Suriname Extractive Industries Technical Assistance RE

Development Objective

The development objective is to support Suriname's participation in the Extractive Industries Transparency Initiative (EITI) towards more transparent and efficient management of its mining and oil sectors.

Key Details

Project Details

  • P163612

  • Closed

  • Susana Moreira

  • Ministry of Finance

  • Suriname

  • August 9, 2017

  • (as of board presentation)

    December 6, 2017

  • March 2, 2018

  • US$ 0.35 million

  • C

  • Not Applicable

  • September 30, 2020

  • Yes

  • BANK APPROVED

  • October 16, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Extractives Global Programmatic Support 0.35

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 0.35
Total Project Cost** 0.35

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2020-03-23
Overall Moderable 2020-03-23
Overall Implementation Progress (IP) Satisfactory 2020-03-23

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-07-2022
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Annual publication of reconciled information on extractive industries’ revenuesValueNoYesYes
    DateAugust 31, 2017September 30, 2020September 30, 2020
    Comment
  • Citizen engagement in accountability and governance of extractive industriesValueNoYesYes
    DateJune 30, 2017September 30, 2020September 30, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Completion and documentation of MSG meetingsValue0.0020.0051.00
    DateJune 30, 2017September 30, 2020September 30, 2020
    Comment
  • Number of Secretariat staff and Stakholders completing trainingValue0.00100.0041.00
    DateJune 30, 2017September 30, 2020September 30, 2020
    Comment
  • Number of outreach events, including in the interiorValue0.0010.004.00
    DateJune 30, 2017September 30, 2020September 30, 2020
    Comment