Abstract*

The development objective of the Land Administration Project for Liberia is to strengthen the institutional capacity of the Liberia land authority (LLA) and establish a land administration system. The project comprises of four components. The first component is support to the Liberia land authority. With the passage of the LLA act by the legislature in October 2016, the LLA has the legal mandate for land administration in Liberia. Even though the...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to strengthen the institutional capacity of the Liberia Land Authority and establish a land administration system.

Key Details

Project Details

  • P162893

  • Closed

  • Linus Pott , Victoria Stanley

  • Ministry of Finance and Development Planning

  • Liberia

  • May 9, 2017

  • (as of board presentation)

    September 28, 2017

  • March 22, 2018

  • US$ 7.00 million

  • B

  • October 24, 2023

  • January 31, 2023

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 7.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 7.00
IBRD + IDA Commitment 7.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 7.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 30, 2018 IDA-D2370 Loan Disb 428,203.03
Sep 8, 2020 IDA-D2370 Loan Disb 354,355.16
Sep 8, 2022 IDA-D2370 Loan Disb 337,204.62
Oct 31, 2022 IDA-D2370 Loan Disb 88,154.28
Apr 8, 2021 IDA-D2370 Loan Disb 415,109.12
May 11, 2018 IDA-D2370 Loan Disb 499,716.47
Jan 28, 2022 IDA-D2370 Loan Disb 444,371.66
Nov 1, 2018 IDA-D2370 Loan Disb 149,856.34
Mar 26, 2019 IDA-D2370 Loan Disb 227,573.94
Apr 1, 2019 IDA-D2370 Loan Disb 409,955.38
Oct 18, 2019 IDA-D2370 Loan Disb 117,353.11
May 25, 2022 IDA-D2370 Loan Disb 407,207.03
Jul 8, 2022 IDA-D2370 Loan Disb 437,027.62
Aug 22, 2019 IDA-D2370 Loan Disb 129,128.49
Dec 2, 2020 IDA-D2370 Loan Disb 311,233.25
Feb 3, 2020 IDA-D2370 Loan Disb 241,656.17
Sep 28, 2017 IDA-D2370 Loan Commitment 7,000,000.00
Apr 14, 2022 IDA-D2370 Loan Disb 355,100.40
Nov 2, 2021 IDA-D2370 Loan Disb -34,477.01
Nov 19, 2021 IDA-D2370 Loan Disb 460,312.38
Sep 3, 2021 IDA-D2370 Loan Disb 485,339.94
Jun 10, 2021 IDA-D2370 Loan Disb 404,830.70
Jun 17, 2020 IDA-D2370 Loan Disb 271,695.53
Jun 30, 2018 IDA-D2370 Loan Disb 283.52

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2023-01-29
Project Management Moderately Satisfactory 2023-01-29
Progress towards achievement of PDO Moderately Satisfactory 2023-01-29
Procurement Moderately Satisfactory 2023-01-29
Financial Management Moderately Satisfactory 2023-01-29
Monitoring and Evaluation Moderately Satisfactory 2023-01-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 07-07-2023
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-27-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • LLA departments are functional, with managers and minimum technical staff in placeValueNoYes
    DateMarch 30, 2017October 31, 2022
    Comment
  • Policy and processes for identification and recording of customary land rights developed and adoptedValueNoYes
    DateMarch 30, 2017January 31, 2023
    Comment
  • System for recording and managing land rights information establishedValueNoYes
    DateMarch 30, 2017January 31, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of Community Land Development Management Committees established disaggregated by men, women, youthsValue04
    DateFebruary 6, 2020January 31, 2023
    Comment
  • Number of national land laws developed and regulations adoptedValue02
    DateMay 1, 2017January 31, 2023
    Comment
  • Project M&E system developed and functionalValueNoYes
    DateMay 1, 2017January 31, 2023
    Comment
  • Network of geodetic and survey control points established and functionalValueNoYes
    DateMay 1, 2017January 31, 2023
    Comment
  • Gender-sensitive upscaling strategy for systematic registration of customary land rights developedValueNoYes
    DateFebruary 6, 2020January 31, 2023
    Comment
  • Increase of capacities of LLA staff in land related disciplinesValue50%71%
    DateMay 17, 2017January 31, 2023
    Comment
  • Number of decentralized LLA offices established and operationalValue055
    DateMay 1, 2017January 31, 2023April 14, 2020
    Comment
  • Number of communities surveyed and registered based on gender-sensitive community by-lawsValue04
    DateFebruary 6, 2020January 31, 2023
    Comment
  • Number of staff trained in land related disciplines, disaggregated by genderValue0429 staff trained (330 male; 99 female)
    DateMay 1, 2017January 31, 2023
    Comment
  • Number of total training daysValue0
    DateMay 1, 2017January 12, 2018
    Comment
  • Number of training certificates issued, disaggregated by genderValue0
    DateMay 1, 2017January 12, 2018
    Comment
  • Increase of awareness of general public and Government entities about LLA and its mandatesValue32%51.2%
    DateMay 1, 2017January 31, 2023
    Comment
  • Number of business plans developed and administrative procedures adoptedValue010 (1 business plan; 9 administrative procedures)
    DateMay 10, 2017January 31, 2023
    Comment
  • Grievance Redress Mechanism established and reported on regularlyValueNoYes
    DateJune 12, 2017January 31, 2023
    Comment
  • System, capacities and budget for maintenance of geodetic network in placeValueNoNo
    DateMay 10, 2017January 31, 2023
    Comment