| Financier | Commitments |
|---|---|
| IDA Grant | 45.00 |
P169949
Closed
Hemang Karelia
UNOPS
November 12, 2019
(as of board presentation)
August 3, 2020
September 3, 2020
US$ 45.00 million
UNOPS
2021
US$ 45.00 million
N/A
High
July 31, 2024
Yes
Bank Approved
April 19, 2024
| Financier | Commitments |
|---|---|
| IDA Grant | 45.00 |
| Product Line | IBRD/IDA |
|---|---|
| IBRD Commitment | N/A |
| IDA Commitment | 45.00 |
| IBRD + IDA Commitment | 45.00 |
| Lending Instrument | |
|---|---|
| Grant Amount | N/A |
| Total Project Cost** | 45.00 |
| Name | Review | Date |
|---|---|---|
| Financial Management | Satisfactory | 2024-10-13 |
| Monitoring and Evaluation | Satisfactory | 2024-10-13 |
| Overall Implementation Progress (IP) | Satisfactory | 2024-10-13 |
| Procurement | Satisfactory | 2024-10-13 |
| Progress towards achievement of PDO | Satisfactory | 2024-10-13 |
| Project Management | Satisfactory | 2024-10-13 |
| INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-23-2025 |
|---|---|
| Outcomes | |
| Risk to Development Outcome | |
| Bank Performance | |
| Borrower Performance | |
| Government Performance | |
| Implementing Agency |
| INDICATOR | ICR REVIEW: 05-23-2025 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
|---|---|---|
| Outcome Rating | Satisfactory | N/a |
| Risk To Development Outcome | N/a | |
| Bank Performance | Satisfactory | N/a |
| Borrower Performance | N/a | |
| Government Performance | N/a | |
| Implementing Agency | N/a | |
| Icr Quality | High | N/a |
| M&e Quality | Substantial | N/a |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| Number of people with access to improved infrastructure due to the project (disaggregated by infrastructure type, gender, displacement status) | Value | 0.00 | 693760.00 | 250000.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| Percentage of PDCs/BDCs that are functional and accountable as measured by an institutional maturity index | Value | 0.00 | 90.00 | 100.00 |
| Date | August 1, 2020 | September 21, 2023 | September 21, 2022 | |
| Comment |
| Percentage of subprojects that are functional at project completion (disaggregated by infrastructure type) | Value | 0.00 | 100.00 | 0.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| INDICATOR | BASELINE | CURRENT | TARGET |
|---|
| Number of people benefitting from DRM activities designed to reduce vulnerability to flooding. | Value | 0.00 | 81190.00 | 0.00 |
| Date | August 1, 2020 | September 21, 2023 | ||
| Comment |
| Number of workdays generated from subproject construction/rehabilitation (disaggregated by infrastructure type, gender, displacement status) | Value | 0.00 | 491317.00 | 35000.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| Percentage of BDC/PDC members trained (disaggregated by gender, displacement status). | Value | 0.00 | 90.00 | 60.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| Percentage of counties for which the required information is uploaded to the MIS in a timely manner to monitor results. | Value | 0.00 | 90.00 | 70.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| Percentage of county government officials trained. | Value | 0.00 | 0.00 | 0.00 |
| Date | August 1, 2020 | September 21, 2023 | ||
| Comment |
| Percentage of female representation in BDCs/PDCs | Value | 0.00 | 45.00 | 0.00 |
| Date | September 18, 2020 | September 21, 2023 | ||
| Comment |
| Percentage of grievances appropriately responded to within the pre-determined timeframe. | Value | 0.00 | 98.00 | 60.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| Percentage of leadership positions held by women in BDCs/PDCs. | Value | 0.00 | 39.00 | 20.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| Percentage of sampled benecifiary community who report that the subprojects meet their needs (disaggregated by infrastructure type,gender, displacement status) | Value | 0.00 | 86.40 | 60.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| Percentage of sampled beneficiary community satisfied with access to functional infrastructure provided under the project (disaggregated by infrastructure type, gender, displacement status) | Value | 0.00 | 100.00 | 60.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| Percentage of subprojects for which arrangements for operations and maintenance are established (disaggregated by infrastructure type). | Value | 0.00 | 89.00 | 60.00 |
| Date | August 1, 2020 | September 21, 2023 | February 28, 2022 | |
| Comment |
| Percentage of women in O&M groups. | Value | 0.00 | 49.00 | 15.00 |