Skip to Main Navigation

Sri Lanka Integrated Watershed and Water Resources Management Project

Abstract*

The objective of the Integrated Watershed and Water Resources Management Project for Sri Lanka is to improve watershed and water resources planning and enhance functionality of water resources infrastructure. The Project has four components. 1. Watershed and Water Resources Planning component has three subcomponents. 1.1. Watershed Management Planning subcomponent will support development of watershed management plan for the upper Mahaweli watershed...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to improve watershed and water resources planning and enhance functionality of water resources infrastructure.

Key Details

Project Details

  • P166865

  • Active

  • Thiruni Lekamwasam Liyanage

  • Democratic Socialist Republic of Sri Lanka

  • Sri Lanka

  • September 30, 2018

  • (as of board presentation)

    May 18, 2020

  • May 13, 2021

  • US$ 75.03 million

  • Ministry of Agriculture, Livestock, Land and Irrigation

  • South Asia

  • 2020

  • US$ 69.53 million

  • B

  • Not Applicable

  • October 31, 2026

  • Yes

  • BANK APPROVED

  • April 22, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 69.53
Borrower/Recipient 5.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 69.53
IBRD + IDA Commitment 69.53
Lending Instrument
Grant Amount N/A
Total Project Cost** 75.03

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 24, 2022 IDA-66210 Loan Disb 3,000,000.00
May 24, 2022 IDA-66210 Loan Disb 2,000,000.00
Nov 15, 2022 IDA-66210 Int Charges 26,437.86
Nov 15, 2022 IDA-66210 Int Charges 26,437.86
Nov 15, 2022 IDA-66210 Int Charges 45,354.52
Nov 15, 2022 IDA-66210 Int Charges 1,489.95
Nov 15, 2022 IDA-66210 Int Charges 1,489.95
Mar 30, 2023 IDA-66210 Loan Disb 2,000,000.00
May 15, 2023 IDA-66210 Int Charges 1,216.02
May 15, 2023 IDA-66210 Int Charges 30,737.99
May 15, 2023 IDA-66210 Int Charges 30,737.99
May 15, 2023 IDA-66210 Int Charges 45,576.18
Nov 15, 2023 IDA-66210 Int Charges 59,264.87
Nov 15, 2023 IDA-66210 Int Charges 5,585.13
Nov 15, 2023 IDA-66210 Int Charges 35,908.70
Nov 15, 2023 IDA-66210 Int Charges 35,908.70
Dec 13, 2023 IDA-66210 Loan Disb 2,000,000.00
Dec 13, 2023 IDA-66210 Loan Disb 2,000,000.00
Apr 4, 2024 IDA-66210 Loan Disb 2,000,000.00
May 15, 2024 IDA-66210 Int Charges 581.65
May 15, 2024 IDA-66210 Int Charges 50,154.85
May 15, 2024 IDA-66210 Int Charges 50,154.85
May 15, 2024 IDA-66210 Int Charges 79,859.87
Jun 24, 2024 IDA-66210 Loan Disb 3,000,000.00
Jun 28, 2021 IDA-66210 Loan Disb 3,000,000.00
May 15, 2022 IDA-66190 Int Charges 2,288.49
Nov 15, 2022 IDA-66190 Int Charges 33,154.80
Nov 15, 2022 IDA-66190 Int Charges 6,651.35
May 18, 2020 IDA-66190 Loan Commitment 26,700,000.00
May 18, 2020 IDA-66210 Loan Commitment 42,827,400.00
May 15, 2023 IDA-66190 Int Charges 550.33
May 15, 2023 IDA-66190 Int Charges 32,614.24
May 15, 2023 IDA-66190 Int Charges 10,538.72
Nov 15, 2023 IDA-66190 Int Charges 235.08
Nov 15, 2023 IDA-66190 Int Charges 33,154.80
Nov 15, 2023 IDA-66190 Int Charges 12,591.95
May 15, 2024 IDA-66190 Int Charges 32,727.97
May 15, 2024 IDA-66190 Int Charges 13,273.53
May 15, 2024 IDA-66190 Int Charges 77.37
May 13, 2021 IDA-66190 Loan Disb 66,750.00
May 13, 2021 IDA-66190 Fee Charges 66,750.00
May 13, 2021 IDA-66190 Loan Disb 325,635.44
Nov 15, 2021 IDA-66190 Int Charges 4.26
Nov 15, 2021 IDA-66190 Int Charges 26,487.81
Nov 15, 2021 IDA-66190 Int Charges 2,266.98
May 15, 2022 IDA-66190 Int Charges 32,614.24
Nov 15, 2021 IDA-66210 Int Charges 14,034.39
Nov 15, 2021 IDA-66210 Int Charges 8,420.63
Nov 15, 2021 IDA-66210 Int Charges 8,420.63
May 15, 2022 IDA-66210 Int Charges 336.76
May 15, 2022 IDA-66210 Int Charges 336.76
May 15, 2022 IDA-66210 Int Charges 14,975.09
May 15, 2022 IDA-66210 Int Charges 14,975.09
May 15, 2022 IDA-66210 Int Charges 25,519.76

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Unsatisfactory 2025-04-16
Project Management Satisfactory 2025-04-16
Financial Management Satisfactory 2025-04-16
Monitoring and Evaluation Satisfactory 2025-04-16
Progress towards achievement of PDO Moderately Satisfactory 2025-04-16
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-04-16

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Watershed Management plan developed for Upper Mahaweli WatershedValueNoNoYes
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Number of dams at riskValue36.0034.000.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Area provided with new/improved irrigation or drainage servicesValue0.003342.00164707.32
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Area provided with improved irrigation or drainage servicesValue0.003342.00164707.32
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Families directly benefiting from improved infrastructureValue0.002508.00356404.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Progress reports submitted timelyValueYesYesYes
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Number of dams rehabilitatedValue0.002.0036.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Grievances resolved within the standard timeValue0.0090.0080.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Number of HMIS stations installed and in-operationsValue0.000.00120.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Number of irrigation canals rehabilitatedValue0.003.0019.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Watershed Management committees with at least 50% female members, and two women in leadership and decision making rolesValue0.000.0050.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • O&M manuals developed,in useValue0.000.006.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Emergency preparedness plans developed for damsValue0.000.0012.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Farmers’ organizations with at least 50% female members, and two women in leadership and decision-making roles.Value0.0018.0050.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Guideline for dam safety inspection and monitoring preparedValueNoNoYes
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment
  • Annual reports on groundwater management disseminatedValue0.000.005.00
    DateMay 15, 2019January 31, 2024October 31, 2025
    Comment