| Financier | Commitments | 
|---|---|
| International Bank for Reconstruction and Development | 25.00 | 
| Borrower/Recipient | 2.00 | 
P163864
Closed
Wei Wang
Democratic Socialist Republic of Sri Lanka
May 11, 2018
(as of board presentation)
February 21, 2019
June 12, 2019
US$ 25.64 million
Ministry of Finance
2019
US$ 25.00 million
A
Not Applicable
February 19, 2020
TBD
BANK APPROVED
April 3, 2024
| Financier | Commitments | 
|---|---|
| International Bank for Reconstruction and Development | 25.00 | 
| Borrower/Recipient | 2.00 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | 25.00 | 
| IDA Commitment | N/A | 
| IBRD + IDA Commitment | 25.00 | 
| Lending Instrument | |
|---|---|
| Grant Amount | N/A | 
| Total Project Cost** | 25.64 | 
| Period | Financier | Transaction Type | Amount (US$) | 
|---|---|---|---|
| May 15, 2024 | IBRD-89070 | Int Charges | 75.34 | 
| Feb 19, 2020 | IBRD-89070 | Loan Cancel | 21,550,224.00 | 
| Feb 21, 2019 | IBRD-89070 | Loan Commitment | 25,000,000.00 | 
| May 15, 2023 | IBRD-89070 | Int Charges | 535.91 | 
| May 15, 2023 | IBRD-89070 | Int Charges | 10,070.46 | 
| Nov 15, 2023 | IBRD-89070 | Int Charges | 228.91 | 
| Nov 15, 2023 | IBRD-89070 | Int Charges | 12,066.69 | 
| Nov 15, 2022 | IBRD-89070 | Int Charges | 5,670.60 | 
| Nov 15, 2022 | IBRD-89070 | Int Charges | 611.20 | 
| Nov 15, 2021 | IBRD-89070 | Int Charges | 1,992.03 | 
| May 15, 2022 | IBRD-89070 | Int Charges | 2,036.39 | 
| Jun 9, 2020 | IBRD-89070 | Loan Disb | 300.98 | 
| Jun 9, 2020 | IBRD-89070 | Loan Disb | -300.98 | 
| Nov 15, 2020 | IBRD-89070 | Int Charges | -12,659.28 | 
| Nov 15, 2020 | IBRD-89070 | Int Charges | 6,002.46 | 
| May 15, 2021 | IBRD-89070 | Int Charges | 2,017.20 | 
| Jun 21, 2019 | IBRD-89070 | Loan Disb | 3,387,276.50 | 
| Jun 12, 2019 | IBRD-89070 | Loan Disb | 62,500.00 | 
| Jun 12, 2019 | IBRD-89070 | Fee Charges | 62,500.00 | 
| Nov 15, 2019 | IBRD-89070 | Int Charges | 23,577.53 | 
| Nov 15, 2019 | IBRD-89070 | Int Charges | 47,806.50 | 
| Jun 9, 2020 | IBRD-89070 | Loan Disb | -3,067,673.20 | 
| May 15, 2020 | IBRD-89070 | Int Charges | 26,809.53 | 
| May 15, 2020 | IBRD-89070 | Int Charges | 47,263.86 | 
| Jun 9, 2020 | IBRD-89070 | Loan Cancel | 3,067,673.20 | 
| May 15, 2024 | IBRD-89070 | Int Charges | 12,732.53 | 
| Name | Review | Date | 
|---|---|---|
| Progress towards achievement of PDO | Moderately Satisfactory | 2020-04-03 | 
| Financial Management | Satisfactory | 2020-04-03 | 
| Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-04-03 | 
| Procurement | Moderately Unsatisfactory | 2020-04-03 | 
| Counterpart Funding | Satisfactory | 2020-04-03 | 
| Project Management | Moderately Satisfactory | 2020-04-03 | 
| Monitoring and Evaluation | Satisfactory | 2020-04-03 | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Feasibility studies or project designs completed for at least five (5) PPP transactions with the assistance of the project | Value | 0.00 | 0.00 | 5.00 | 
| Date | April 2, 2018 | November 5, 2019 | February 28, 2024 | |
| Comment | 
| Transaction advisory services provided for at least four (4) PPP transactions with the assistance of the project | Value | 0.00 | 0.00 | 4.00 | 
| Date | April 2, 2018 | November 5, 2019 | February 28, 2024 | |
| Comment | 
| Commercial closure of at least three (3) PPP transactions with the assistance of the project | Value | 0.00 | 0.00 | 3.00 | 
| Date | April 2, 2018 | November 5, 2019 | February 28, 2024 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Capacity building workshops that focus on the project cycle, screening and scoring tool, structure of concession agreements (number) | Value | 0.00 | 0.00 | 4.00 | 
| Date | April 2, 2018 | November 5, 2019 | February 28, 2024 | |
| Comment | 
| NAPPP includes a social specialist with gender expertise in the team | Value | No social specialist with gender expertise in the | Social and gender specialist is in the process of | One social specialist with strong expertise on gen | 
| Date | April 2, 2018 | November 5, 2019 | March 31, 2019 | |
| Comment | 
| Number of Environmental and Social Asessments completed | Value | 0.00 | 0.00 | 3.00 | 
| Date | April 2, 2018 | November 5, 2019 | February 28, 2024 | |
| Comment | 
| At least 20% of the Government staff who will be PPP certified will be female | Value | 0.00 | 76.00 | 20.00 | 
| Date | April 2, 2018 | November 5, 2019 | February 28, 2024 | |
| Comment | 
| Stakeholder engagement for the implementation of the Communications strategy | Value | 0.00 | 0.00 | 3.00 | 
| Date | April 2, 2018 | November 5, 2019 | September 29, 2020 | |
| Comment | 
| Number of PPP nodes established in participating Line Agencies or Ministries | Value | 0.00 | 0.00 | 3.00 | 
| Date | April 2, 2018 | November 5, 2019 | February 28, 2024 | |
| Comment |