| Financier | Commitments |
|---|---|
| International Bank for Reconstruction and Development | 100.00 |
P164575
Closed
Sameer Akbar , Lazar Sestovic, Vincent De Paul Tsoungui Belinga
Republic of Serbia
August 14, 2019
(as of board presentation)
April 29, 2021
September 22, 2021
US$ 200.00 million
Commission for State Aid Control,Ministry of Environmental Protection,Ministry of Finance,Ministry of Labor, Employment, Veterans and Social Affairs,Ministry of Mining and Energy,Public Procurement Office
2021
US$ 100.00 million
N/A
Not Applicable
December 31, 2022
Bank Approved
December 21, 2023
| Financier | Commitments |
|---|---|
| International Bank for Reconstruction and Development | 100.00 |
| Product Line | IBRD/IDA |
|---|---|
| IBRD Commitment | 100.00 |
| IDA Commitment | N/A |
| IBRD + IDA Commitment | 100.00 |
| Lending Instrument | |
|---|---|
| Grant Amount | N/A |
| Total Project Cost** | 200.00 |
| INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-21-2023 |
|---|---|
| Outcomes | Moderately Satisfactory |
| Risk to Development Outcome | |
| Bank Performance | Substantial |
| Borrower Performance | |
| Government Performance | |
| Implementing Agency |
| INDICATOR | ICR REVIEW: 05-09-2024 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
|---|---|---|
| Outcome Rating | Moderately Satisfactory | N/a |
| Risk To Development Outcome | N/a | |
| Bank Performance | Satisfactory | N/a |
| Borrower Performance | N/a | |
| Government Performance | N/a | |
| Implementing Agency | N/a | |
| Icr Quality | Substantial | N/a |
| M&e Quality | N/a |