Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 60.90 |
Bosnia and Herzegovina Water and Sanitation Sector Moderniza | 7.00 |
P168943
Active
IGOR PALANDZIC , Camilo Lombana Cordoba
Bosnia and Herzegovina
Bosnia and Herzegovina
November 8, 2019
(as of board presentation)
November 24, 2021
August 11, 2023
US$ 67.90 million
Ministry of Agriculture, Forestry and Water Management of Republika Srpska,Ministry of Agriculture, Water Management and Forestry of Federation of Bosnia and Herzegovina
2022
US$ 67.90 million
N/A
Substantial
November 30, 2027
Yes
BANK APPROVED
January 24, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 60.90 |
Bosnia and Herzegovina Water and Sanitation Sector Moderniza | 7.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 60.90 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 60.90 |
Lending Instrument | |
---|---|
Grant Amount | 7.00 |
Total Project Cost** | 67.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 15, 2023 | IBRD-93020 | Loan Disb | -139,899.75 |
Aug 11, 2023 | IBRD-93020 | Loan Disb | 141,541.31 |
Apr 2, 2024 | IBRD-93020 | Loan Disb | 3,223,200.00 |
May 15, 2024 | IBRD-93020 | Int Charges | 68,226.95 |
Nov 24, 2021 | IBRD-93020 | Loan Commitment | 60,900,000.00 |
Nov 15, 2023 | IBRD-93020 | Int Charges | 1,704.92 |
Aug 11, 2023 | IBRD-93020 | Fee Charges | 141,541.31 |
Nov 15, 2023 | IBRD-93020 | Int Charges | 170,854.03 |
May 15, 2024 | IBRD-93020 | Loan Disb | -3,247,500.00 |
May 15, 2024 | IBRD-93020 | Loan Disb | 3,247,500.00 |
Nov 15, 2023 | IBRD-93020 | Loan Disb | 139,899.75 |
May 15, 2024 | IBRD-93020 | Int Charges | 2,917.06 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Satisfactory | 2025-01-24 |
Procurement | Moderately Satisfactory | 2025-01-24 |
Financial Management | Satisfactory | 2025-01-24 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-01-24 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-01-24 |
Project Management | Moderately Satisfactory | 2025-01-24 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Sector financing frameworks/policies drafted and submitted for approval | Value | No | No | Yes |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Percentage of participating utilities achieving the agreed threshold score for key efficiency performance indicators as agreed in their utility operational manual. | Value | 0.00 | 0.00 | 70.00 |
Date | January 1, 2021 | September 28, 2023 | March 1, 2027 | |
Comment |
Number of WUs utilizing the newly established WSS benchmarking system | Value | 0.00 | 0.00 | 40.00 |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
People provided with access to safely managed water services | Value | 0.00 | 0.00 | 165000.00 |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Female beneficiaries with access to safely managed water services | Value | 0.00 | 0.00 | 15000.00 |
Date | ||||
Comment |
People provided with access to safely managed sanitation services | Value | 0.00 | 0.00 | 35000.00 |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Female beneficiaries with access to safely managed sanitation services | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of new service agreements between LGs and WUs developed and signed | Value | 0.00 | 0.00 | 15.00 |
Date | January 1, 2021 | September 28, 2023 | January 25, 2027 | |
Comment |
Percentage of utilities achieving the agreed threshold score for their operational key performance indicators as agreed in the utility operational plan | Value | 0.00 | 0.00 | 70.00 |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Benchmarking system established | Value | No | No | Yes |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Water utilities that have prepared new or have updated business plans | Value | 0.00 | 6.00 | 15.00 |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Improved customer satisfaction with WSS service delivery | Value | 0.00 | 0.00 | 5.00 |
Date | February 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Capacity building program launched | Value | No | No | Yes |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Number of water utility staff participating in capacity building programs | Value | 0.00 | 0.00 | 200.00 |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Share of newly recruited engineers that are female | Value | 0.00 | 0.00 | 45.00 |
Date | January 1, 2020 | September 28, 2023 | March 25, 2027 | |
Comment |
Reduced energy consumption of the operated water supply system (as a result of rehabilitation) | Value | 0.00 | 0.00 | 15.00 |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |
Number of female professionals participating in capacity building programs | Value | 0.00 | 0.00 | 70.00 |
Date | January 1, 2021 | September 28, 2023 | March 25, 2027 | |
Comment |