Skip to Main Navigation

Integrated Land Administration and Spatial Planning Project

Abstract*

More than 60 percent of the emission reduction target in Indonesia’s Enhanced Nationally Determined Contributions (NDC) is set to be achieved through actions in the Forestry and Other Land Use (FOLU) sector. To this end, this project will support climate-informed spatial planning; (ii) advance Agrarian Reform through the registration of lands to enhance sustainable land use management and promote social inclusion; (iii) support the development of...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

to strengthen climate-informed spatial planning, land tenure security and land administration in Indonesia

Key Details

Project Details

  • P180860

  • Active

  • Willem Van Der Muur , Dong Kwak

  • Republic of Indonesia

  • Indonesia

  • May 30, 2023

  • (as of board presentation)

    September 30, 2024

  • December 23, 2024

  • US$ 0.00 million

  • Ministry of Home Affairs,Ministry of Agrarian Affairs and Spatial Planning / National Land Agency (ATR/BPN),Geospatial Information Agency

  • East Asia and Pacific

  • 2025

  • US$ 653.00 million

  • N/A

  • Substantial

  • November 30, 2029

  • No

  • BANK APPROVED

  • May 15, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 653.00
National Government 1.63

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 653.00
IDA Commitment N/A
IBRD + IDA Commitment 653.00
Lending Instrument
Grant Amount N/A
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2024-12-12
Progress towards achievement of PDO Satisfactory 2024-12-12
Financial Management Satisfactory 2024-12-12
Monitoring and Evaluation Satisfactory 2024-12-12
Procurement Satisfactory 2024-12-12
Project Management Satisfactory 2024-12-12

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.