Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 137.00 |
Borrowing Agency | 64.06 |
P166977
Closed
Chabungbam Singh
Odisha Water Resource Department,Madhya Pradesh Water Resources Department,Karnataka Water Resources Development Organisation,Damodar Valley Corporation (DVC),Central Water Commission under Minsitry of Water Resources, River Development and Ganga Rejuvenation,Kerala Water Resources Department,TANGEDCO Tamil Nadu,Kerala State Electricity Board,Department of Economic Affairs,Uttarakhand Jal Vidyut Nigam Limited,Tamil Nadu Water Resources Department
February 6, 2019
(as of board presentation)
February 28, 2019
N/A
US$ 206.00 million
Kerala State Electricity Board,Uttarakhand Jal Vidyut Nigam Limited,Odisha Water Resource Department,Karnataka Water Resources Development Organisation,Tamil Nadu Water Resources Department,TANGEDCO Tamil Nadu,Central Water Commission under the Ministry of Water Resources,Damodar Valley Corporation (DVC),Kerala Water Resources Department,Madhya Pradesh Water Resources Department
2019
US$ 137.00 million
B
Not Applicable
March 31, 2021
Yes
BANK APPROVED
July 11, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 137.00 |
Borrowing Agency | 64.06 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 137.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 137.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 206.00 |