Assam Integrated River Basin Management Program

Abstract*

The proposed project would support the State of Assam to improve integrated basin planning, including addressing the key threats of flooding and erosion and making most productive use of the rich water resources. This will help achieve the higher-level objective of achieving water security to build the State’s climate resilience and launch it on a sustainable growth path, which will serve as a platform for broader transformation in the region. The...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To reduce the vulnerability of people to climate-related disasters and improve integrated water resources management in Assam.

Key Details

Project Details

  • P174593

  • Active

  • Greg Browder , Anup Karanth, Yukio Tanaka

  • India

  • India

  • December 10, 2020

  • (as of board presentation)

    March 24, 2023

  • July 28, 2023

  • US$ 135.00 million

  • Flood and River Erosion Management Agency of Assam,Government of Assam, Water Resources Department,Assam State Disaster Management Authority

  • South Asia

  • 2023

  • US$ 108.00 million

  • N/A

  • January 9, 2024

  • July 31, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 108.00
Borrower/Recipient 27.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 108.00
IDA Commitment N/A
IBRD + IDA Commitment 108.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 135.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 24, 2023 IBRD-94870 Loan Commitment 108,000,000.00
Aug 1, 2024 IBRD-94870 Loan Disb 34,917.55
Jul 15, 2024 IBRD-94870 Int Charges 192.78
Jun 27, 2024 IBRD-94870 Loan Disb 4,747,553.00
Jun 25, 2024 IBRD-94870 Loan Disb 3,711,251.00
May 16, 2024 IBRD-94870 Loan Disb 1,237,862.20
Mar 28, 2024 IBRD-94870 Loan Disb 2,812,657.00
Jul 15, 2024 IBRD-94870 Int Charges 242,080.62
Jul 15, 2024 IBRD-94870 Int Charges 123,190.08
Jul 15, 2024 IBRD-94870 Int Charges 5,355.20
Feb 21, 2024 IBRD-94870 Loan Disb 419,242.66
Sep 5, 2023 IBRD-94870 Loan Disb 1,379,676.50
Sep 5, 2023 IBRD-94870 Loan Disb 151,071.03
Sep 18, 2023 IBRD-94870 Loan Disb 3,324,343.80
Jul 28, 2023 IBRD-94870 Fee Charges 270,000.00
Jul 28, 2023 IBRD-94870 Loan Disb 270,000.00
Nov 17, 2023 IBRD-94870 Loan Disb 477,379.60
Jan 15, 2024 IBRD-94870 Int Charges 112,271.25
Jan 15, 2024 IBRD-94870 Int Charges 110,539.46

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2024-11-07
Overall Implementation Progress (IP) Satisfactory 2024-11-07
Progress towards achievement of PDO Satisfactory 2024-11-07
Procurement Satisfactory 2024-11-07
Project Management Satisfactory 2024-11-07
Financial Management Moderately Satisfactory 2024-11-07

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Adoption of Assam State Water PolicyValueNo state water policy in placeInitial discussions on state water policy have begWater Policy Approved by GoA
    DateJanuary 31, 2023June 1, 2023January 31, 2027
    Comment
  • People with enhanced flood protection in Beki and Buridehing.Value0.000.00100000.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • People receiving emergency alerts from State EOCValue0.000.006000000.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • People with improved flood forecasting informationValue0.000.004200000.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • People with access to new or enhanced flood sheltersValue0.000.0010000.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Riverbank and flood protection embankments improvedValue0.000.0040.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Completion of Assam Brahmaputra State of the Basin Report.ValueNoneDiscussions have started.State of the basin report completed.
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Flood Shelters constructed.Value0.000.0025.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Upgrading the flood forecasting system in three basinsValueNoneProcurement startedFlood Forecasting System operational
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Completion of Disaster Risk Financing StudyValueNoneProcurement StartedStudy report completed
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Upgraded State and District EOCs operational.ValueNoneDiscussion StartedUpgraded state EOC and 10 upgraded District EOCs o
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Preparation of IFRM PlansValueNoneProcurement started.Works procurement completed
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Completion of Flash Flood Forecasting StudyValueNoneDiscussions started.Report submitted
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • CQRT teams receiving basic trainingValue0.000.0039.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Collection of hydrological baseline dataValueNoneCollection UnderwayBaseline information utilized.
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Grievances from PAPs redressed satisfactorily within timelinesValue0.000.0085.00
    DateOctober 20, 2022June 1, 2023January 31, 2027
    Comment
  • Climate risk-informed VDMPs developed in a participatory manner with local communitiesValue0.000.0040.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Flood Embankment Asset Management ProgramValueNoneNot startedReport finalized
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • Flood shelter management committees have 40% female decision making membersValue0.000.0075.00
    DateJanuary 30, 2023June 1, 2023January 31, 2027
    Comment
  • VLCDMC have 40% female decision making membersValue0.000.0075.00
    DateJanuary 17, 2023June 1, 2023January 31, 2027
    Comment