Lao National Road 13 Improvement and Maintenance

Development Objective

To improve the road condition, safety and climate resilience on critical sections of National Road 13.

Key Details

Project Details

  • P163730

  • Active

  • Sombath Southivong , Chanin Manopiniwes

  • Lao People's Democratic Republic

  • US$ 128.00 million

  • Ministry of Public Works and Transport

  • East Asia and Pacific

  • 2018

  • US$ 89.50 million

  • A

  • February 28, 2024

  • March 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Asian Infrastructure Investment Bank 40.00
IDA Credit 40.00
Borrower/Recipient 38.50
Nordic Development Fund (NDF) 9.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 40.00
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount 49.50
Total Project Cost** 128.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 17, 2022 IDA-62260 Int Charges 1,690.00
May 17, 2022 IDA-62260 Int Charges 28,610.30
May 17, 2022 IDA-62260 Int Charges 28,610.30
May 17, 2022 IDA-62260 Int Charges 47,683.83
Feb 15, 2022 IDA-62260 Loan Disb 1,026,816.56
Feb 15, 2022 IDA-62260 Loan Disb 338,383.25
Nov 28, 2022 IDA-62260 Loan Disb 510,563.94
Nov 15, 2022 IDA-62260 Int Charges 2,346.45
Nov 15, 2022 IDA-62260 Int Charges 2,346.45
Nov 15, 2022 IDA-62260 Int Charges 46,981.01
Nov 15, 2022 IDA-62260 Int Charges 46,981.01
Nov 15, 2022 IDA-62260 Int Charges 77,652.13
Dec 19, 2022 IDA-62260 Loan Disb 391,219.80
Feb 9, 2022 IDA-62260 Loan Disb 673,125.80
Dec 14, 2022 IDA-62260 Loan Disb 2,619,235.00
Dec 14, 2022 IDA-62260 Loan Disb 1,188,688.80
Dec 16, 2022 IDA-62260 Loan Disb 862,039.50
Sep 13, 2022 IDA-62260 Loan Disb 2,068,070.60
Sep 16, 2022 IDA-62260 Loan Disb 748,650.94
May 18, 2018 IDA-62260 Loan Commitment 40,000,000.00
May 16, 2023 IDA-62260 Int Charges 126,435.31
May 16, 2023 IDA-62260 Int Charges 4,655.48
May 16, 2023 IDA-62260 Int Charges 77,002.60
May 16, 2023 IDA-62260 Int Charges 77,002.60
Jun 22, 2023 IDA-62260 Loan Disb 3,495,733.80
Nov 15, 2023 IDA-62260 Int Charges 1,878.20
Nov 15, 2023 IDA-62260 Loan Repay 600,842.75
Nov 15, 2023 IDA-62260 Loan Repay 5,365.48
Nov 15, 2023 IDA-62260 Int Charges 106,743.96
Nov 15, 2023 IDA-62260 Int Charges 106,743.96
Nov 15, 2023 IDA-62260 Int Charges 172,770.98
Jun 16, 2023 IDA-62260 Loan Disb 5,588,101.50
May 15, 2024 IDA-62260 Int Charges 112,775.78
May 15, 2024 IDA-62260 Int Charges 112,775.78
May 15, 2024 IDA-62260 Int Charges 187,959.60
Feb 15, 2024 IDA-62260 Loan Disb 760,876.20
May 15, 2024 IDA-62260 Int Charges 5,123.84
May 15, 2024 IDA-62260 Loan Repay 302,649.16
Feb 20, 2024 IDA-62260 Loan Disb 506,519.94
May 15, 2024 IDA-62260 Loan Repay 302,174.25
Jul 12, 2019 IDA-62260 Loan Disb 300,000.00
May 15, 2020 IDA-62260 Int Charges 4,571.85
May 15, 2020 IDA-62260 Int Charges 4,571.85
May 15, 2020 IDA-62260 Int Charges 1,758.86
Apr 6, 2020 IDA-62260 Loan Disb 2,742,475.00
Jan 14, 2020 IDA-62260 Loan Disb 498,000.00
Nov 21, 2019 IDA-62260 Int Charges 765.14
Nov 21, 2019 IDA-62260 Int Charges 765.14
Nov 21, 2019 IDA-62260 Int Charges 1,269.94
May 15, 2020 IDA-62260 Int Charges 5.23
Dec 30, 2020 IDA-62260 Int Charges 6,209.59
Dec 30, 2020 IDA-62260 Int Charges 14,025.12
Dec 30, 2020 IDA-62260 Int Charges 14,025.12
Dec 30, 2020 IDA-62260 Int Charges 22,659.67
May 26, 2021 IDA-62260 Int Charges 718.53
May 26, 2021 IDA-62260 Int Charges 14,084.91
May 26, 2021 IDA-62260 Int Charges 14,084.91
May 26, 2021 IDA-62260 Int Charges 23,000.31
Jun 23, 2021 IDA-62260 Loan Disb 974,639.56
May 19, 2022 IDA-62260 Loan Disb 345,085.47
Jun 14, 2022 IDA-62260 Loan Disb 843,421.40
Nov 29, 2021 IDA-62260 Int Charges 458.63
Nov 29, 2021 IDA-62260 Int Charges 17,429.41
Nov 29, 2021 IDA-62260 Int Charges 17,429.41
Nov 29, 2021 IDA-62260 Int Charges 27,284.53
Oct 6, 2021 IDA-62260 Loan Disb 800,665.20
Oct 8, 2021 IDA-62260 Loan Disb 456,341.25
Jun 10, 2022 IDA-62260 Loan Disb 2,173,997.20
Feb 8, 2022 IDA-62260 Loan Disb 2,042,585.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2024-09-16
Procurement Satisfactory 2024-09-16
Progress towards achievement of PDO Satisfactory 2024-09-16
Financial Management Satisfactory 2024-09-16
Monitoring and Evaluation Satisfactory 2024-09-16
Overall Implementation Progress (IP) Moderately Satisfactory 2024-09-16

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT:
Outcomes
Risk to Development Outcome
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Road condition: Reduction in vehicle operating costs on the project roadValue0.0010.000.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Road safety: Increase in average iRAP star rating of the project roadValue1.001.001.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Climate resilience: Project road upgraded and improved, with climate resilient measuresValueNoYesNo
    DateMay 2, 2018June 23, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Kilometers of road upgraded from 2 to 4 lanes, with climate resilience measuresValue0.0012.007.00
    DateMay 2, 2018June 23, 2022January 18, 2022
    Comment
  • Total Number of MPWT staff received training on OPBRC and related topicsValue0.0098.0010.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Kilometers of road improved on 2 lanes, with climate resilience measuresValue0.0034.0026.00
    DateMay 2, 2018June 23, 2022January 18, 2022
    Comment
  • Number of MPWT female staff received training on OPBRC and related topicsValue0.0019.005.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Roads rehablitatedValue0.0046.0032.00
    DateMay 2, 2018June 23, 2022January 18, 2022
    Comment
  • Roads rehabilitated - non-ruralValue0.000.0015.00
    DateMay 2, 2018
    Comment
  • Kilometers of roads transferred to performance based O&M phase under OPBRCValue0.0046.000.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Percentage of adjacent markets with improved pedestrian facilities, with focus on safety of women traders and school childrenValue0.0050.000.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Share of women employed in paid jobs in implementation of OPBRCValue0.007.0010.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Contractor’s workforce trained on ESHS, OHS and GBV Code of ConductValue0.00100.00100.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Project beneficiaries (number), of which female (percentage)Value0.00400000.00150000.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Female project beneficiariesValue0.000.0047.00
    DateMay 2, 2018
    Comment
  • Reduction in average IRIValue7.004.007.00
    DateMay 2, 2018June 23, 2022
    Comment
  • Grievances registered related to delivery of the project addressed, with disagrigated data by genderValue0.0093.0090.00
    DateMay 2, 2018June 23, 2022
    Comment