spots corrected based on the number of small-scale road safety interventions on the road networkValue0.000.0050.00
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Reduction in vehicle operating cost on the project road section for cars per kmValue0.330.330.29
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Reduction in vehicle operating cost on the project road section for cars per kmValue0.330.330.29
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Road asset management system developed and implemented to inform the annual road maintenance programValueNoNoYes
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Road asset management system developed and implemented to inform the annual road maintenance programValueNoNoYes
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Vehicle operating cost on the project road section for trucks per kmValue0.900.900.76
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Vehicle operating cost on the project road section for trucks per kmValue0.900.900.76
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Adequate equipment used for traffic surveys and road asset inventory conditionsValueNoNoYes
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Adequate equipment used for traffic surveys and road asset inventory conditionsValueNoNoYes
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Climate resilience design guidance manual prepared and pilotedValueNoNoYes
    DateJuly 25, 2019May 9, 2019December 31, 2023
    Comment
  • Climate resilience design guidance manual prepared and pilotedValueNoNoYes
    DateJuly 25, 2019May 9, 2019December 31, 2023
    Comment
  • Climate vulnerability assessment developed and used to inform maintenance and future investment strategiesValueNoYesYes
    DateJanuary 1, 2019December 31, 2023December 29, 2023
    Comment
  • Climate vulnerability assessment developed and used to inform maintenance and future investment strategiesValueNoYesYes
    DateJanuary 1, 2019December 31, 2023December 29, 2023
    Comment
  • Grievances responded an/or resolved within the stipulated service standardsValue0.000.00100.00
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Grievances responded an/or resolved within the stipulated service standardsValue0.000.00100.00
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Length of road with drainage condition improved (with construction of new channel or new and upgraded drainage outfall channels)Value13.3013.3013.30
    DateJune 27, 2023December 29, 2023December 29, 2023
    Comment
  • Length of road with drainage condition improved (with construction of new channel or new and upgraded drainage outfall channels)Value13.3013.3013.30
    DateJune 27, 2023December 29, 2023December 29, 2023
    Comment
  • Number of maintenance community groups trained to use innovative techniques (including using eco-system based appraoches) for road maintenance and stabilization and coastal protectionValue0.000.0030.00
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Number of maintenance community groups trained to use innovative techniques (including using eco-system based appraoches) for road maintenance and stabilization and coastal protectionValue0.000.0030.00
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Number of small scale interventions piloted to increase resilience of the road networkValue0.000.0010.00
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Number of small scale interventions piloted to increase resilience of the road networkValue0.000.0010.00
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • People with enhanced access to transportation servicesValue0.0098800.0098800.00
    DateDecember 1, 2019September 26, 2023June 30, 2024
    Comment
  • People with enhanced access to transportation servicesValue0.0098800.0098800.00
    DateDecember 1, 2019September 26, 2023June 30, 2024
    Comment
  • People with enhanced access to transportation services - Roads/HighwaysValue0.0098800.0098800.00
    DateDecember 1, 2019September 26, 2023June 30, 2024
    Comment
  • People with enhanced access to transportation services - Roads/HighwaysValue0.0098800.0098800.00
    DateDecember 1, 2019September 26, 2023June 30, 2024
    Comment
  • Percentage of women among the members of GIMEs being trained (including on time and project management) to provide better job opportunitiesValue0.000.000.00
    Date
    Comment
  • Percentage of women among the members of GIMEs being trained (including on time and project management) to provide better job opportunitiesValue0.000.000.00
    Date
    Comment
  • Road Safety Strategy prepared, and start of implementation of its action planValueNoNoYes
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Road Safety Strategy prepared, and start of implementation of its action planValueNoNoYes
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Roads rehabilitated - non-ruralValue0.000.007.05
    DateJanuary 1, 2019December 29, 2023
    Comment
  • Roads rehabilitated - non-ruralValue0.000.007.05
    DateJanuary 1, 2019December 29, 2023
    Comment
  • Roads rehabilitated - ruralValue0.000.006.25
    DateJanuary 1, 2019December 29, 2023
    Comment
  • Roads rehabilitated - ruralValue0.000.006.25
    DateJanuary 1, 2019December 29, 2023
    Comment
  • Roads rehablitatedValue0.0013.3013.30
    DateJanuary 1, 2019December 29, 2023December 29, 2023
    Comment
  • Roads rehablitatedValue0.0013.3013.30
    DateJanuary 1, 2019December 29, 2023December 29, 2023
    Comment
  • Share of GIME management positions held by women (Managers, Brigade Leader and Treasurers)Value16.0016.0032.00
    DateMay 21, 2019May 21, 2019June 30, 2024
    Comment
  • Share of GIME management positions held by women (Managers, Brigade Leader and Treasurers)Value16.0016.0032.00
    DateMay 21, 2019May 21, 2019June 30, 2024
    Comment
  • Total length of sidewalks built or rehabilitatedValue0.0012.0014.40
    DateJanuary 1, 2019June 27, 2023December 29, 2023
    Comment
  • Total length of sidewalks built or rehabilitatedValue0.0012.0014.40
    DateJanuary 1, 2019June 27, 2023December 29, 2023
    Comment
  • Updated road asset management system in place and implemented to prepare road maintenance programsValueNoNoYes
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment
  • Updated road asset management system in place and implemented to prepare road maintenance programsValueNoNoYes
    DateJanuary 1, 2019May 9, 2019December 29, 2023
    Comment