Climate Resilient Agriculture and Productivity Enhancement Project

Abstract*

The project consists of four components, namely: (a) First component, Institutional support for sustainable agriculture development and climate resilience is designed to strengthen institutional capacities for agricultural research and development (AR&D) and climate change adaptation at national level. The component includes three sub-components: (i) Strengthening the agricultural research and development system; (ii) Strengthening of national support...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed Project Development Objective (PDO) is to “to promote the adoption of improved technologies leading to increased productivity and to enhance the climate resilience of agricultural production systems in the areas targeted by the Project”.

Key Details

Project Details

  • P162956

  • Closed

  • Elisee Ouedraogo

  • Republic of Chad

  • Chad

  • March 2, 2018

  • (as of board presentation)

    April 30, 2018

  • November 30, 2018

  • US$ 44.60 million

  • Ministry of Agricultural Production and Transformation,West and Central African Council for Agricultural Research and Development (CORAF/WECARD)

  • Western and Central Africa

  • 2018

  • US$ 41.00 million

  • B

  • November 14, 2024

  • December 31, 2023

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Local Beneficiaries 1.82
IDA Grant 41.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 41.00
IBRD + IDA Commitment 41.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 44.60

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 29, 2023 IDA-D8060 Loan Disb 402,896.38
Nov 29, 2023 IDA-D8060 Loan Disb 817,808.60
Jun 12, 2023 IDA-D3020 Loan Disb -1,640,580.00
Aug 4, 2023 IDA-D8060 Loan Disb 370,290.25
Jun 23, 2023 IDA-D8060 Loan Disb 174,352.06
Jun 12, 2023 IDA-D8060 Loan Disb 1,640,580.00
Jun 23, 2023 IDA-D8060 Loan Disb 194,192.55
Aug 10, 2023 IDA-D8060 Loan Disb 395,229.03
Aug 10, 2023 IDA-D8060 Loan Disb 207,792.38
Sep 12, 2023 IDA-D8060 Loan Disb 214,756.72
Aug 28, 2023 IDA-D8060 Loan Disb 264,860.72
Feb 2, 2023 IDA-D3020 Loan Disb 374,657.56
Feb 2, 2023 IDA-D3020 Loan Disb 716,207.50
Apr 28, 2023 IDA-D3020 Loan Disb 342,402.06
Apr 25, 2023 IDA-D3020 Loan Disb 563,773.25
May 9, 2023 IDA-D3020 Loan Disb -752,633.90
May 9, 2023 IDA-D8060 Loan Disb 752,633.90
Feb 28, 2023 IDA-D3020 Loan Disb 290,716.72
Dec 13, 2022 IDA-D3020 Loan Disb 343,726.88
Nov 3, 2022 IDA-D3020 Loan Disb 418,907.38
Mar 29, 2023 IDA-D3020 Loan Disb 379,701.60
Sep 6, 2022 IDA-D3020 Loan Disb 367,155.25
Dec 30, 2022 IDA-D3020 Loan Disb 328,007.00
Oct 11, 2022 IDA-D3020 Loan Disb 606,000.60
May 10, 2022 IDA-D3020 Loan Disb 194,904.16
Aug 11, 2022 IDA-D3020 Loan Disb 473,373.56
Feb 2, 2022 IDA-D3020 Loan Disb 545,707.60
Dec 23, 2021 IDA-D3020 Loan Disb 488,456.34
Jun 2, 2022 IDA-D3020 Loan Disb 515,048.00
Feb 18, 2022 IDA-D3020 Loan Disb 470,692.97
Apr 7, 2022 IDA-D3020 Loan Disb 347,831.40
Jul 13, 2022 IDA-D3020 Loan Disb 447,719.53
Oct 15, 2021 IDA-D3020 Loan Disb 466,608.78
Nov 10, 2021 IDA-D3020 Loan Disb 398,374.75
Oct 13, 2021 IDA-D3020 Loan Disb 337,293.94
Aug 31, 2021 IDA-D3020 Loan Disb 287,215.88
Jul 20, 2021 IDA-D3020 Loan Disb 162,182.81
Jul 20, 2021 IDA-D3020 Loan Disb 493,403.90
Sep 8, 2021 IDA-D3020 Loan Disb 406,259.16
Aug 11, 2021 IDA-D3020 Loan Disb 148,783.69
Jan 15, 2021 IDA-D3020 Loan Disb 2,700,000.00
Dec 3, 2020 IDA-D3020 Loan Disb 149,872.20
Jan 22, 2021 IDA-D3020 Loan Disb 237,961.10
Jan 11, 2021 IDA-D3020 Loan Disb 293,106.80
Mar 19, 2021 IDA-D3020 Loan Disb 435,512.53
Jul 27, 2021 IDA-D3020 Loan Disb 258,213.94
Apr 7, 2021 IDA-D3020 Loan Disb 1,500,000.00
Apr 27, 2020 IDA-D3020 Loan Disb 175,199.84
May 19, 2020 IDA-D3020 Loan Disb 282,301.75
Jul 1, 2020 IDA-D3020 Loan Disb 6,500,000.00
Jun 15, 2020 IDA-D3020 Loan Disb 171,175.44
Jun 29, 2020 IDA-D3020 Loan Disb 7,000,000.00
Sep 28, 2020 IDA-D3020 Loan Disb 217,646.12
Oct 6, 2020 IDA-D3020 Loan Disb 163,046.03
Jul 31, 2020 IDA-D3020 Loan Disb 210,839.02
Nov 4, 2020 IDA-D3020 Loan Disb 501,549.12
Nov 4, 2020 IDA-D3020 Loan Disb 400,552.25
Mar 1, 2021 IDA-D3020 Loan Disb 314,130.10
Nov 30, 2018 IDA-D3020 Loan Disb 910,385.00
Feb 15, 2019 IDA-D3020 Loan Disb 1,211,701.60
May 8, 2019 IDA-D3020 Loan Disb 320,518.75
Jun 11, 2019 IDA-D3020 Loan Disb 282,595.38
Oct 24, 2019 IDA-D3020 Loan Disb 352,064.53
Oct 28, 2019 IDA-D3020 Loan Disb 214,186.95
Oct 28, 2019 IDA-D3020 Loan Disb 192,493.56
Dec 5, 2019 IDA-D3020 Loan Disb 354,561.03
Mar 23, 2020 IDA-D3020 Loan Disb 251,598.88
Mar 23, 2020 IDA-D3020 Loan Disb 194,249.10
Jan 7, 2020 IDA-D3020 Loan Disb 278,721.38
Apr 30, 2018 IDA-D3020 Loan Commitment 41,000,000.00
Aug 6, 2021 IDA-D8060 Loan Commitment 15,000,000.00
May 3, 2024 IDA-D8060 Loan Disb 1,637,465.20
Nov 15, 2023 IDA-D8060 Loan Disb 1,634,788.20
Nov 6, 2023 IDA-D8060 Loan Disb 339,194.40
Nov 6, 2023 IDA-D8060 Loan Disb 415,072.62
Nov 29, 2023 IDA-D3020 Loan Disb 107,681.41
Oct 11, 2023 IDA-D8060 Loan Disb 434,804.50
Nov 10, 2023 IDA-D8060 Loan Disb 312,398.78
Nov 30, 2023 IDA-D3020 Loan Disb 79,423.47
Dec 27, 2023 IDA-D8060 Loan Disb 1,686,767.20
Jan 11, 2024 IDA-D8060 Loan Disb 533,191.56
Jan 11, 2024 IDA-D8060 Loan Disb 392,104.88
Nov 29, 2023 IDA-D8060 Loan Disb 411,824.84

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Moderately Satisfactory 2023-12-22
Counterpart Funding Satisfactory 2023-12-22
Project Management Satisfactory 2023-12-22
Progress towards achievement of PDO Satisfactory 2023-12-22
Monitoring and Evaluation Satisfactory 2023-12-22
Overall Implementation Progress (IP) Satisfactory 2023-12-22
Procurement Satisfactory 2023-12-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-27-2024
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-29-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Farmers reached with agricultural assets or servicesValue0.00685286.00360000.00
    DateJanuary 1, 2018December 31, 2023June 30, 2023
    Comment
  • Percentage increase in average agriculture yield of direct beneficiaries compared to average yields in the Project areaValue0.0030.5010.00
    DateJanuary 1, 2018December 31, 2023December 31, 2022
    Comment
  • Share of targeted beneficiaries with rating ‘Satisfied’ or above on project interventionsValue0.0078.0060.00
    DateJanuary 1, 2018December 31, 2023December 31, 2021
    Comment
  • Farmers reached with agricultural assets or services - FemaleValue0.000.0030000.00
    DateJanuary 1, 2018
    Comment
  • Share of targeted female beneficiaries with rating ‘Satisfied’ or above on project interventionsValue0.0079.0070.00
    DateJanuary 1, 2018December 31, 2023December 31, 2021
    Comment
  • Surface area under improved technology disseminated by the ProjectValue0.0068483.0040000.00
    DateJanuary 1, 2018December 31, 2023April 30, 2023
    Comment
  • Surface area under Climate-smart Agriculture technolgies/practicesValue0.000.001000.00
    DateJanuary 1, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Operational regional innovation platformsValue0.009.009.00
    DateJanuary 1, 2018December 31, 2023December 31, 2022
    Comment
  • Annual audits submitted on time and without major qualificationValue0.004.002.00
    DateJanuary 1, 2018April 30, 2024
    Comment
  • Young researchers trainedValue0.0015.0016.00
    DateJanuary 1, 2018December 31, 2023April 30, 2023
    Comment
  • Time required for the government to make requested funds available for an eligible crisis or emergencyValue0.004.004.00
    DateJanuary 1, 2018December 31, 2023
    Comment
  • Direct beneficiaries using agricultural climate servicesValue0.0095.0030.00
    DateJanuary 1, 2018December 31, 2023December 31, 2022
    Comment
  • Grievance Resolution Mechanism established and operationalValueNoYesYes
    DateJanuary 1, 2018December 31, 2023
    Comment
  • Beneficiaries that received emergency food assistanceValue0.00194952.000.00
    DateAugust 3, 2020December 31, 2023
    Comment
  • Young researchers trained - femaleValue0.000.0025.00
    DateJanuary 1, 2018October 2, 2018
    Comment
  • Improved seeds produced by the targeted beneficiariesValue0.001117.00850.00
    DateJanuary 1, 2018December 31, 2023April 30, 2023
    Comment
  • Technical audit report for matching grants funded sub-projectsValue0.002.001.00
    DateFebruary 21, 2018December 31, 2023
    Comment
  • Quantity of foundation seeds produced - cerealsValue0.00122.4022.00
    DateJanuary 1, 2018December 31, 2023
    Comment
  • Small holder farmers provided with improved seeds and small agricultural equipmentValue0.0020000.000.00
    DateAugust 3, 2020December 31, 2023
    Comment
  • Number of sub-projects to intensify sustainable production systemsValue0.002080.00600.00
    DateJanuary 1, 2018December 31, 2023December 31, 2020
    Comment
  • Quantity of foundation seeds - other cropsValue0.000.008.00
    DateJanuary 1, 2018October 2, 2018
    Comment
  • Number of diversification sub-projects supportedValue0.00179.0060.00
    DateJanuary 1, 2018December 31, 2023
    Comment
  • Improved technologies disseminated by the projectValue0.0021.0015.00
    DateJanuary 1, 2018December 31, 2023December 31, 2022
    Comment
  • Number of CSA sub-projectsValue0.0045.0050.00
    DateJanuary 1, 2018December 31, 2023April 30, 2023
    Comment
  • Agriculture sector reform/ policies & strategies supportedValue0.004.004.00
    DateJanuary 1, 2018December 31, 2023April 30, 2023
    Comment
  • Total beneficiaries who participated in Cash for Work rotations (IOM)Value0.0012367.000.00
    DateMarch 9, 2020December 31, 2023
    Comment
  • Productive assets rehabilitated (IOM)Value0.0025.000.00
    DateMarch 9, 2020December 31, 2023
    Comment
  • People trained (IOM)Value0.005201.000.00
    DateMarch 9, 2020December 31, 2023
    Comment