Skip to Main Navigation

Horn of Africa - Groundwater Initiative

Development Objective

To support selected IGAD countries prepare for the development and management of groundwater through strengthening knowledge systems, building their capacity and assessing the feasibility of specific investments.

Key Details

Project Details

  • P169078

  • Closed

  • Victor Vazquez Alvarez

  • Intergovernmental Authority on Development (IGAD)

  • Eastern and Southern Africa

  • October 19, 2018

  • (as of board presentation)

    May 17, 2019

  • July 11, 2019

  • US$ 2.70 million

  • N/A

  • Not Applicable

  • July 31, 2022

  • Yes

  • BANK APPROVED

  • September 6, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Cooperation in International Waters in Africa 2.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 2.70
Total Project Cost** 2.50

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Low 2022-05-26
Overall Implementation Progress (IP) Moderately Satisfactory 2022-05-26
Overall Safeguards Rating Satisfactory 2022-05-26
Progress towards achievement of PDO Moderately Satisfactory 2022-05-26
Overall Safeguards Rating Satisfactory 2022-05-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 01-29-2023
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Ground water assessment for selected parts of the region preparedValue0.001.001.00
    DateAugust 14, 2019May 17, 2021July 31, 2022
    Comment
  • Capacity development needs assessment to develop and manage groundwater in the region preparedValue0.001.001.00
    DateAugust 14, 2019May 17, 2021July 31, 2022
    Comment
  • Feasibility study on ground water potential aquifers preparedValue0.001.001.00
    DateAugust 14, 2019May 17, 2021July 31, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Capacity development action plan to develop and manage ground water in the region preparedValue0.001.001.00
    DateAugust 14, 2019May 17, 2021July 31, 2022
    Comment