Financier | Commitments |
---|---|
IDA Grant | 3.55 |
P164468
Closed
Christopher De Serio
Pacific Aviation Safety Office
Pacific Islands
April 3, 2018
(as of board presentation)
May 23, 2018
N/A
US$ 3.55 million
Pacific Aviation Safety Office
2018
US$ 3.55 million
C
Not Applicable
December 31, 2022
Yes
BANK APPROVED
July 15, 2021
Financier | Commitments |
---|---|
IDA Grant | 3.55 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 3.55 |
IBRD + IDA Commitment | 3.55 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 3.55 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
ICAO Regional Safety and Security Oversight Organization (RSOO) service level | Value | Level 1 | Level 1 | Level 2 |
Date | February 28, 2018 | February 28, 2018 | December 31, 2021 | |
Comment |
Indicator One: Successful recruitment of coordinators | Value | No positions filled | General Manager supported by pool of inspectors | General Manager/ Operations Manager/ Corporate Ser |
Date | November 1, 2013 | February 28, 2018 | December 31, 2019 | |
Comment |
Indicator Two: Establishment of a Register of Inspectors (ROI) | Value | No ROI | Updated ROI in place | Updated ROI in place |
Date | November 1, 2013 | October 31, 2017 | June 30, 2017 | |
Comment |
Indicator Three: Recommended Annual Work Program Implemented by PASO Members | Value | 12.50 | 73.20 | 80.00 |
Date | November 1, 2013 | January 1, 2018 | December 31, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component C: Intermediate Results Indicator Two: Modernization of communication technology | Value | Inadequate ICT system in use | PASO IT server updated; internet bandwidth upgrade | Upgraded ICT System in use |
Date | August 1, 2013 | October 31, 2017 | December 31, 2020 | |
Comment |
Component B: Intermediate Results Indicator One: Adherence to Agreed Annual Work Plans | Value | 0.00 | 0.00 | 0.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Kiribati | Value | 130.00 | 82.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Cook Islands | Value | 0.00 | 100.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Nauru | Value | 0.00 | 0.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Niue | Value | 0.00 | 0.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Papua New Guinea | Value | 0.00 | 42.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Samoa | Value | 54.00 | 100.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Solomon Islands | Value | 24.00 | 0.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Tonga | Value | 62.00 | 100.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Tuvalu | Value | 0.00 | 54.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Annual Work Plan Implemented - Vanuatu | Value | 27.00 | 100.00 | 80.00 |
Date | January 1, 2013 | December 29, 2017 | December 31, 2021 | |
Comment |
Component D: Supporting Regional Aviation Infrastructure | Value | No VSAT | Selection of Design services completed/ goods acqu | VSAT operating |
Date | August 1, 2013 | February 28, 2018 | July 1, 2019 | |
Comment |
Beneficiaries of job-focused interventions | Value | 0.00 | 0.00 | 10.00 |
Date | March 30, 2018 | December 31, 2021 | ||
Comment |
Project-supported organization(s) publish reports on effect of collaboration on project/program/policies (Yes/No) | Value | No | No | Yes |
Date | March 30, 2018 | March 30, 2018 | January 1, 2019 | |
Comment |
Beneficiaries of job-focused interventions - Female | Value | 0.00 | 0.00 | 2.00 |
Date | March 30, 2018 | December 31, 2021 | ||
Comment |
Component A: Intermediate Results Indicator One: Revised governance structure (technical and financial committee composition), as per PASO Constitution | Value | PASO Constitution | Current PASO Constitution. Legal Advisor has compl | Updated PASO Constitution |
Date | August 1, 2013 | October 31, 2017 | December 31, 2019 | |
Comment |
Component A: Intermediate Results Indicator Two: Revised financing mechanism for sustainability | Value | Existing funding mechanism inadequate | The Final Report for the Financial Sustainability | Sustainable Financing Mechansim in place |
Date | August 1, 2013 | February 28, 2018 | January 1, 2020 | |
Comment |
Component C: Intermediate Results Indicator One: Establishment of Quality Assurance System | Value | No Quality Assurance System | The QA system has been completed, and will be revi | Quality Assurance System in Use |
Date | August 1, 2013 | October 31, 2017 | June 30, 2017 | |
Comment |