Financier | Commitments |
---|---|
Borrower/Recipient | 0.50 |
IDA Grant | 9.00 |
P163131
Active
Bonnie Sirois , Elena Georgieva-Andonovska, Pike Aye
The Republic of the Marshall Islands
September 29, 2017
(as of board presentation)
May 30, 2018
October 1, 2018
US$ 9.50 million
Ministry of Finance
2018
US$ 9.00 million
B
June 6, 2024
March 31, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 0.50 |
IDA Grant | 9.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 9.00 |
IBRD + IDA Commitment | 9.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 9.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 25, 2024 | IDA-D3220 | Loan Disb | 82,385.10 |
May 18, 2022 | IDA-D3220 | Loan Disb | 819,534.94 |
May 18, 2022 | IDA-D3220 | Loan Disb | 157,314.14 |
Jan 25, 2022 | IDA-D3220 | Loan Disb | 182,300.22 |
Jan 20, 2022 | IDA-D3220 | Loan Disb | 199,598.60 |
Dec 17, 2020 | IDA-D3220 | Loan Disb | 270,331.62 |
Jun 16, 2021 | IDA-D3220 | Loan Disb | 199,864.27 |
Jun 24, 2019 | IDA-D3220 | Loan Disb | 186,305.56 |
Mar 22, 2019 | IDA-D3220 | Loan Disb | 125,965.08 |
Oct 1, 2018 | IDA-D3220 | Loan Disb | 200,000.00 |
Apr 1, 2020 | IDA-D3220 | Loan Disb | 195,955.52 |
Jun 29, 2020 | IDA-D3220 | Loan Disb | 187,257.55 |
Feb 24, 2021 | IDA-D3220 | Loan Disb | 197,092.11 |
May 30, 2018 | IDA-D3220 | Loan Commitment | 9,000,000.00 |
Feb 2, 2023 | IDA-D3220 | Loan Disb | 1,321,745.40 |
Jan 9, 2023 | IDA-D3220 | Loan Disb | 195,181.30 |
Jan 9, 2023 | IDA-D3220 | Loan Disb | 193,323.30 |
Jan 9, 2023 | IDA-D3220 | Loan Disb | 195,416.16 |
Jan 9, 2023 | IDA-D3220 | Loan Disb | 32,520.51 |
Jan 9, 2023 | IDA-D3220 | Loan Disb | 197,126.28 |
Aug 9, 2024 | IDA-D3220 | Loan Disb | 46,333.64 |
Nov 16, 2023 | IDA-D3220 | Loan Disb | 534,210.30 |
Nov 7, 2023 | IDA-D3220 | Loan Disb | 199,395.06 |
Nov 10, 2023 | IDA-D3220 | Loan Disb | 198,235.70 |
Apr 16, 2024 | IDA-D3220 | Loan Disb | 4,905.40 |
Feb 23, 2024 | IDA-D3220 | Loan Disb | 102,509.42 |
Apr 16, 2024 | IDA-D3220 | Loan Disb | 73,066.54 |
Feb 14, 2024 | IDA-D3220 | Loan Disb | 199,326.39 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2024-11-20 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-20 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-11-20 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-11-20 |
Procurement | Moderately Satisfactory | 2024-11-20 |
Project Management | Moderately Satisfactory | 2024-11-20 |
Financial Management | Moderately Satisfactory | 2024-11-20 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PDO-1: Completeness, quality and timeliness criteria met for Annual Financial Statements by MoF | Value | Single audit submission deadline (9 months after y | Year 4 target delayed, FY23 will be the first year | AFS for FY2022 submitted for audit by Dec 31, 2022 |
Date | June 29, 2018 | March 31, 2024 | June 30, 2023 | |
Comment |
PDO-2: Production, publication of statistical abstract featuring key findings from the HIES | Value | No HIES data available since 2002 | Achieved | Statistical abstract featuring key findings from H |
Date | June 29, 2018 | March 31, 2024 | March 31, 2021 | |
Comment |
PDO-3: New FMIS used for preparation of budget and recording of revenue and expenditure transactions | Value | Accounting software 4-Gov in use but being phased | Achieved | New FMIS used for recording revenue and expenditur |
Date | June 29, 2018 | March 31, 2024 | July 31, 2023 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
IR-1: Procedures Manual updated with detailed guidance | Value | As-is manuals for three functions available | Year 2: achieved. Year 3 in progress. Year 4 delay | Procedures Manual in place with detailed guidance |
Date | June 29, 2018 | March 31, 2024 | March 31, 2022 | |
Comment |
IR-4: Financial data integrity achieved to meet “B” score for PI-27 | Value | “D” score in 2012 PEFA PI-22. Bank account reconci | Year 1 and 3 achieved – workflows documented. Year | Criteria for “B” score for PI-27 fully met |
Date | June 29, 2018 | March 31, 2024 | December 31, 2022 | |
Comment |
IR-6: Competency framework with gender targets adopted for PFM related jobs across govt | Value | No competencies for PFM related roles defined. Gen | Year 1 and 2 achieved. Year 3 partially achieved – | Competency framework specifying minimum skillsets |
Date | June 29, 2018 | March 31, 2024 | June 30, 2023 | |
Comment |
IR-12: Household Income and Expenditure Survey (HIES) fieldwork and data cleaning completed | Value | HIES not conducted since 2002 | Achieved | HIES data cleaning completed and documented |
Date | June 30, 2018 | March 31, 2024 | December 31, 2020 | |
Comment |
IR-2: New chart of accounts adopted to facilitate management, financial and statistical reporting | Value | “D” score in 2012 PEFA PI-5; economic classificati | Achieved | New COA meets criteria for "A" score for PI-4 |
Date | June 29, 2018 | March 31, 2024 | December 30, 2020 | |
Comment |
IR-5: In-year budget reports prepared and published by MoF to meet PEFA Framework “B” score of PI-28 | Value | In-year budget reports not prepared and not publis | Yr 1 achieved. Yr 2-4 in progress | In-year budget reports prepared and cleared for pu |
Date | June 29, 2018 | March 31, 2024 | June 30, 2023 | |
Comment |
IR-7: Number of staff completing external training programs in PFM related disciplines | Value | 0.00 | 129.00 | 50.00 |
Date | June 29, 2018 | March 31, 2024 | September 30, 2023 | |
Comment |
IR-3: Update to Public Procurement Code and Implementation Guidance issued | Value | Code in need of update and no implementation guida | Year 1 and 2 achieved. Year 3 in progress – IRR de | Updated Public Procurement Code and IRR in use for |
Date | June 29, 2018 | March 31, 2024 | June 30, 2023 | |
Comment |
IR-8: Gender-sensitive communications conducted for the project for awareness and building ownership | Value | No communication strategy; regular updates and inf | Year 1, 2 and 3 partially achieved. Year 4 delayed | MoF website enhanced and regularly updated with in |
Date | June 29, 2018 | March 31, 2024 | June 30, 2023 | |
Comment |
IR-9: Transparency and citizen engagement in budget preparation and execution | Value | MoF website exists but does not provide platform f | Year 3 partially achieved. Year 4 delayed – Citize | MoF website includes functionality to capture citi |
Date | April 30, 2018 | March 31, 2024 | June 25, 2024 | |
Comment |
IR-10: Training plan developed to meet standards set in competency framework and address skills gaps | Value | No training plans in place | Achieved | Training plans in place for MoF staff |
Date | June 29, 2018 | March 31, 2024 | January 31, 2022 | |
Comment |
IR-11: Number of external training program partnerships for certification and degree courses in PFM | Value | No external training program partnerships in place | Achieved | Four (4) external training program partnerships fo |
Date | June 30, 2018 | March 31, 2024 | June 30, 2023 | |
Comment |