Support to Institutional Capacity Enhancement for Urban Development and Management

Abstract*

The project focuses on enhancing the institutional capacity of the selected Ministries, Departments and Agencies for urban development and management. The project has two components, and each component has two sub components.Overall, relevant staff training will cover ESHS aspects of all phases of infrastructure project preparation and management. While this component will not include project design, stakeholder engagement, risk assessment and project/product...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To enhance institutional capacity of the selected Ministries, Departments and Agencies, and local governments responsible for Urban development and management.

Key Details

Project Details

  • P170732

  • Closed

  • John Stephen Ajalu , Martin Onyach-Olaa

  • Ministry of Finance, Planning and Economic Development

  • Uganda

  • October 2, 2019

  • (as of board presentation)

    December 22, 2021

  • February 28, 2020

  • US$ 2.65 million

  • Ministry of Lands, Housing and Urban Development,National Planning Authority

  • Eastern and Southern Africa

  • 2022

  • US$ 2.65 million

  • N/A

  • Substantial

  • March 31, 2022

  • Yes

  • BANK APPROVED

  • August 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
UK-DFID Trust Fund to Support Uganda's NDP 2.65

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 2.65
Total Project Cost** 2.65

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2022-04-29
Overall Implementation Progress (IP) Satisfactory 2022-04-29
Overall Satisfactory 2022-04-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-23-2022
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Streamlined processes and tools for urban Management developedValue0.004.004.00
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment
  • Percentage of Capital Investment Projects prepared and appraised in-houseValue0.0040.0068.00
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Tourism circuit feasibility assessment completed and Investment Plan developedValueNoYesYes
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment
  • Web geoportal for sharing spatial data/information developedValueNoYesYes
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment
  • Number of Urban Councils with updated or developed detailed neighborhood plansValue0.004.004.00
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment
  • Number of technical staff from GKMA institutions trained in strategic thematic areasValue0.0040.0051.00
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment
  • Spatial data management standards and guidelines developedValueNoYesYes
    DateNovember 18, 2019March 31, 2022March 31, 2022
    Comment
  • Land Banking Guidelines developedValueNoYesYes
    DateNovember 14, 2019March 31, 2022March 31, 2022
    Comment
  • Criteria and guidelines for national shared infrastructure corridor developedValueNoYesYes
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment
  • Map of the eastern arm (Kampala to Malaba) of the Main Spine of the national infrastructure corridor developedValueNoYesYes
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment
  • Road/Public facility management committees establishedValue0.0020.0010.00
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment
  • Percentage of road reserves/public utilities marked as plannedValue0.0040.0030.00
    DateNovember 15, 2019March 31, 2022March 31, 2022
    Comment