| Financier | Commitments | 
|---|---|
| International Bank for Reconstruction and Development | 90.00 | 
P165711
Closed
Amal Talbi , Nishtha Mehta, Sally Zgheib
Ministry of Finance
May 5, 2018
(as of board presentation)
June 15, 2018
N/A
US$ 90.00 million
Council for Development & Reconstruction
2018
US$ 90.00 million
A
Not Applicable
April 30, 2025
Yes
Bank Approved
November 14, 2022
| Financier | Commitments | 
|---|---|
| International Bank for Reconstruction and Development | 90.00 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | 90.00 | 
| IDA Commitment | N/A | 
| IBRD + IDA Commitment | 90.00 | 
| Lending Instrument | |
|---|---|
| Grant Amount | N/A | 
| Total Project Cost** | 90.00 | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Number of customers in Greater Beirut Mount Lebanon receiving 24/7 water supply | Value | 0.00 | 0.00 | 20000.00 | 
| Date | December 6, 2011 | November 7, 2017 | November 30, 2020 | |
| Comment | 
| Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 0.00 | 200000.00 | 
| Date | December 6, 2011 | November 7, 2017 | June 30, 2019 | |
| Comment | 
| Volume (million cum/year) of additional potable water distributed in the project area (cumulative) | Value | 0.00 | 0.00 | 45.00 | 
| Date | January 3, 2011 | November 7, 2017 | November 30, 2020 | |
| Comment | 
| New piped household connections for poor households in Southern Beirut | Value | 0.00 | 4059.00 | 20000.00 | 
| Date | December 6, 2011 | November 7, 2017 | November 30, 2020 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Water treatment plant | Value | 0.00 | 0.00 | 1.00 | 
| Date | January 4, 2011 | November 8, 2018 | November 30, 2020 | |
| Comment | 
| Transmission lines | Value | 0.00 | 0.00 | 2.00 | 
| Date | January 5, 2010 | November 8, 2018 | November 30, 2020 | |
| Comment | 
| Bulk reservoirs | Value | 0.00 | 0.00 | 3.00 | 
| Date | January 8, 2010 | November 8, 2018 | November 30, 2020 | |
| Comment | 
| Supply Reservoirs | Value | 0.00 | 0.00 | 16.00 | 
| Date | January 5, 2010 | November 7, 2017 | November 30, 2020 | |
| Comment | 
| Pipelines (kms) | Value | 0.00 | 392.95 | 395.00 | 
| Date | January 5, 2016 | November 7, 2017 | November 30, 2020 | |
| Comment | 
| Household meters | Value | 0.00 | 0.00 | 200000.00 | 
| Date | January 5, 2010 | November 7, 2017 | June 30, 2019 | |
| Comment | 
| House connections in poor areas | Value | 0.00 | 4059.00 | 20000.00 | 
| Date | January 5, 2010 | November 7, 2017 | June 30, 2019 | |
| Comment | 
| PMU Staff hired | Value | 0.00 | 12.00 | 10.00 | 
| Date | January 5, 2010 | November 7, 2017 | June 30, 2019 | |
| Comment | 
| Telemetry/Scada System installed | Value | 0.00 | 1.00 | 1.00 | 
| Date | January 5, 2010 | November 7, 2017 | November 30, 2020 | |
| Comment | 
| GIS System Installed | Value | 0.00 | 1.00 | 1.00 | 
| Date | January 5, 2010 | November 7, 2017 | November 30, 2020 | |
| Comment | 
| Customer Information System | Value | 0.00 | 1.00 | 1.00 | 
| Date | January 5, 2010 | November 7, 2017 | November 30, 2020 | |
| Comment | 
| TA for Design and operation of distribution system for 24/7 supply | Value | 0.00 | 1.00 | 1.00 | 
| Date | January 5, 2010 | November 7, 2017 | November 30, 2020 | |
| Comment | 
| Implementation of international accounting standards. | Value | 0.00 | 0.00 | 1.00 | 
| Date | January 5, 2010 | November 7, 2017 | December 30, 2016 | |
| Comment | 
| Studies completed satisfactorily | Value | 0.00 | 0.00 | 4.00 | 
| Date | January 5, 2010 | November 7, 2017 | June 30, 2019 | |
| Comment | 
| Number of leadership and technical trainings conducted for female employees | Value | 0.00 | 0.00 | 3.00 | 
| Date | March 28, 2018 | March 29, 2018 | November 30, 2020 | |
| Comment | 
| Grievances responded to and resolved according to GRM processes and procedures | Value | 0.00 | 0.00 | 100.00 | 
| Date | December 31, 2010 | March 29, 2018 | November 30, 2020 | |
| Comment | 
| Female employees satisfied with technical and management skills acquired through trainings | Value | 0.00 | 0.00 | 70.00 | 
| Date | March 28, 2018 | November 8, 2018 | November 30, 2020 | |
| Comment | 
| Tunnel (kms) | Value | 0.00 | 22.00 | 24.00 | 
| Date | January 4, 2011 | November 8, 2018 | November 30, 2020 | |
| Comment |