Support to the Bogota Metro Line 1 Section 1 Project - (Series 1)

Abstract*

The development objective of Support to the First Bogota Metro Line Section One Project for Colombia is to improve access to jobs and quality transit for public transport users in the area of influence of the Bogota Metro Line 1, Section 1 (PLMB). This project has two components. 1) The first component, Detailed Designs, initial construction works, including inter alia, civil works related to ground improvement and compacting for the rail yard, and...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO of the proposed first Project under the series is to improve readiness and start the implementation of the Bogota Metro Line 1, Section 1 (PLMB).

Key Details

Project Details

  • P165300

  • Active

  • Leonardo Canon Rubiano , Linda Ivarsson Molina

  • Empresa Metro de Bogota, SA

  • Colombia

  • January 2, 2018

  • (as of board presentation)

    August 2, 2018

  • January 27, 2021

  • US$ 196.00 million

  • A

  • February 6, 2024

  • December 12, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
EC: European Investment Bank 53.00
Inter-American Development Bank 73.00
International Bank for Reconstruction and Development 70.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 70.00
IDA Commitment N/A
IBRD + IDA Commitment 70.00
Lending Instrument
Grant Amount 126.00
Total Project Cost** 4400.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 15, 2024 IBRD-89010 Int Charges 4.66
Mar 15, 2024 IBRD-89010 Int Charges 0.85
Mar 15, 2024 IBRD-89010 Int Charges 87,083.56
Mar 15, 2024 IBRD-89010 Int Charges 2,173.33
Jun 30, 2023 IBRD-89010 Loan Disb 70,000.00
Mar 15, 2022 IBRD-89010 Int Charges 86,780.81
Mar 8, 2019 IBRD-89010 Fee Charges 175,000.00
Aug 2, 2018 IBRD-89010 Loan Commitment 70,000,000.00
Sep 15, 2021 IBRD-89010 Int Charges 28,287.67
Sep 15, 2021 IBRD-89010 Int Charges 88,219.16
Sep 15, 2021 IBRD-89010 Int Charges 398,904.06
Sep 15, 2022 IBRD-89010 Int Charges 88,219.16
Aug 25, 2023 IBRD-89010 Loan Disb -5,943.24
Sep 15, 2023 IBRD-89010 Int Charges 88,182.25
Sep 15, 2023 IBRD-89010 Int Charges 908.58
Mar 15, 2023 IBRD-89010 Int Charges 86,780.81

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2025-01-21
Financial Management Satisfactory 2025-01-21
Overall Implementation Progress (IP) Moderately Satisfactory 2025-01-21
Progress towards achievement of PDO Moderately Satisfactory 2025-01-21
Procurement Moderately Satisfactory 2025-01-21
Project Management Satisfactory 2025-01-21

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • DFBOMT Contract awardedValueNoYesYes
    DateJuly 31, 2018November 27, 2019December 31, 2019
    Comment
  • Cumulative percentage of physical works for railyard and Cl72 interchangeValue0.0026.6630.00
    DateJuly 31, 2018November 27, 2023May 29, 2026
    Comment
  • Cumulative percentage of physical works for Cl72 interchangeValue0.0042.3250.00
    DateAugust 30, 2018November 27, 2023May 29, 2026
    Comment
  • cumulative percentage of physical works for RailyardsValue0.0085.8850.00
    DateAugust 30, 2018November 27, 2023December 30, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Cumulative percentage of transfer of utility networks completed.Value0.00100.00100.00
    DateJuly 31, 2018November 27, 2023December 30, 2022
    Comment
  • Project Management Office hiredValueNoYesYes
    DateJuly 31, 2018December 31, 2018January 31, 2019
    Comment
  • Grievances responded and/or resolved within the stipulated service standards for response times (%)Value0.00100.0080.00
    DateJuly 31, 2018November 27, 2023May 29, 2026
    Comment
  • DFBOMT contract includes target of women employed in O&M phase of the PLMBValueNoYesYes
    DateJuly 31, 2018November 27, 2019December 31, 2019
    Comment
  • Traffic management plans for preliminary works (Railyards, Av 68 & Cl 72) approved by the Secretariat of MobilityValue0.002.003.00
    DateJuly 31, 2018January 7, 2022January 28, 2022
    Comment
  • Cumulative percentage of land purchase completedValue0.0098.14100.00
    DateAugust 30, 2018November 27, 2023January 31, 2023
    Comment