Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 32.00 |
Borrower/Recipient | 42.10 |
P151972
Closed
Simon O'Meally , Zahid Hasnain
Republic of Albania
June 25, 2015
(as of board presentation)
August 25, 2015
March 22, 2016
US$ 74.10 million
Agency for Delivery of Integrated Services in Albania (ADISA)
2016
US$ 32.00 million
B
July 15, 2022
December 31, 2020
TBD
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 32.00 |
Borrower/Recipient | 42.10 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 32.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 32.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 74.10 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 10, 2016 | IBRD-85210 | Loan Disb | -898,185.06 |
Nov 7, 2016 | IBRD-85210 | Loan Disb | 278,539.90 |
Jun 7, 2016 | IBRD-85210 | Loan Disb | 454,400.00 |
Dec 28, 2016 | IBRD-85210 | Loan Disb | 304,804.06 |
Jan 15, 2017 | IBRD-85210 | Int Charges | 32,020.46 |
Jan 15, 2017 | IBRD-85210 | Int Charges | 23,558.03 |
Jan 15, 2017 | IBRD-85210 | Int Charges | 1,889.72 |
Jan 15, 2017 | IBRD-85210 | Int Charges | 659.99 |
Jun 22, 2017 | IBRD-85210 | Loan Disb | 327,820.06 |
Nov 9, 2017 | IBRD-85210 | Loan Disb | 4,248,600.00 |
Apr 18, 2017 | IBRD-85210 | Loan Disb | 353,628.40 |
Jul 15, 2017 | IBRD-85210 | Int Charges | 94.11 |
Jul 15, 2017 | IBRD-85210 | Int Charges | 31,107.00 |
Jul 15, 2017 | IBRD-85210 | Int Charges | 32,171.48 |
Aug 25, 2015 | IBRD-85210 | Loan Commitment | 32,000,000.00 |
Jan 15, 2024 | IBRD-85210 | Int Charges | 718,373.50 |
Jan 15, 2024 | IBRD-85210 | Loan Repay | 1,184,373.80 |
Jul 15, 2024 | IBRD-85210 | Int Charges | 674,604.20 |
Jul 15, 2024 | IBRD-85210 | Loan Repay | 1,180,532.50 |
Jan 15, 2023 | IBRD-85210 | Int Charges | 211,228.61 |
Jan 15, 2023 | IBRD-85210 | Loan Repay | 1,169,928.20 |
Jul 15, 2023 | IBRD-85210 | Int Charges | 582,336.56 |
Jul 15, 2023 | IBRD-85210 | Loan Repay | 1,214,076.50 |
Jan 15, 2022 | IBRD-85210 | Int Charges | -712.06 |
Jan 15, 2022 | IBRD-85210 | Int Charges | 712.06 |
Jan 15, 2022 | IBRD-85210 | Int Charges | 79,900.76 |
Apr 27, 2021 | IBRD-85210 | Loan Disb | 686,168.30 |
Jul 15, 2021 | IBRD-85210 | Int Charges | 2,230.47 |
Jul 15, 2021 | IBRD-85210 | Int Charges | 77,573.38 |
Jul 15, 2021 | IBRD-85210 | Int Charges | 585.05 |
Jul 15, 2021 | IBRD-85210 | Int Charges | 1,005.61 |
Apr 30, 2021 | IBRD-85210 | Loan Cancel | 1,442,867.40 |
Jul 15, 2022 | IBRD-85210 | Int Charges | 66,806.89 |
Aug 11, 2020 | IBRD-85210 | Loan Disb | 302,183.12 |
Jul 15, 2020 | IBRD-85210 | Int Charges | 90,024.09 |
Jul 15, 2020 | IBRD-85210 | Int Charges | 9,117.36 |
Jan 15, 2021 | IBRD-85210 | Int Charges | 97,418.83 |
Dec 28, 2020 | IBRD-85210 | Loan Disb | 121,945.00 |
Dec 28, 2020 | IBRD-85210 | Loan Disb | 387,508.53 |
Dec 28, 2020 | IBRD-85210 | Loan Disb | 4,390,020.00 |
Jan 15, 2021 | IBRD-85210 | Int Charges | 8,294.05 |
Apr 6, 2021 | IBRD-85210 | Loan Disb | 22,487.40 |
Apr 29, 2021 | IBRD-85210 | Loan Disb | -64.93 |
Apr 29, 2021 | IBRD-85210 | Loan Disb | -1,107.67 |
Mar 14, 2019 | IBRD-85210 | Loan Disb | 383,523.16 |
Jul 15, 2019 | IBRD-85210 | Int Charges | 1,968.25 |
Jul 15, 2019 | IBRD-85210 | Int Charges | 3,858.85 |
Jul 15, 2019 | IBRD-85210 | Int Charges | 13,082.11 |
Jul 15, 2019 | IBRD-85210 | Int Charges | 85,944.90 |
Oct 8, 2019 | IBRD-85210 | Loan Disb | 313,902.60 |
Aug 23, 2019 | IBRD-85210 | Loan Disb | 2,211,000.00 |
Feb 3, 2020 | IBRD-85210 | Loan Disb | 280,211.20 |
Sep 19, 2019 | IBRD-85210 | Loan Disb | 171,036.10 |
Jan 15, 2020 | IBRD-85210 | Int Charges | 10,421.40 |
Jan 15, 2020 | IBRD-85210 | Int Charges | 82,285.45 |
May 14, 2020 | IBRD-85210 | Loan Disb | 539,600.00 |
Jul 15, 2017 | IBRD-85210 | Int Charges | 41.15 |
Oct 13, 2017 | IBRD-85210 | Loan Disb | 308,020.34 |
Jan 15, 2018 | IBRD-85210 | Int Charges | 30,911.88 |
Jan 15, 2018 | IBRD-85210 | Int Charges | 42,457.26 |
Jan 23, 2018 | IBRD-85210 | Loan Disb | 396,346.10 |
Jan 15, 2018 | IBRD-85210 | Int Charges | 56.69 |
Jan 15, 2018 | IBRD-85210 | Int Charges | 120.33 |
Jul 15, 2018 | IBRD-85210 | Int Charges | 24,868.99 |
Jul 15, 2018 | IBRD-85210 | Int Charges | 51,382.91 |
Nov 9, 2018 | IBRD-85210 | Loan Disb | 3,179,260.00 |
Jan 15, 2019 | IBRD-85210 | Int Charges | 21,175.62 |
Jan 15, 2019 | IBRD-85210 | Int Charges | 56,383.38 |
Oct 22, 2018 | IBRD-85210 | Loan Disb | 351,069.30 |
Nov 20, 2018 | IBRD-85210 | Loan Disb | 5,201,560.00 |
Mar 22, 2016 | IBRD-85210 | Loan Disb | 82,131.56 |
Mar 22, 2016 | IBRD-85210 | Fee Charges | 82,131.56 |
Mar 22, 2016 | IBRD-85210 | Loan Disb | 986,118.10 |
Jul 15, 2016 | IBRD-85210 | Int Charges | 51,103.05 |
Jul 15, 2016 | IBRD-85210 | Int Charges | 3,220.03 |
Sep 16, 2016 | IBRD-85210 | Loan Disb | 337,944.44 |
Jan 26, 2017 | IBRD-85210 | Loan Disb | 1,395,095.00 |
Jun 22, 2016 | IBRD-85210 | Loan Disb | 5,075,080.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2020-12-18 |
Financial Management | Satisfactory | 2020-12-18 |
Monitoring and Evaluation | Satisfactory | 2020-12-18 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-12-18 |
Counterpart Funding | Satisfactory | 2020-12-18 |
Procurement | Satisfactory | 2020-12-18 |
Project Management | Satisfactory | 2020-12-18 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-21-2021 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Time taken to obtain motor vehicle registration | Value | 5.30 | 4.00 | 0.00 |
Date | May 31, 2016 | December 31, 2020 | ||
Comment |
Access to services for the poor and vulnerable: Percentage of the poor who stated that receiving services from institutions contacted was "easy" or "very easy" | Value | 50.00 | 70.00 | 0.00 |
Date | May 31, 2016 | December 31, 2020 | ||
Comment |
Time taken to process old age pension application | Value | 53.00 | 40.00 | 0.00 |
Date | May 31, 2016 | December 31, 2020 | ||
Comment |
Access to the poor and vulnerable: Percentage of the Roma who stated that receiving services from institutions contacted was "easy"or "very easy" | Value | 52.00 | 72.00 | 0.00 |
Date | May 31, 2016 | December 31, 2020 | ||
Comment |
Time taken to obtain health insurance card | Value | 5.50 | 4.00 | 0.00 |
Date | May 31, 2016 | December 31, 2020 | ||
Comment |
Access to services for the poor and vulnerable: Percentage of females who stated that receiving services from institutions contacted was "easy" or "very easy" | Value | 50.00 | 71.00 | 0.00 |
Date | May 31, 2016 | December 31, 2020 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Agencies with new or enhanced backend IT systems to improve service delivery | Value | 0.00 | 8.00 | 3.00 |
Date | April 29, 2015 | December 31, 2020 | ||
Comment |
Services offered with improved customer service front office interface | Value | 0.00 | 130.00 | 70.00 |
Date | April 29, 2015 | December 31, 2020 | ||
Comment |
Number of institutions with proactive citizen feedback mechanisms implemented | Value | 1.00 | 8.00 | 5.00 |
Date | April 29, 2015 | December 31, 2020 | ||
Comment |
Priority services with business process reengineered | Value | 0.00 | 100.00 | 70.00 |
Date | April 29, 2015 | December 31, 2020 | ||
Comment |
Services with information available on multiple platforms | Value | 0.00 | 130.00 | 0.00 |
Date | April 29, 2015 | December 31, 2020 | ||
Comment |
Institutional pre-requisites of Citizen Centric Service Delivery Program | Value | No | Yes | |
Date | April 29, 2015 | December 31, 2020 | ||
Comment |
New services with level 3 automation | Value | 0.00 | 75.00 | 35.00 |
Date | June 15, 2015 | December 31, 2020 | ||
Comment |
Institutions with key performance indicators reported and quarterly performance reports circulated | Value | 0.00 | 8.00 | 4.00 |
Date | April 29, 2015 | December 31, 2020 | ||
Comment |
Number of registered users accessing e-government services (as percentage of adult population) | Value | 2.25 | 3.60 | 0.00 |
Date | December 31, 2015 | December 31, 2020 | ||
Comment |
The amount of data prefilled in public services' online forms | Value | 58.40 | 71.00 | 0.00 |
Date | December 30, 2016 | December 31, 2020 | ||
Comment |