Financier | Commitments |
---|---|
IDA Credit | 10.00 |
Lao PDR - Free-standing Trust Fund Program | 3.00 |
P164813
Closed
Konesawang Nghardsaysone
Lao People’s Democratic Republic
February 18, 2018
(as of board presentation)
September 27, 2018
December 10, 2018
US$ 13.00 million
Ministry of Industry and Commerce
2019
US$ 13.00 million
C
November 30, 2023
December 31, 2024
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 10.00 |
Lao PDR - Free-standing Trust Fund Program | 3.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 10.00 |
IBRD + IDA Commitment | 10.00 |
Lending Instrument | |
---|---|
Grant Amount | 3.00 |
Total Project Cost** | 13.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 15, 2019 | IDA-63180 | Int Charges | 1,320.21 |
Apr 15, 2019 | IDA-63180 | Int Charges | 1,320.21 |
Apr 15, 2019 | IDA-63180 | Int Charges | 1,987.80 |
Aug 29, 2019 | IDA-63180 | Loan Disb | 406,666.75 |
Apr 15, 2020 | IDA-63180 | Int Charges | 8,063.98 |
Apr 15, 2020 | IDA-63180 | Int Charges | 8,063.98 |
Apr 15, 2020 | IDA-63180 | Int Charges | 12,315.96 |
Apr 15, 2020 | IDA-63180 | Int Charges | 1,054.71 |
Jun 10, 2020 | IDA-63180 | Loan Disb | 378,475.44 |
Feb 24, 2020 | IDA-63180 | Loan Disb | 400,710.22 |
Nov 13, 2019 | IDA-63180 | Loan Disb | 375,666.38 |
Oct 22, 2020 | IDA-63180 | Int Charges | 1,166.87 |
Oct 22, 2020 | IDA-63180 | Int Charges | 11,427.19 |
Oct 22, 2020 | IDA-63180 | Int Charges | 11,427.19 |
Oct 22, 2020 | IDA-63180 | Int Charges | 18,240.78 |
Sep 24, 2020 | IDA-63180 | Loan Disb | 515,734.75 |
Jan 27, 2021 | IDA-63180 | Loan Disb | 988,843.00 |
Oct 15, 2021 | IDA-63180 | Int Charges | 214.18 |
Apr 29, 2021 | IDA-63180 | Loan Disb | 745,123.00 |
Apr 21, 2021 | IDA-63180 | Int Charges | 812.92 |
Apr 21, 2021 | IDA-63180 | Int Charges | 15,336.91 |
Apr 21, 2021 | IDA-63180 | Int Charges | 15,336.91 |
Apr 21, 2021 | IDA-63180 | Int Charges | 25,561.53 |
Sep 30, 2021 | IDA-63180 | Loan Disb | 1,212,286.00 |
Nov 4, 2021 | IDA-63180 | Int Charges | 19,828.96 |
Nov 4, 2021 | IDA-63180 | Int Charges | 19,828.96 |
Nov 4, 2021 | IDA-63180 | Int Charges | 32,796.87 |
Oct 15, 2021 | IDA-63180 | Int Charges | 214.18 |
May 18, 2022 | IDA-63180 | Loan Disb | 721,257.00 |
Apr 27, 2022 | IDA-63180 | Int Charges | 23,370.72 |
Apr 27, 2022 | IDA-63180 | Int Charges | 23,370.72 |
Apr 27, 2022 | IDA-63180 | Int Charges | 38,951.15 |
Apr 27, 2022 | IDA-63180 | Int Charges | 581.55 |
Sep 27, 2022 | IDA-63180 | Loan Disb | 221,976.98 |
Oct 15, 2022 | IDA-63180 | Int Charges | 21,876.53 |
Oct 15, 2022 | IDA-63180 | Int Charges | 21,876.53 |
Oct 15, 2022 | IDA-63180 | Int Charges | 40,516.31 |
Oct 15, 2022 | IDA-63180 | Int Charges | 2,433.26 |
Oct 15, 2022 | IDA-63180 | Int Charges | 2,433.26 |
May 10, 2023 | IDA-63180 | Loan Disb | 232,217.00 |
Apr 15, 2023 | IDA-63180 | Int Charges | 25,599.46 |
Apr 15, 2023 | IDA-63180 | Int Charges | 25,599.46 |
Apr 15, 2023 | IDA-63180 | Int Charges | 45,061.59 |
Apr 15, 2023 | IDA-63180 | Int Charges | 1,998.49 |
Apr 15, 2023 | IDA-63180 | Int Charges | 1,998.49 |
Jan 30, 2023 | IDA-63180 | Loan Disb | 320,201.00 |
Aug 7, 2023 | IDA-63180 | Loan Disb | 119,208.00 |
Oct 15, 2023 | IDA-63180 | Loan Repay | 78,950.57 |
Oct 15, 2023 | IDA-63180 | Int Charges | 28,260.74 |
Oct 15, 2023 | IDA-63180 | Int Charges | 28,260.74 |
Oct 15, 2023 | IDA-63180 | Int Charges | 47,101.28 |
Oct 15, 2023 | IDA-63180 | Int Charges | 904.19 |
Oct 15, 2023 | IDA-63180 | Loan Repay | 76,667.93 |
Nov 8, 2023 | IDA-63180 | Loan Disb | 90,893.00 |
Apr 15, 2024 | IDA-63180 | Loan Repay | 3,970.59 |
Apr 15, 2024 | IDA-63180 | Loan Repay | 78,752.82 |
Apr 15, 2024 | IDA-63180 | Int Charges | 28,970.04 |
Apr 15, 2024 | IDA-63180 | Int Charges | 28,970.04 |
Apr 15, 2024 | IDA-63180 | Int Charges | 48,283.36 |
Apr 15, 2024 | IDA-63180 | Loan Repay | 73,661.34 |
Oct 22, 2019 | IDA-63180 | Loan Disb | 243,426.20 |
Oct 18, 2019 | IDA-63180 | Int Charges | 3,891.44 |
Oct 18, 2019 | IDA-63180 | Int Charges | 3,891.44 |
Oct 18, 2019 | IDA-63180 | Int Charges | 5,422.99 |
Oct 18, 2019 | IDA-63180 | Int Charges | 210.46 |
Dec 30, 2019 | IDA-63180 | Loan Disb | 272,021.72 |
Jan 30, 2019 | IDA-63180 | Loan Disb | 800,000.00 |
Mar 20, 2019 | IDA-63180 | Loan Disb | 146,603.83 |
Sep 27, 2018 | IDA-63180 | Loan Commitment | 10,000,000.00 |
Aug 28, 2024 | IDA-63180 | Loan Disb | 1,418,223.00 |
Jan 31, 2024 | IDA-63180 | Loan Disb | 302,344.00 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2025-02-17 |
Project Management | Satisfactory | 2025-02-17 |
Financial Management | Satisfactory | 2025-02-17 |
Progress towards achievement of PDO | Satisfactory | 2025-02-17 |
Monitoring and Evaluation | Satisfactory | 2025-02-17 |
Overall Implementation Progress (IP) | Satisfactory | 2025-02-17 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Time needed to start a business | Value | 173.00 | 30.00 | 70.00 |
Date | June 25, 2021 | December 6, 2023 | December 31, 2024 | |
Comment |
Sales growth in BAF supported firms compared to non-supported firms | Value | 1.00 | 1.85 | 1.20 |
Date | May 22, 2018 | December 6, 2023 | December 31, 2024 | |
Comment |
Mean time to clear imports, exports and transit through customs | Value | 5.12 | 4.85 | 4.09 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Time to obtain Enterprise Registration Certificates (ERC) from the Department of Enterprise Registration and Management (DERM) | Value | 60.00 | 10.00 | 10.00 |
Date | June 25, 2021 | December 6, 2023 | December 31, 2024 | |
Comment |
Commitments under the Trade Facilitation Agreement implemented by Lao PDR | Value | 21.00 | 49.60 | 80.00 |
Date | January 1, 2018 | December 6, 2023 | December 31, 2024 | |
Comment |
Total number of grants disbursed | Value | 0.00 | 401.00 | 500.00 |
Date | April 1, 2019 | December 6, 2023 | December 31, 2024 | |
Comment |
Lao Business Fora held per year | Value | 1.00 | 1.00 | 1.00 |
Date | December 29, 2017 | March 27, 2023 | December 31, 2024 | |
Comment |
Number of operating licenses streamlined | Value | 0.00 | 14.00 | 20.00 |
Date | May 22, 2018 | December 6, 2023 | December 31, 2024 | |
Comment |
Technical Trade Facilitation Secretariat meetings with Private Sector Participation (last 12 months) | Value | 0.00 | 13.00 | 6.00 |
Date | May 1, 2018 | December 6, 2023 | December 31, 2024 | |
Comment |
Grants to women-led enterprises | Value | 0.00 | 0.00 | 40.00 |
Date | ||||
Comment |
Issues captured and actioned through the Lao Business Forum that have been raised by women-led enterprises | Value | 33.30 | 33.30 | 0.00 |
Date | ||||
Comment |
Number of Covid-19 affected firms that seek BAF assistance and receive BAF grants to recover and respond to the shock | Value | 0.00 | 202.00 | 100.00 |
Date | May 25, 2021 | December 6, 2023 | December 31, 2024 | |
Comment |
Perception of Lao Business Forum’s effectiveness | Value | Very effective 31 percent | Very effective 31 percent | |
Date | ||||
Comment |
Number of operating licenses streamlined in sectors of particular interest to women | Value | 0.00 | 9.00 | 9.00 |
Date | May 23, 2018 | December 6, 2023 | December 31, 2024 | |
Comment |
Time to prepare documentary requirements for imports and exports | Value | 37.17 | 22.28 | 18.59 |
Date | December 31, 2020 | December 6, 2023 | December 31, 2024 | |
Comment |
Hits on the Lao Trade Portal | Value | 370.60 | 640.84 | 400.00 |
Date | December 29, 2017 | December 6, 2023 | December 31, 2024 | |
Comment |
Number of new enterprise registrations per year | Value | 9127.00 | 12024.00 | 11000.00 |
Date | December 31, 2021 | October 30, 2023 | December 31, 2024 | |
Comment |
Percentage of women-owned enterprises registrations per year | Value | 43.00 | 44.23 | 45.00 |
Date | June 25, 2021 | December 6, 2023 | December 31, 2024 | |
Comment |
Time to start a business owned by a woman as a percentage of time to start a business owned by a man | Value | 100.00 | 114.00 | 100.00 |
Date | December 31, 2021 | December 6, 2023 | December 31, 2024 | |
Comment |