Somalia - Horn of Africa Infrastructure Integration Project

Abstract*

The development objective of the Horn of Africa Infrastructure Integration Project for Somalia is to prepare a spatially coordinated investment pipeline of economic corridor projects, and to strengthen the national government’s management of selected sectors. The project comprises of five components. The first component, development of regional economic corridors will carry out the identification of a regional economic corridor, prioritizing corridor...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to prepare a spatially coordinated investment pipeline of economic corridor projects, and to strengthen the national government’s management of selected sectors.

Key Details

Project Details

  • P173119

  • Active

  • Susan Owuor , Alejandro Espinosa-Wang, Adam Diehl

  • Ministry of Finance, Federal Republic of Somalia

  • Somalia

  • February 8, 2021

  • (as of board presentation)

    September 30, 2022

  • May 31, 2023

  • US$ 63.00 million

  • Somaliland Ministry of Transport and Road Development,Ministry of Public Works, Reconstruction and Housing

  • Eastern and Southern Africa

  • 2023

  • US$ 63.00 million

  • N/A

  • June 29, 2024

  • September 30, 2026

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Horn of Africa Initiative Umbrella Trust Fund 5.00
IDA Grant 58.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 58.00
IBRD + IDA Commitment 58.00
Lending Instrument
Grant Amount 5.00
Total Project Cost** 63.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 30, 2022 IDA-E1270 Loan Commitment 58,000,000.00
Jul 31, 2023 IDA-E1270 Loan Disb 2,700,000.00
Dec 22, 2023 IDA-E1270 Loan Disb 241,752.56

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2025-02-06
Procurement Moderately Satisfactory 2025-02-06
Financial Management Moderately Satisfactory 2025-02-06
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-02-06
Project Management Moderately Satisfactory 2025-02-06
Monitoring and Evaluation Satisfactory 2025-02-06

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Value of spatially coordinated economic corridor pipeline projects ready for investmentValue0.000.00690000000.00
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • National Transport Policy developed and submitted to Cabinet for approvalValueNoNoYes
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Harmonized trade facilitation measures are piloted in at least two FMSValueNoNoYes
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Length of HoA Initiative identified economic corridor pipeline projects ready for investmentValue0.000.000.00
    Date
    Comment
  • # of staff FGS working for at least a month with the PCUValue0.006.0010.00
    DateSeptember 30, 2022January 17, 2024September 30, 2026
    Comment
  • of which femaleValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • The percentage of studies that collect sex disaggregated dataValue0.000.0080.00
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Number of formal stakeholder engagement events heldValue0.000.0010.00
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Priority economic corridor road designs prepared for investmentValue0.000.00550.00
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Transport climate resilience diagnosis conductedValueNoNoYes
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Number of FGS staff trained on financial or technical issuesValue0.000.0010.00
    DateSeptember 30, 2022January 26, 2023September 30, 2024
    Comment
  • Kilometers of road with aligned fiber optic or energy infrastructure studies preparedValue0.000.00200.00
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • National road safety diagnosis completedValueNoNoYes
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Capacity of the Ministry of Environment and Climate Change enhanced with the establishment of a nation-wide Environment and Social Management System (ESMS)ValueNoNoYes
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Kilometers of road connecting to primary economic corridors with designs preparedValue0.000.00900.00
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Pilot transit facilitation instrument developed and tested along selected priority corridorValueNoNoYes
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Collection of trade data along selected priority corridors and analysis of performance of cross-border tradeValueNoNoYes
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • Number of environmental and social specialists trained and certified in environmental and social impact assessment methodologiesValue0.000.0015.00
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment
  • # of prepared assessments/feasibility/designs for digital, ports, fisheries, and/or energy infrastructureValue0.000.005.00
    DateSeptember 30, 2022January 26, 2023September 30, 2026
    Comment