P162022
Active
Hung Tran , Gunjan Gautam
Islamic Republic of Afghanistan
May 5, 2017
(as of board presentation)
June 13, 2017
October 18, 2017
US$ 60.00 million
Da Afghanistan Breshna Sherkat (DABS)
2017
US$ 60.00 million
B
Not Applicable
June 30, 2026
Yes
BANK APPROVED
April 17, 2023
| Financier | Commitments | 
|---|---|
| IDA Grant | 60.00 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | N/A | 
| IDA Commitment | 60.00 | 
| IBRD + IDA Commitment | 60.00 | 
| Lending Instrument | |
|---|---|
| Grant Amount | N/A | 
| Total Project Cost** | 60.00 | 
| Period | Financier | Transaction Type | Amount (US$) | 
|---|---|---|---|
| Jun 13, 2017 | IDA-D2080 | Loan Commitment | 60,000,000.00 | 
| Dec 3, 2020 | IDA-D2080 | Loan Disb | 1,357,996.40 | 
| Dec 3, 2020 | IDA-D2080 | Loan Disb | 3,000,000.00 | 
| Jun 8, 2021 | IDA-D2080 | Loan Disb | 3,731,207.20 | 
| Jun 13, 2019 | IDA-D2080 | Loan Disb | 1,479,324.60 | 
| Dec 16, 2019 | IDA-D2080 | Loan Disb | 3,217,458.20 | 
| Nov 13, 2017 | IDA-D2080 | Loan Disb | 5,000,000.00 | 
| Jun 29, 2018 | IDA-D2080 | Loan Disb | 347,629.00 | 
| Feb 22, 2019 | IDA-D2080 | Loan Disb | 2,146,522.00 | 
| Oct 13, 2020 | IDA-D2080 | Loan Disb | 1,427,944.20 | 
| Name | Review | Date | 
|---|---|---|
| Progress towards achievement of PDO | Moderately Satisfactory | 2022-10-23 | 
| Financial Management | Moderately Satisfactory | 2022-10-23 | 
| Overall Implementation Progress (IP) | Moderately Satisfactory | 2022-10-23 | 
| Monitoring and Evaluation | Satisfactory | 2022-10-23 | 
| Overall Safeguards Rating | Moderately Satisfactory | 2022-10-23 | 
| Procurement | Moderately Satisfactory | 2022-10-23 | 
| Project Management | Moderately Satisfactory | 2022-10-23 | 
| INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 04-14-2023 | 
|---|---|
| Outcomes | Moderately Unsatisfactory | 
| Risk to Development Outcome | |
| Bank Performance | Moderately Satisfactory | 
| Borrower Performance | |
| Government Performance | |
| Implementing Agency | 
| INDICATOR | ICR REVIEW: 08-30-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: | 
|---|---|---|
| Outcome Rating | Moderately Unsatisfactory | N/a | 
| Risk To Development Outcome | N/a | |
| Bank Performance | Moderately Satisfactory | N/a | 
| Borrower Performance | N/a | |
| Government Performance | N/a | |
| Implementing Agency | N/a | |
| Icr Quality | Substantial | N/a | 
| M&e Quality | Substantial | N/a | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| People provided with new or improved electricity service | Value | 0.00 | 230800.00 | 180000.00 | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Number of non-residential consumers provided with new or improved electricity service | Value | 0.00 | 1600.00 | 1600.00 | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Number of girl schools with electricity service | Value | 0.00 | 5.00 | 5.00 | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Awareness campaigns targeted to women on uses of electricity and safety aspects | Value | No | Yes | Yes | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Percentage of grievances satisfactorily resolved within stipulated timeframe | Value | 0.00 | 60.00 | 60.00 | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Percentage of CDCs consulted on project activities affecting them in the project intervention areas | Value | 0.00 | 100.00 | 100.00 | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Transmission line constructed under the Project | Value | 0.00 | 25.00 | 25.00 | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Additional distribution grid asset created | Value | No | Yes | Yes | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Grid code prepared | Value | No | Yes | Yes | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Capacity of new substations constructed and commissioned | Value | 0.00 | 40000.00 | 40000.00 | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Off-grid pilots implemented | Value | No | Yes | Yes | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment | 
| Grid extension study prepared | Value | No | Yes | Yes | 
| Date | June 1, 2017 | January 31, 2023 | June 30, 2022 | |
| Comment |