Financier | Commitments |
---|---|
Horn of Africa Initiative Umbrella Trust Fund | 5.00 |
IDA Grant | 58.00 |
P173119
Active
Susan Owuor , Alejandro Espinosa-Wang, Adam Diehl
Ministry of Finance, Federal Republic of Somalia
February 8, 2021
(as of board presentation)
September 30, 2022
May 31, 2023
US$ 63.00 million
Somaliland Ministry of Transport and Road Development,Ministry of Public Works, Reconstruction and Housing
2023
US$ 63.00 million
N/A
June 29, 2024
September 30, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Horn of Africa Initiative Umbrella Trust Fund | 5.00 |
IDA Grant | 58.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 58.00 |
IBRD + IDA Commitment | 58.00 |
Lending Instrument | |
---|---|
Grant Amount | 5.00 |
Total Project Cost** | 63.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 30, 2022 | IDA-E1270 | Loan Commitment | 58,000,000.00 |
Jul 31, 2023 | IDA-E1270 | Loan Disb | 2,700,000.00 |
Dec 22, 2023 | IDA-E1270 | Loan Disb | 241,752.56 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Unsatisfactory | 2025-02-06 |
Procurement | Moderately Satisfactory | 2025-02-06 |
Financial Management | Moderately Satisfactory | 2025-02-06 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2025-02-06 |
Project Management | Moderately Satisfactory | 2025-02-06 |
Monitoring and Evaluation | Satisfactory | 2025-02-06 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Value of spatially coordinated economic corridor pipeline projects ready for investment | Value | 0.00 | 0.00 | 690000000.00 |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
National Transport Policy developed and submitted to Cabinet for approval | Value | No | No | Yes |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Harmonized trade facilitation measures are piloted in at least two FMS | Value | No | No | Yes |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Length of HoA Initiative identified economic corridor pipeline projects ready for investment | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
# of staff FGS working for at least a month with the PCU | Value | 0.00 | 6.00 | 10.00 |
Date | September 30, 2022 | January 17, 2024 | September 30, 2026 | |
Comment |
of which female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
The percentage of studies that collect sex disaggregated data | Value | 0.00 | 0.00 | 80.00 |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Number of formal stakeholder engagement events held | Value | 0.00 | 0.00 | 10.00 |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Priority economic corridor road designs prepared for investment | Value | 0.00 | 0.00 | 550.00 |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Transport climate resilience diagnosis conducted | Value | No | No | Yes |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Number of FGS staff trained on financial or technical issues | Value | 0.00 | 0.00 | 10.00 |
Date | September 30, 2022 | January 26, 2023 | September 30, 2024 | |
Comment |
Kilometers of road with aligned fiber optic or energy infrastructure studies prepared | Value | 0.00 | 0.00 | 200.00 |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
National road safety diagnosis completed | Value | No | No | Yes |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Capacity of the Ministry of Environment and Climate Change enhanced with the establishment of a nation-wide Environment and Social Management System (ESMS) | Value | No | No | Yes |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Kilometers of road connecting to primary economic corridors with designs prepared | Value | 0.00 | 0.00 | 900.00 |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Pilot transit facilitation instrument developed and tested along selected priority corridor | Value | No | No | Yes |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Collection of trade data along selected priority corridors and analysis of performance of cross-border trade | Value | No | No | Yes |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
Number of environmental and social specialists trained and certified in environmental and social impact assessment methodologies | Value | 0.00 | 0.00 | 15.00 |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |
# of prepared assessments/feasibility/designs for digital, ports, fisheries, and/or energy infrastructure | Value | 0.00 | 0.00 | 5.00 |
Date | September 30, 2022 | January 26, 2023 | September 30, 2026 | |
Comment |