Financier | Commitments |
---|---|
Borrower/Recipient | 326.30 |
Montreal Protocol Investment Fund | 168.00 |
P115561
Closed
Viraj Vithoontien
People's Republic of China
August 10, 2010
(as of board presentation)
November 22, 2012
January 4, 2013
US$ 494.30 million
FOREIGN ECONOMIC COOPERATION CENTER (FECO)
2013
US$ 168.00 million
B
Not Applicable
June 30, 2019
BANK APPROVED
July 16, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 326.30 |
Montreal Protocol Investment Fund | 168.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 168.00 |
Total Project Cost** | 494.30 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2018-12-24 |
Summary Global Objective Rating | Satisfactory | 2018-12-24 |
Project Management | Satisfactory | 2018-12-24 |
Financial Management | Satisfactory | 2018-12-24 |
Monitoring and Evaluation | Satisfactory | 2018-12-24 |
Counterpart Funding | Satisfactory | 2018-12-24 |
Overall Implementation Progress (IP) | Satisfactory | 2018-12-24 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-18-2019 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 05-26-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction of GHG Emission from the PU Foam Sector | Value | N/A | 12.2 million tCO2e (tonnes of CO2 equivalent) | |
Date | January 2, 2012 | October 1, 2019 | ||
Comment |
Production of HCFC 141B, HCFC 142B and HCFC 22 within maximum allowable limits in 2013 and 2015 | Value | 29,122 ODP tons | 20,714 ODP tons | |
Date | November 12, 2012 | October 1, 2019 | ||
Comment |
Consumption of HCFC141B within Maximum Allowable Limits in 2013 and 2015 | Value | 5,393 ODP tons | 4,191 ODP tons | |
Date | November 12, 2012 | October 1, 2019 | ||
Comment |
Reduction of GHG from the Production Sector | Value | N/A | 182.7 million tCO2 (tonnes of CO2 equivalent) | |
Date | January 1, 2010 | October 1, 2019 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Implementation of key policies and regulations | Value | n/a | For the production sector, quotas have been establ | |
Date | November 12, 2012 | October 1, 2018 | ||
Comment |
Compliance with project reporting requirements | Value | 0.00 | 100.00 | 0.00 |
Date | November 12, 2012 | June 1, 2018 | ||
Comment |
Project Progress reports prepared | Value | 0.00 | 100.00 | 0.00 |
Date | November 12, 2012 | October 1, 2018 | ||
Comment |
Number of enterprises covered by contracts | Value | 0.00 | 58.00 | 0.00 |
Date | November 12, 2012 | October 1, 2018 | ||
Comment |
Number of phaseout contracts signed with HCFC producer | Value | 0.00 | 21.00 | 0.00 |
Date | November 12, 2012 | October 1, 2018 | ||
Comment |