Abstract*

The development objective of Urban Development and Resilience Project is to enhance resilient infrastructure and urban planning in selected cities in Maldives and strengthen the government’s capacity to provide effective response to disasters. This project has four components, 1) The first component, Resilient Infrastructure and Emergency Preparedness, has the following sub-components: (i) Resilient Infrastructure; and (ii) Strengthening emergency...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To strengthen the Government’s capacity to provide effective response to disasters, urban planning and resilient infrastructure planning.

Key Details

Project Details

  • P163957

  • Active

  • Phoram Shah , Natsuko Kikutake

  • Republic of Maldives

  • Maldives

  • July 19, 2018

  • (as of board presentation)

    February 27, 2020

  • May 11, 2020

  • US$ 16.50 million

  • Ministry of National Planning and Infrastructure

  • South Asia

  • 2020

  • US$ 13.05 million

  • B

  • April 19, 2024

  • June 30, 2026

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 4.80
IDA Grant 8.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 13.05
IBRD + IDA Commitment 13.05
Lending Instrument
Grant Amount N/A
Total Project Cost** 16.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 15, 2021 IDA-65370 Int Charges 407.83
Feb 15, 2021 IDA-65370 Int Charges 407.83
Jun 15, 2020 IDA-65370 Loan Disb 104,385.13
Aug 15, 2021 IDA-65370 Int Charges 1.04
Aug 15, 2021 IDA-65370 Int Charges 1.04
Aug 15, 2021 IDA-65370 Int Charges 403.10
Aug 15, 2021 IDA-65370 Int Charges 403.10
Feb 15, 2022 IDA-65370 Int Charges 5.35
Feb 15, 2022 IDA-65370 Int Charges 5.35
Feb 15, 2022 IDA-65370 Int Charges 390.99
Feb 15, 2022 IDA-65370 Int Charges 390.99
Aug 15, 2022 IDA-65370 Int Charges 1.15
Aug 15, 2022 IDA-65370 Int Charges 1.15
Aug 15, 2022 IDA-65370 Int Charges 374.73
Aug 15, 2022 IDA-65370 Int Charges 374.73
Feb 27, 2020 IDA-65370 Loan Commitment 8,250,000.00
Feb 27, 2020 IDA-D5540 Loan Commitment 8,250,000.00
Dec 5, 2023 IDA-D5540 Loan Disb 840,588.00
Nov 8, 2022 IDA-D5540 Loan Disb 29,863.62
Oct 20, 2022 IDA-D5540 Loan Disb 1,097,466.00
Dec 27, 2021 IDA-D5540 Loan Disb 250,000.00
Jul 24, 2020 IDA-D5540 Loan Disb 500,000.00
Mar 16, 2021 IDA-D5540 Loan Disb 350,000.00
Feb 15, 2023 IDA-65370 Int Charges 374.44
Feb 15, 2023 IDA-65370 Int Charges 374.44
Feb 15, 2023 IDA-65370 Int Charges 3.25
Feb 15, 2023 IDA-65370 Int Charges 3.25
Aug 15, 2023 IDA-65370 Int Charges 1.85
Aug 15, 2023 IDA-65370 Int Charges 1.85
Aug 15, 2023 IDA-65370 Int Charges 378.12
Aug 15, 2023 IDA-65370 Int Charges 378.12
Aug 15, 2024 IDA-65370 Int Charges 368.84
Aug 15, 2024 IDA-65370 Int Charges 368.84
Aug 15, 2024 IDA-65370 Int Charges 5.10
Aug 15, 2024 IDA-65370 Int Charges 5.10
Feb 15, 2024 IDA-65370 Int Charges 374.77
Feb 15, 2024 IDA-65370 Int Charges 374.77
Jun 25, 2024 IDA-65370 Loan Cancel 3,454,906.50
Feb 15, 2024 IDA-65370 Int Charges 0.65
Feb 15, 2024 IDA-65370 Int Charges 0.65
Feb 15, 2021 IDA-65370 Int Charges 136.29
Feb 15, 2021 IDA-65370 Int Charges 136.29

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2025-01-07
Overall Implementation Progress (IP) Moderately Satisfactory 2025-01-07
Progress towards achievement of PDO Moderately Satisfactory 2025-01-07
Procurement Moderately Satisfactory 2025-01-07
Monitoring and Evaluation Moderately Unsatisfactory 2025-01-07
Financial Management Satisfactory 2025-01-07

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with improved urban living conditionsValue0.000.00176749.00
    DateSeptember 30, 2019April 11, 2024June 30, 2026
    Comment
  • Urban planning tools are operationalValueNo regional development plans, housing strategy, hhousing strategy has been completedRegional development: 3 regional development plans
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment
  • People provided with improved urban living conditions - Female (RMS requirement)Value0.000.000.00
    Date
    Comment
  • Reduction in area in Male city that is flooded from a 1 in 5 year flooding eventValue0.000.0020.00
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment
  • Emergency response simulations/drills conducted per year using EOCC with at least 70% of population targeted (by the drill) participatingValue0.000.002.00
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Wastewater safely treated and discharged in Hulhumale Phase 1 to country’s discharge standardsValue0.000.00100.00
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment
  • Roadmap on housing reforms developedValueNoYesYes
    DateSeptember 30, 2019April 11, 2024December 31, 2020
    Comment
  • Length of stormwater drains upgradedValue0.000.004.00
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment
  • Regional urban development plans developedValue0.000.003.00
    DateJanuary 1, 2020April 11, 2024December 31, 2021
    Comment
  • Capacity of stormwater storage tanks builtValue0.000.002000.00
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment
  • Online platform for building permit processing developedValueNoNoYes
    DateJanuary 1, 2020April 11, 2024December 31, 2022
    Comment
  • Stormwater management master plan for Male and Hulhumale developedValueNoNoYes
    DateJanuary 1, 2020April 11, 2024December 31, 2023
    Comment
  • EOCC establishedValueEOCC does not existIn progress.EOCC components are established: Community inciden
    DateJanuary 1, 2020April 11, 2024December 31, 2022
    Comment
  • People signed up for emergency warning applicationValue0.000.0020000.00
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment
  • People signed up for emergency warning application, of which womenValue0.000.009800.00
    DateJanuary 1, 2020April 11, 2024June 30, 2025
    Comment
  • Population satisfied with warning service provided by EOCCValue0.000.0080.00
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment
  • Gender equitable guidelines developed for disaster risk reductionValueNoYesYes
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment
  • Representatives in DRR committees who are womenValue0.0033.0033.00
    DateJanuary 1, 2020April 11, 2024June 30, 2026
    Comment