Financier | Commitments |
---|---|
IDA Credit | 150.00 |
P164906
Active
Victoria Stanley , Camille Bourguignon-Roger, David Mason
United Republic of Tanzania
September 17, 2019
(as of board presentation)
December 21, 2021
May 18, 2022
US$ 150.00 million
Ministry of Lands, Housing and Human Settlements Development
2022
US$ 150.00 million
N/A
March 10, 2024
June 30, 2025
No
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 150.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 150.00 |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 1, 2022 | IDA-70220 | Loan Disb | 1,400,000.00 |
Aug 2, 2024 | IDA-70220 | Loan Disb | 12,214,779.00 |
Feb 15, 2023 | IDA-70220 | Int Charges | 2,174.61 |
Feb 15, 2023 | IDA-70220 | Int Charges | 2,174.61 |
Aug 21, 2023 | IDA-70220 | Int Charges | 10.68 |
Aug 21, 2023 | IDA-70220 | Int Charges | 10.68 |
Aug 21, 2023 | IDA-70220 | Int Charges | 21,455.43 |
Dec 21, 2021 | IDA-70220 | Loan Commitment | 150,000,000.00 |
Aug 21, 2023 | IDA-70220 | Int Charges | 21,455.43 |
Sep 27, 2023 | IDA-70220 | Loan Disb | 7,287,043.50 |
Aug 15, 2024 | IDA-70220 | Int Charges | 697.11 |
Aug 15, 2024 | IDA-70220 | Int Charges | 697.11 |
Aug 15, 2024 | IDA-70220 | Int Charges | 107,725.26 |
Aug 15, 2024 | IDA-70220 | Int Charges | 107,725.26 |
Feb 15, 2024 | IDA-70220 | Int Charges | 54.01 |
Feb 15, 2024 | IDA-70220 | Int Charges | 54.01 |
Feb 15, 2024 | IDA-70220 | Int Charges | 51,261.75 |
Feb 15, 2024 | IDA-70220 | Int Charges | 51,261.75 |
Mar 1, 2024 | IDA-70220 | Loan Disb | 15,000,000.00 |
Apr 19, 2023 | IDA-70220 | Loan Disb | 6,763,466.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2025-03-19 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-03-19 |
Project Management | Moderately Satisfactory | 2025-03-19 |
Monitoring and Evaluation | Satisfactory | 2025-03-19 |
Procurement | Moderately Satisfactory | 2025-03-19 |
Financial Management | Moderately Satisfactory | 2025-03-19 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increased number of CRO transactions | Value | 97000 | TBC | 20% increase over baseline |
Date | September 30, 2021 | October 16, 2023 | January 31, 2027 | |
Comment |
Increased perception of tenure security | Value | 0 | 81% | 75% |
Date | September 30, 2021 | September 1, 2023 | January 31, 2027 | |
Comment |
Reduction in average time for issuance of a CRO, first registration | Value | 180 | will be assessed at MTR | 60 |
Date | September 30, 2021 | October 16, 2023 | January 31, 2027 | |
Comment |
Female | Value | 0 | 83% | 75% |
Date | September 30, 2021 | September 1, 2023 | January 31, 2027 | |
Comment |
Number of certificates (CROs, CCROs) registered | Value | 0 | 8105 | 1,000,000 CROs / 500,000 CCROs |
Date | September 30, 2021 | September 30, 2023 | January 31, 2027 | |
Comment |
of which female (including individual and joint tenure) | Value | 0 | 31% | 40% |
Date | September 30, 2021 | September 30, 2023 | January 31, 2027 | |
Comment |
Degree of satisfaction of beneficiaries with the process for systematic issuance for CROs, CCROs | Value | 0 | 68% | 70% |
Date | September 30, 2021 | August 31, 2023 | January 31, 2027 | |
Comment |
of which female | Value | 0 | 65% | 70% of female beneficiaries |
Date | September 30, 2021 | August 31, 2023 | January 31, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of villages with land certificates | Value | 0.00 | 0.00 | 250.00 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of districts with CORS coverage | Value | 0 | tender has been launched in August 2023 | 15 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of staff trained | Value | 0.00 | 368.00 | 1600.00 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Semi-annual and annual progress reports prepared | Value | 0 | 3 | 25 (20 quarterly, 5 annual) |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of village land registries renovated | Value | 0.00 | 0.00 | 250.00 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Female | Value | 0 | 114 | 600 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of VLUPs completed | Value | 0 | 80 | 250 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Increased collection of land rent | Value | 121 TZS (BLN) | 58 TZS (BLN) | 50% increase over the baseline |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Reduced number of land conflicts | Value | 10,622 | 11371 | 30% decrease over the baseline |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of residential licenses issued | Value | 0.00 | 0.00 | 1000000.00 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of offices with ILMIS operational | Value | 6.00 | 8.00 | 66.00 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of District Land and Housing Tribunals operational | Value | 55.00 | 93.00 | 72.00 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of surveys completed | Value | 0.00 | 2.00 | 4.00 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of districts with updated base maps | Value | 1.00 | 1.00 | 35.00 |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Number of people informed on the project including land administration, certification process | Value | 0 | 14436 | 2 million |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |
Female | Value | 0 | 0 | 300,000 (30%) |
Date | September 30, 2021 | October 19, 2023 | January 31, 2027 | |
Comment |