Abstract*

Even after two decades of relative peace, more than half of Liberia’s population still lives in poverty, reflecting the scars of a devastating civil conflict and the Ebola crisis. Poverty—measured at the official national poverty line—increased from 54.1 percent in 2014 to 58.9 percent in 2016, driven by the Ebola crisis and the 2015 economic downturn. Persistent low income and low human capital continue to be the main barriers to progress, perpetuating...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase access to income-earning opportunities for the vulnerable in the informal sector in response to crises, expand income and livelihood support to poor and food insecure households, and improve efficiency in managing social protection programs in Liberia.

Key Details

Project Details

  • P174417

  • Active

  • Mack Mulbah

  • Republic of Liberia

  • Liberia

  • October 16, 2020

  • (as of board presentation)

    March 12, 2021

  • October 1, 2021

  • US$ 10.00 million

  • Ministry of Youth and Sports,Liberia Agency for Community Empowerment,Ministry of Gender, Children and Social Protection

  • Western and Central Africa

  • 2021

  • US$ 44.50 million

  • N/A

  • Substantial

  • December 31, 2026

  • Yes

  • BANK APPROVED

  • June 25, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
FRANCE: French Agency for Development 9.50
IDA Credit 25.00
Miscellaneous 1 5.00
IDA Grant 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 30.00
IBRD + IDA Commitment 30.00
Lending Instrument
Grant Amount 14.50
Total Project Cost** 10.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 15, 2022 IDA-68480 Int Charges 2,639.43
Oct 31, 2022 IDA-D7830 Loan Disb 273,842.12
Nov 29, 2021 IDA-D7830 Loan Disb 839,097.75
Dec 22, 2022 IDA-72660 Loan Commitment 20,000,000.00
Mar 12, 2021 IDA-D7830 Loan Commitment 5,000,000.00
Mar 12, 2021 IDA-68480 Loan Commitment 5,000,000.00
Feb 15, 2022 IDA-68480 Int Charges 2,639.43
Aug 15, 2022 IDA-68480 Int Charges 6,251.28
Aug 15, 2022 IDA-68480 Int Charges 6,251.28
Oct 28, 2022 IDA-68480 Loan Disb 273,842.12
Nov 29, 2021 IDA-68480 Loan Disb 839,097.75
Aug 24, 2023 IDA-72660 Loan Disb 3,007,808.20
Jun 21, 2024 IDA-72660 Loan Disb 2,838,533.20
Jul 12, 2024 IDA-D7830 Loan Disb 614,778.90
Apr 1, 2024 IDA-68480 Int Charges 19,940.72
Apr 1, 2024 IDA-68480 Int Charges 19,940.72
Aug 29, 2024 IDA-68480 Int Charges 20,357.14
Aug 29, 2024 IDA-68480 Int Charges 20,357.14
Feb 23, 2023 IDA-68480 Int Charges 7,464.02
Feb 23, 2023 IDA-68480 Int Charges 7,464.02
Jun 28, 2024 IDA-68480 Loan Disb 614,778.90
Aug 24, 2023 IDA-68480 Loan Disb 1,117,928.40
Aug 24, 2023 IDA-D7830 Loan Disb 1,117,928.40
Sep 29, 2023 IDA-68480 Int Charges 10,845.14
Sep 29, 2023 IDA-68480 Int Charges 10,845.14
Apr 12, 2023 IDA-D7830 Loan Disb 501,632.84
Apr 12, 2023 IDA-68480 Loan Disb 501,632.84

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2025-07-28
Project Management Moderately Satisfactory 2025-07-28
Progress towards achievement of PDO Satisfactory 2025-07-28
Procurement Satisfactory 2025-07-28
Financial Management Moderately Satisfactory 2025-07-28
Monitoring and Evaluation Moderately Satisfactory 2025-07-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of small businesses that are invested in by beneficiary householdsValue0.001072.002424.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Project beneficiaries of the CLAS programValue0.005000.006200.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Social Protection programs utilizing the LHSRValue2.003.006.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Cash transfer payments delivered to beneficiaries on-timeValue0.000.0075.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Share of female-led small businesses that are invested in by beneficiary householdsValue0.000.000.00
    Date
    Comment
  • Female project beneficiaries of the CLAS programValue0.000.000.00
    Date
    Comment
  • Project beneficiaries of the CLAS program who are persons with disabilitiesValue0.000.000.00
    Date
    Comment
  • Project beneficiaries of the SCT programValue0.00550.0016000.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Number of project beneficiaries of the labor-intensive public works programValue0.005740.0017000.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Female cash recipients of the SCT programValue0.000.000.00
    Date
    Comment
  • Project beneficiaries of the SCT program with at least one person with disabilities in their householdsValue0.000.000.00
    Date
    Comment
  • Share of female project beneficiaries of the labor-intensive public works programValue0.000.000.00
    Date
    Comment
  • Project beneficiaries of the labor intensive public works program who are persons with disabilitiesValue0.001.100.00
    Date
    Comment
  • Number of project beneficiaries who have completed the Life Skills and Employability trainingValue0.004966.0017000.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Share of female project beneficiaries who have completed the Life Skills and Employability trainingValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Households enrolled in Component 1 registered in Liberia Household Social RegistryValue0.0057.60100.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Beneficiaries of social safety net programsValue0.005000.0031000.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Beneficiaries of social safety net programsValue0.00550.0080000.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Work-days created by the project under labor-intensive public works programValue0.00599460.001020000.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Households benefitting from grant support program under Component 1Value0.002811.004450.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Beneficiaries of Safety Nets programs - Cash-for-work, food-for-work and public works (number)Value0.005000.0031000.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Labor-intensive public works program beneficiaries that receive their final wage payment within two weeks of completing 60 days of workValue0.0043.5090.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Beneficiaries of Safety Nets programs - Unconditional cash transfers (number)Value0.00550.0080000.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Households with female representative benefitting from grant support program under Component 1Value0.000.000.00
    Date
    Comment
  • Households enrolled in Component 1 with representatives that are registered for mobile moneyValue0.0099.2090.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Households enrolled in Component 1 with female representatives that are registered for mobile moneyValue0.000.000.00
    Date
    Comment
  • Labor-intensive public works program beneficiaries satisfied with the project interventionsValue0.000.0080.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • SCT payments delivered on timeValue0.000.0075.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Enrolled beneficiary households that receive the full grant payments under Component 1Value0.0034.8060.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Farming communities practicing improved and climate resistant farming methods with access to market informationValue0.000.0060.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Female labor-intensive public works program beneficiaries satisfied with the project interventionsValue0.000.0080.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Labor-intensive public works program beneficiaries registered in Liberia Household Social RegistryValue0.0055.20100.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • CLAS program beneficiaries that receive full payment of labor subsidyValue0.000.0080.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Households registered in the LHSRValue0.00282.0050000.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • New businesses started in a male-dominated field by female grant recipients in Component 1Value0.000.0050.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Labor-intensive public works program beneficiaries registered for mobile moneyValue0.0099.0090.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Beneficiaries satisfied with the project interventions under Component 1Value0.000.0080.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Male labor-intensive public works program beneficiaries satisfied with the project interventionsValue0.000.0080.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Female CLAS program beneficiaries that receive full payment of labor subsidyValue0.000.000.00
    Date
    Comment
  • Community development plan funded by the project benefiting to the community membersValue0.000.00222.00
    DateNovember 1, 2022June 7, 2024December 31, 2026
    Comment
  • Female beneficiaries satisfied with the project interventions under Component 1Value0.000.0080.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Public work projects initiated in poor communitiesValue0.00230.00600.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Share of female labor-intensive public works program beneficiaries registered for mobile moneyValue0.000.000.00
    Date
    Comment
  • Male beneficiaries satisfied with the project interventions under Component 1Value0.000.0080.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Public work projects targeted to benefit/improve services for women/girlsValue0.000.000.00
    Date
    Comment
  • Complaints received by Project Grievance Redress Mechanism that are addressed within 4 weeksValue0.0099.9080.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Beneficiaries of labor market programsValue0.0014132.0022250.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Public work projects aimed at climate mitigation/adaptationValue0.000.000.00
    Date
    Comment
  • Beneficiaries of social safety net programsValue0.0024769.0085000.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Beneficiaries of labor market programs - FemaleValue0.000.000.00
    Date
    Comment
  • Individuals who have completed the business skills trainingValue0.003055.004450.00
    DateNovember 23, 2022June 7, 2024December 31, 2026
    Comment
  • Beneficiaries of Safety Nets programs - Cash-for-work, food-for-work and public works (number)Value0.0024769.0085000.00
    DateNovember 23, 2020June 7, 2024December 31, 2026
    Comment
  • Female individuals who have completed the business skills trainingValue0.0081.800.00
    Date
    Comment