Kenya Digital Economy Acceleration Project

Abstract*

The proposed program (MPA) harnesses opportunities to develop a vibrant, safe and inclusive digital economy in Kenya and its neighbors as a driver of growth and job creation and leveraging digital technologies to improve service delivery and resilience. It also supports efforts to promote digital inclusion and mitigate growing digital era risks related to data protection and cybersecurity to ensure that every individual and business has the opportunity...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To expand access to high-speed internet, improve the quality and delivery of education and selected government services, and build skills for the regional digital economy

Key Details

Project Details

  • P170941

  • Active

  • Timothy Kelly , Onur Erdem, Aneliya Muller

  • Republic of Kenya

  • Kenya

  • October 20, 2020

  • (as of board presentation)

    March 31, 2023

  • February 2, 2024

  • US$ 350.00 million

  • Information Communications Technology Authority (ICTA),Ministry of Information, Communications and Digital Economy (MICDE)

  • Eastern and Southern Africa

  • 2023

  • US$ 390.00 million

  • N/A

  • Moderate

  • October 31, 2028

  • Yes

  • BANK APPROVED

  • February 13, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 390.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 390.00
IBRD + IDA Commitment 390.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 350.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 31, 2023 IDA-72890 Loan Commitment 330,000,000.00
Mar 31, 2023 IDA-72900 Loan Commitment 60,000,000.00
Jun 27, 2024 IDA-72890 Loan Disb 3,059,203.20

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2025-06-25
Project Management Moderately Satisfactory 2025-06-25
Procurement Moderately Satisfactory 2025-06-25
Progress towards achievement of PDO Moderately Satisfactory 2025-06-25
Financial Management Moderately Satisfactory 2025-06-25
Monitoring and Evaluation Moderately Satisfactory 2025-06-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Public institutions provided with new or enhanced access to high-speed internet under the projectValue0.000.00500.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • Transactional government services digitized under the projectValue0.000.0020.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • Percentage of high-speed internet users who are femaleValue44.5044.5046.00
    DateDecember 31, 2019December 31, 2019October 31, 2028
    Comment
  • Number of optical fiber border crossings with neighboring countriesValue8.008.0012.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • Students, provided with new or enhanced access to high-speed internet under the projectValue0.000.001000000.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • People provided with enhanced digital skills training under the projectValue0.000.0010000.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • People provided with enhanced digital skills training under the project, of which femaleValue0.000.003000.00
    Date
    Comment
  • Students, provided with new or enhanced access to high-speed internet under the project, of which femaleValue0.000.00500000.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • Estimated percentage of the population who are users of high-speed internetValue22.5728.7630.00
    DateDecember 31, 2019December 31, 2021October 31, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average download speed on fixed broadband networks, in Mbit/sValue8.929.9524.00
    DateNovember 30, 2022October 31, 2023October 31, 2028
    Comment
  • Number of MCDAs benefitting from new or enhanced access to high-speed internet under the projectValue0.000.00105.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • Number of people receiving training in advanced digital skills under the projectValue0.000.005000.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • Percentage of grievances registered with PIU that received a satisfactory response within statutory timeValue0.000.0080.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • Used international internet bandwidth. in Gbit/sValue3298.004746.0030000.00
    DateDecember 31, 2021December 31, 2022October 31, 2028
    Comment
  • Number of Government staff benefitting from Unified Communication ServiceValue0.000.0010000.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • Estimated volume of Private Capital Mobilized by Project InvestmentsValue0.000.00130000000.00
    DateDecember 31, 2021June 19, 2023December 31, 2028
    Comment
  • Number of women and girls receiving training in digital skills and digital literacy, under the projectValue0.000.002500.00
    DateNovember 30, 2022June 19, 2023October 31, 2028
    Comment
  • Increase in the kilometers of climate-resilient fiber in the national backbone and cross-border networkValue8900.009530.0050000.00
    DateJune 30, 2022October 31, 2023October 31, 2028
    Comment
  • Number of energy-efficient computers, laptops and tablets distributed to schools, TVETs and universities under the projectValue0.000.002000.00
    DateDecember 31, 2022June 19, 2023October 31, 2028
    Comment