Financier | Commitments |
---|---|
Energy Sector Management Assistance Program | 0.86 |
Carbon Initiative for Development | 5.58 |
P169538
Closed
Rutu Dave
Lao People's Democratic Republic
February 13, 2019
(as of board presentation)
June 26, 2019
August 29, 2019
US$ 6.44 million
The Ministry of Energy and Mines (MEM)
2019
US$ 6.44 million
N/A
Moderate
March 15, 2024
No
BANK APPROVED
August 30, 2024
Financier | Commitments |
---|---|
Energy Sector Management Assistance Program | 0.86 |
Carbon Initiative for Development | 5.58 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 6.44 |
Total Project Cost** | 6.44 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2024-01-15 |
Project Management | Satisfactory | 2024-01-15 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-01-15 |
Financial Management | Satisfactory | 2024-01-15 |
Monitoring and Evaluation | Satisfactory | 2024-01-15 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2024-01-15 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-06-2024 |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Emissions Reductions from avoided use of charcoal (measured in ton of carbon dioxide equivalent or tCO2e) | Value | 0.00 | 558648.00 | 0.00 |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Time savings for direct beneficiaries (days per year) | Value | 0.00 | 7.00 | 0.00 |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Lowered occurrences of eye irritation and headaches | Value | 0.00 | 50.00 | 0.00 |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Implementing entity contracted | Value | No | Yes | |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Registration of the Programme of Activities (PoA) | Value | No | Yes | |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Forced-draft gasifier stoves distributed in Vientiane Capital | Value | 0.00 | 26000.00 | 0.00 |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
CDM Operations Manual | Value | No | Yes | |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Forced-draft gasifier stoves distributed in Savannakhet | Value | 0.00 | 12000.00 | 0.00 |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Pellets distributed in Vientiane Capital | Value | 0.00 | 10530.00 | 0.00 |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Forced-draft gasifier stoves distributed in Champasack | Value | 0.00 | 12000.00 | 0.00 |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Pellets distributed in Savanakhet | Value | 0.00 | 4860.00 | 0.00 |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Awareness campaign on clean cookstoves launched | Value | No | Yes | |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |
Pellets distributed in Champasack | Value | 0.00 | 4860.00 | 0.00 |
Date | July 1, 2019 | December 31, 2025 | ||
Comment |