Angola Strengthening Governance for Enhanced Service Delivery Project

Abstract*

These project will be delivered through a combination of technical assistance (TA) and PBCs. TA will be provided for capacity-building to strengthen the core functions of municipalities, including PFM, procurement, urban planning, and civil registry services. It will also finance investments in systems and infrastructure services to support improved administrative effectiveness and better services in the areas above. PBCs will support a municipal...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase the amount and reliability of fiscal transfers to selected municipalities; strengthen their public financial and land management capacity; and increase identity coverage.

Key Details

Project Details

  • P178040

  • Active

  • Eduardo Estrada , Belisario Carvalheda Dos Santos

  • Republic of Angola

  • Angola

  • February 7, 2022

  • (as of board presentation)

    December 21, 2022

  • September 14, 2023

  • US$ 250.00 million

  • Ministry of Public Works, Urbanism and Housing,Ministry of Finance,Ministry of Territorial Administration,Ministry of Justice and Human Rights,Ministry of Public Administration, Labor, and Social Security,National School of Administration and Public Policy

  • Eastern and Southern Africa

  • 2023

  • US$ 250.00 million

  • N/A

  • January 10, 2024

  • April 30, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 250.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 250.00
IDA Commitment N/A
IBRD + IDA Commitment 250.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 250.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 14, 2023 IBRD-94610 Loan Disb 625,000.00
Dec 21, 2022 IBRD-94610 Loan Commitment 250,000,000.00
Nov 15, 2023 IBRD-94610 Int Charges 258,522.12
Nov 15, 2023 IBRD-94610 Int Charges 6,623.42
Nov 15, 2023 IBRD-94610 Int Charges 6,623.42
Mar 14, 2024 IBRD-94610 Loan Disb 373,533.00
Apr 18, 2024 IBRD-94610 Loan Disb 70,000,000.00
May 15, 2024 IBRD-94610 Int Charges 297,135.94
May 15, 2024 IBRD-94610 Int Charges 23.67
Feb 8, 2024 IBRD-94610 Loan Disb 373,533.00
May 15, 2024 IBRD-94610 Int Charges 25,475.09
Feb 20, 2024 IBRD-94610 Loan Disb -373,301.62
Sep 14, 2023 IBRD-94610 Fee Charges 625,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2025-02-27
Project Management Moderately Satisfactory 2025-02-27
Overall Implementation Progress (IP) Moderately Satisfactory 2025-02-27
Progress towards achievement of PDO Moderately Satisfactory 2025-02-27
Financial Management Moderately Satisfactory 2025-02-27
Monitoring and Evaluation Moderately Satisfactory 2025-02-27

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Municipalities demonstrating strengthened capacity for managing Municipal Performance GrantsValue0.000.0058.00
    DateNovember 1, 2022March 21, 2023March 19, 2027
    Comment
  • Procurement practices enhanced in municipalitiesValue0.000.0058.00
    DateNovember 1, 2022March 21, 2023March 19, 2027
    Comment
  • Identity coverage of the populationValue40%40%55%
    DateNovember 1, 2022March 21, 2023March 19, 2027
    Comment
  • Public financial management practices strengthened in municipalitiesValue0.000.0058.00
    DateNovember 1, 2022March 21, 2023March 19, 2027
    Comment
  • Of which 50 percent of new ID cards for womenValue48.0048.0049.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Municipalities receiving Municipal Performance GrantsValue0.000.0058.00
    DateNovember 1, 2022March 21, 2023March 19, 2027
    Comment
  • Municipalities holding PFM training events for municipal level public servantsValueNo PFM training events for municipal level public No PFM training events for municipal level public Selected municipalities (58) had least 2 PFM train
    DateNovember 1, 2022March 21, 2023April 30, 2027
    Comment
  • Number of civil registration posts renovated or in new health facilitiesValue105.00105.00135.00
    DateNovember 1, 2022March 21, 2023March 19, 2027
    Comment
  • Of which at least x% of participants are femaleValue0.000.0025.00
    Date
    Comment
  • Elaboration of climate-informed Municipal Master Plans (PDMs) in selected municipalitiesValue0.000.0012.00
    DateNovember 1, 2022March 21, 2023March 19, 2027
    Comment
  • Implementation of SAGIT in selected municipalitiesValue0.000.0012.00
    DateNovember 1, 2022March 21, 2023March 19, 2027
    Comment
  • Training of CACs in PFMValueNo training of CACs on PFMNo training of CACs on PFMAll CACs in targeted municipalities trained on PFM
    DateNovember 1, 2022March 21, 2023December 31, 2027
    Comment
  • Of which at least x% of participants are femaleValue0.000.0030.00
    Date
    Comment
  • Implementation of Citizens' Portal in target municipalitiesValue0.000.0058.00
    DateNovember 1, 2022March 21, 2023March 19, 2027
    Comment
  • Municipalities holding consultations with citizens across the budget cycleValueNo guidelines exist for consultation with citizensNo guidelines exist for consultation with citizens30 target municipalities have held consultations o
    DateNovember 1, 2022March 21, 2023December 30, 2027
    Comment
  • Distribution of information regarding women’s property rights included as part of the participatory cadaster processValueNoNoYes
    DateNovember 1, 2022March 21, 2023April 30, 2027
    Comment
  • Number of participants in the participatory cadaster process conducted in the priority municipalitiesValue0.000.00100000.00
    DateNovember 1, 2022March 21, 2023April 30, 2027
    Comment
  • Of which femaleValue0.000.0050.00
    Date
    Comment