Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 160.00 |
P170874
Active
Eric Dickson
Republic of Indonesia
May 21, 2019
(as of board presentation)
November 27, 2019
October 12, 2020
US$ 160.00 million
Indonesian Agency for Meteorology, Climatology and Geophysics,National Disaster Management Authority
2020
US$ 160.00 million
N/A
Moderate
October 31, 2025
TBD
BANK APPROVED
January 8, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 160.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 160.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 160.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 160.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 15, 2024 | IBRD-89800 | Loan Disb | 5,400,000.00 |
Aug 1, 2024 | IBRD-89800 | Int Charges | 9,542.84 |
Aug 1, 2024 | IBRD-89800 | Int Charges | 120,243.74 |
Aug 1, 2024 | IBRD-89800 | Int Charges | 2,134,540.50 |
Feb 1, 2024 | IBRD-89800 | Int Charges | 100,498.54 |
Nov 16, 2023 | IBRD-89800 | Loan Disb | 11,900,000.00 |
Aug 26, 2024 | IBRD-89800 | Loan Disb | 14,490,000.00 |
Aug 1, 2021 | IBRD-89800 | Int Charges | 190,403.52 |
Aug 1, 2021 | IBRD-89800 | Int Charges | 37,735.44 |
Aug 1, 2021 | IBRD-89800 | Int Charges | 269.04 |
Dec 2, 2020 | IBRD-89800 | Loan Disb | 690,000.00 |
Feb 1, 2021 | IBRD-89800 | Int Charges | 62,118.86 |
Nov 30, 2020 | IBRD-89800 | Fee Charges | 400,000.00 |
Feb 25, 2021 | IBRD-89800 | Loan Disb | 6,600,000.00 |
Aug 1, 2022 | IBRD-89800 | Int Charges | 129,400.93 |
Feb 1, 2022 | IBRD-89800 | Int Charges | 186,645.50 |
Feb 1, 2022 | IBRD-89800 | Int Charges | 66,909.32 |
Aug 1, 2022 | IBRD-89800 | Int Charges | 176,797.33 |
Nov 9, 2021 | IBRD-89800 | Loan Disb | 10,100,000.00 |
Aug 1, 2021 | IBRD-89800 | Int Charges | 1,157.34 |
Jun 26, 2023 | IBRD-89800 | Loan Disb | 17,347,000.00 |
Aug 1, 2023 | IBRD-89800 | Int Charges | 166,864.10 |
Aug 1, 2023 | IBRD-89800 | Int Charges | 666,639.80 |
Apr 19, 2023 | IBRD-89800 | Loan Disb | 7,940,000.00 |
Feb 1, 2023 | IBRD-89800 | Int Charges | 179,727.69 |
Feb 1, 2023 | IBRD-89800 | Int Charges | 381,304.75 |
Nov 27, 2019 | IBRD-89800 | Loan Commitment | 160,000,000.00 |
Feb 26, 2024 | IBRD-89800 | Loan Disb | 9,500,000.00 |
Feb 1, 2024 | IBRD-89800 | Int Charges | 141,521.95 |
Feb 1, 2024 | IBRD-89800 | Int Charges | 1,637,754.20 |
Feb 1, 2024 | IBRD-89800 | Int Charges | 4,277.35 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2025-06-30 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2025-06-30 |
Procurement | Moderately Unsatisfactory | 2025-06-30 |
Financial Management | Moderately Unsatisfactory | 2025-06-30 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2025-06-30 |
Project Management | Moderately Unsatisfactory | 2025-06-30 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Local governments with functioning emergency operations centers | Value | 0.00 | 0.00 | 20.00 |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |
Satisfaction of end-users with geophysical information services | Value | 0.00 | 60.29 | 60.00 |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Multi-hazard early warning system platform established and operational | Value | No | No | Yes |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |
Local governments served by seismic information services | Value | 0.00 | 70.00 | 50.00 |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |
Grievance redress mechanism established and functioning | Value | No | Yes | Yes |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |
Functional emergency operations centers upgraded and meet minimum standards | Value | 0.00 | 0.00 | 20.00 |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |
Equipment installed by the project and functioning in line with established SOPs | Value | 0.00 | 36.00 | 80.00 |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |
Complaints resolved | Value | 0.00 | 33.00 | 90.00 |
Date | July 1, 2019 | December 13, 2023 | December 31, 2024 | |
Comment |
Share of registered users of mobile phone applications designed for early warning dissemination that are women | Value | 0.00 | 0.00 | 45.00 |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |
Government officials (disaggregated by gender) that have been trained by capacity building programs | Value | 0.00 | 424.00 | 800.00 |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |
People (disaggregated by gender) who believe they are prepared to respond to natural disasters after participating in outreach, training and advocacy activities | Value | 0.00 | 0.00 | 80.00 |
Date | July 1, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Women facilitators hired and trained to undertake outreach, training and advocacy activities | Value | 0.00 | 49.50 | 45.00 |
Date | July 1, 2019 | December 12, 2023 | December 31, 2024 | |
Comment |