Jamuna River Sustainable Management Project 1

Abstract*

The proposed Project is the first major investment to be implemented under the Bangladesh Delta Plan 2100 (BDP2100) and is the first of a Series of Projects (SoP) to be implemented within the next 14 years. The Project invests US$144.2 million over 5.5 years (including IDA credit of US$102.0 million), combining investments in river structures, navigation channel development, disaster risk financing solutions, community engagement, and institutional...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to increase capacity for flood management and navigation along the Jamuna River.

Key Details

Project Details

  • P172499

  • Active

  • Joop Stoutjesdijk , Cheick Diallo, Sumati Rajput

  • People's Republic of Bangladesh

  • Bangladesh

  • October 28, 2020

  • (as of board presentation)

    September 19, 2023

  • November 22, 2023

  • US$ 188.33 million

  • Insurance Development and Regulatory Authority (IDRA), Ministry of Finance (MoF),Bangladesh Water Development Board (BWDB), Ministry of Water Resources (MoWR),Bangladesh Inland Water Transport Authority (BIWTA), Ministry of Shipping (MoS)

  • South Asia

  • 2024

  • US$ 108.00 million

  • N/A

  • High

  • December 31, 2028

  • Yes

  • BANK APPROVED

  • October 4, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 30.00
Borrower/Recipient 30.20
IDA Shorter Maturity Loan (SML) 72.00
Global Risk Financing Facility Multi-Donor Trust Fund 6.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 102.00
IBRD + IDA Commitment 102.00
Lending Instrument
Grant Amount 6.00
Total Project Cost** 188.33

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 19, 2023 IDA-74100 Loan Commitment 30,000,000.00
Dec 13, 2023 IDA-74100 Fee Charges 73,331.20
Dec 13, 2023 IDA-74100 Loan Disb 73,331.20
Sep 19, 2023 IDA-74110 Loan Commitment 72,000,000.00
Jun 1, 2024 IDA-74100 Int Charges 1,745.28
Jun 1, 2024 IDA-74100 Int Charges 26,542.66

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2025-05-24
Financial Management Moderately Satisfactory 2025-05-24
Procurement Moderately Satisfactory 2025-05-24
Project Management Moderately Satisfactory 2025-05-24
Monitoring and Evaluation Satisfactory 2025-05-24
Overall Implementation Progress (IP) Moderately Satisfactory 2025-05-24

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.