The Project Development Objective (PDO) is to improve the oversight of the revenues from the extractive industry in targeted countries. This will lead to a more inclusive and sustainable economic growth stemming from extractive industry activities

Key Details

Project Details

  • P162380

  • Closed

  • Adjalou Celestin Niamien

  • CREFIAF

  • Africa

  • December 12, 2016

  • (as of board presentation)

    March 7, 2017

  • March 28, 2017

  • US$ 0.50 million

  • CREFIAF

  • Africa

  • 2017

  • US$ 0.50 million

  • C

  • Not Applicable

  • June 30, 2019

  • BANK APPROVED

  • July 12, 2022

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Supreme Audit Institutions Capacity Development Fund 0.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 0.50
Total Project Cost** 0.50

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Moderable 2019-06-27
Progress towards achievement of PDO Satisfactory 2019-06-27
Overall Implementation Progress (IP) Satisfactory 2019-06-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 02-20-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Auditors (of which female) trained in the audit of revenue of the extractive industry revenueValue0.0080.00190.00
    DateFebruary 24, 2017June 30, 2019June 30, 2019
    Comment
  • Report issued by SAI on audit of the revenue of the extractive industryValue0.008.008.00
    DateFebruary 24, 2017June 30, 2019June 30, 2019
    Comment
  • Time elapsed between the end of the audit and the publication of the reportValue0.006.001.00
    DateFebruary 24, 2017June 30, 2019June 30, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • A manual of audit on control of flow of revenues of the extractive industry is developedValueNOYESYES
    DateFebruary 24, 2017June 30, 2019June 30, 2019
    Comment
  • Training sessions conducted on the audit manualValue0.008.0015.00
    DateFebruary 24, 2017June 30, 2019June 30, 2019
    Comment
  • Coaching/mentoring missions on the audit of revenue flowsValue0.008.0016.00
    DateFebruary 24, 2017June 30, 2019June 30, 2019
    Comment
  • Audit work programs are adopted before conducting the audit mission and issuing the audit reportValueNoYesYes
    DateFebruary 24, 2017June 30, 2019June 30, 2019
    Comment