Benin Second Boosting Inclusive Growth and Resilience DPF and PBG

Abstract*

The development objective of Second Boosting Inclusive Growth and Resilience Development Policy Financing (DPF) Project for Benin is to support the recipient's efforts to: (i) enhance private sector-led growth, (ii) boost domestic revenue collection, and (iii) strengthen social and climate resilience. The operation is aligned with the priority areas identified in the PAG II 2021-2026 as well as with other World Bank strategies. The program is also...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to support the recipient's efforts to: (i) enhance private sector-led growth, (ii) boost domestic revenue collection, and (iii) strengthen social and climate resilience.

Key Details

Project Details

  • P181457

  • Active

  • Felix Oppong , Van Vu Hong, Vincent Launay

  • REPUBLIC OF BENIN

  • Benin

  • January 31, 2024

  • (as of board presentation)

    October 31, 2024

  • November 26, 2024

  • US$ 0.00 million

  • Ministry of Economy and Finance

  • Western and Central Africa

  • 2025

  • US$ 150.00 million

  • N/A

  • Not Applicable

  • December 31, 2025

  • BANK APPROVED

  • P180286

  • January 24, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Guarantee 221.50
IDA Credit 118.60
IDA Shorter Maturity Loan (SML) 31.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 150.00
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Program Management Satisfactory 2025-05-08
Overall Implementation Progress (IP) Satisfactory 2025-05-08
Progress towards achievement of PDO Satisfactory 2025-05-08
Monitoring and Evaluation Satisfactory 2025-05-08

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.