Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 80.00 |
Borrower/Recipient | 20.00 |
P165129
Active
Saumya Srivastava , Pyush Dogra
Republic of India
July 8, 2019
(as of board presentation)
February 18, 2020
May 28, 2020
US$ 100.00 million
Department of Forest, Government of Himachal Pradesh
2020
US$ 80.00 million
N/A
Moderate
March 31, 2026
No
BANK APPROVED
February 23, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 80.00 |
Borrower/Recipient | 20.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 80.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 80.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 100.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 27, 2021 | IBRD-90410 | Loan Disb | 611,136.94 |
Jul 15, 2021 | IBRD-90410 | Int Charges | 510.34 |
Jun 18, 2021 | IBRD-90410 | Loan Disb | 4,006,752.80 |
Jul 15, 2021 | IBRD-90410 | Int Charges | 92,388.52 |
Jul 15, 2021 | IBRD-90410 | Int Charges | 21,341.46 |
Jul 15, 2021 | IBRD-90410 | Int Charges | 181.09 |
Jan 15, 2021 | IBRD-90410 | Int Charges | 35,764.68 |
Jan 15, 2021 | IBRD-90410 | Int Charges | 2,581.83 |
Jan 15, 2021 | IBRD-90410 | Int Charges | 97,697.00 |
Jan 15, 2021 | IBRD-90410 | Int Charges | 10,278.06 |
Nov 18, 2022 | IBRD-90410 | Loan Disb | 1,943,070.60 |
Jan 15, 2022 | IBRD-90410 | Int Charges | 740.97 |
Dec 22, 2021 | IBRD-90410 | Loan Disb | 2,651,154.20 |
Aug 15, 2022 | IBRD-90410 | Loan Disb | 824,958.75 |
Jan 15, 2022 | IBRD-90410 | Int Charges | 1,873.43 |
Jan 15, 2022 | IBRD-90410 | Int Charges | 88,086.77 |
Jan 15, 2022 | IBRD-90410 | Int Charges | 38,906.92 |
Jul 15, 2022 | IBRD-90410 | Int Charges | 435.81 |
Jul 15, 2022 | IBRD-90410 | Int Charges | 942.79 |
Jul 15, 2022 | IBRD-90410 | Int Charges | 81,388.44 |
Jul 15, 2022 | IBRD-90410 | Int Charges | 69,934.38 |
May 25, 2022 | IBRD-90410 | Loan Disb | 3,660,342.20 |
Jul 15, 2023 | IBRD-90410 | Int Charges | 39,227.04 |
Jul 15, 2023 | IBRD-90410 | Int Charges | 71,503.72 |
Jul 15, 2023 | IBRD-90410 | Int Charges | 567,248.70 |
Jul 15, 2023 | IBRD-90410 | Int Charges | 771.91 |
Aug 22, 2023 | IBRD-90410 | Loan Disb | 115,059.50 |
Aug 14, 2023 | IBRD-90410 | Loan Disb | 757,219.90 |
Jan 15, 2023 | IBRD-90410 | Int Charges | 24,206.05 |
Jan 15, 2023 | IBRD-90410 | Int Charges | 77,399.13 |
Jan 15, 2023 | IBRD-90410 | Int Charges | 362,705.22 |
Jan 15, 2023 | IBRD-90410 | Int Charges | 1,278.60 |
Feb 17, 2023 | IBRD-90410 | Loan Disb | 1,197,406.40 |
Jan 15, 2024 | IBRD-90410 | Int Charges | 892,285.00 |
Jan 15, 2024 | IBRD-90410 | Int Charges | 65,765.43 |
Jan 15, 2024 | IBRD-90410 | Int Charges | 1,597.79 |
Jan 15, 2024 | IBRD-90410 | Int Charges | 44,205.62 |
Jul 31, 2024 | IBRD-90410 | Loan Disb | 3,374,800.80 |
Feb 12, 2024 | IBRD-90410 | Loan Disb | 2,268,319.80 |
Nov 7, 2023 | IBRD-90410 | Loan Disb | 2,019,319.60 |
May 30, 2023 | IBRD-90410 | Loan Disb | 5,071,244.00 |
Mar 25, 2024 | IBRD-90410 | Loan Disb | 4,724,495.50 |
Jul 15, 2024 | IBRD-90410 | Int Charges | 5,905.49 |
Jul 15, 2024 | IBRD-90410 | Int Charges | 56,619.59 |
Jul 15, 2024 | IBRD-90410 | Int Charges | 1,112,314.60 |
May 13, 2024 | IBRD-90410 | Loan Disb | 1,194,322.90 |
Feb 18, 2020 | IBRD-90410 | Loan Commitment | 80,000,000.00 |
Feb 17, 2021 | IBRD-90410 | Loan Disb | 2,222,521.20 |
Dec 14, 2020 | IBRD-90410 | Loan Disb | 827,513.30 |
Aug 21, 2020 | IBRD-90410 | Loan Disb | 471,803.00 |
May 28, 2020 | IBRD-90410 | Loan Disb | 200,000.00 |
May 28, 2020 | IBRD-90410 | Fee Charges | 200,000.00 |
Jun 22, 2020 | IBRD-90410 | Loan Disb | 1,350,334.80 |
Jun 29, 2020 | IBRD-90410 | Loan Disb | 212,016.19 |
Mar 8, 2022 | IBRD-90410 | Loan Disb | 1,073,447.20 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2025-05-14 |
Project Management | Satisfactory | 2025-05-14 |
Procurement | Moderately Satisfactory | 2025-05-14 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2025-05-14 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-05-14 |
Progress towards achievement of PDO | Satisfactory | 2025-05-14 |
Financial Management | Satisfactory | 2025-05-14 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Land area under sustainable landscape management practices | Value | 0.00 | 6569.00 | 12000.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
New farm area brought under higher efficiency irrigation through project support in targeted GPs | Value | 0.00 | 22.74 | 200.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Area managed for improved soil | Value | 0.00 | 0.00 | 200.00 |
Date | ||||
Comment |
Number of reforms recommended by the institutional assessments that are implemented | Value | 0.00 | 0.00 | 5.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Share of participating farmers who give a rating of “Satisfied” or above on process and realized benefits of project interventions | Value | 0.00 | 0.00 | 75.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Share of participating female farmers who give a rating of “Satisfied” or above on process and realized benefits of project interventions | Value | 0.00 | 0.00 | 75.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Farmers reached with agricultural assets or services | Value | 0.00 | 9793.00 | 20000.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Survival rate of seedlings planted with project support | Value | 0.00 | 71.26 | 80.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Percentage of women signatories engaged in approving GP-RMPs | Value | 0.00 | 43.39 | 30.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Technical staff of participating line departments trained on integrated watershed management | Value | 0.00 | 373.00 | 400.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Farmers reached with agricultural assets or services - Female | Value | 0.00 | 0.00 | 1000.00 |
Date | ||||
Comment |
Farmers reached with agricultural extension or training – Male | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Farmers reached with agricultural extension or training – Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Farmers adopting improved agricultural technology | Value | 0.00 | 0.00 | 10000.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Farmers adopting improved agricultural technology - Female | Value | 0.00 | 0.00 | 300.00 |
Date | ||||
Comment |
Farmers adopting improved agricultural technology - male | Value | 0.00 | 0.00 | 700.00 |
Date | ||||
Comment |
Area provided with new/improved irrigation or drainage services | Value | 0.00 | 568.92 | 1500.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Area provided with new irrigation or drainage services | Value | 0.00 | 550.39 | 1300.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Area provided with improved irrigation or drainage services | Value | 0.00 | 22.74 | 200.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |
Share of user groups for agriculture extension services with female treasurers | Value | 0.00 | 48.15 | 30.00 |
Date | March 2, 2020 | June 30, 2023 | February 28, 2025 | |
Comment |