Vanuatu Affordable and Resilient Settlements Project

Resumo*

Component 1: Affordable and Resilient New Settlement Development This component will develop a new urban expansion area on 10 ha of public land in Etas, able to accommodate 171 households. The site is in a low-hazard area and connected to existing trunk infrastructure. The objective is to develop a replicable model for future urban expansion that is planned; has basic public infrastructure (roads, drainage, streetlights, sanitation) and amenities...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

The PDO is to: (i) improve access to and resilience of infrastructure and services in selected new and existing settlements, and (ii) strengthen land planning and management for resilient human settlement.

Chave Detalhes

Projeto Detalhes

  • P173278

  • Active

  • Andre Bald , Tevi Obed

  • Ministry of Finance and Economic Management

  • Vanuatu

  • 1 de junho de 2021

  • (conforme apresentação da Diretoria Executiva)

    17 de março de 2022

  • 5 de agosto de 2022

  • US$ 25.00 milhões

  • Ministry of Lands and Natural Resources

  • Leste Asiático e Pacífico

  • 2022

  • US$ 25.00 milhões

  • N/A

  • 20 de fevereiro de 2024

  • 30 de junho de 2027

  • TBD

  • BANK APPROVED

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
IDA Grant 25.00

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD N/A
Compromissos da AID 25.00
Compromisso do BIRD + AID 25.00
Instrumento de empréstimo
Montante do subsídio N/A
Custo total do projeto** 25.00

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 31 de março de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 31 de março de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Procurement Moderately Satisfactory 2024-06-28
Project Management Satisfactory 2024-06-28
Progress towards achievement of PDO Moderately Satisfactory 2024-06-28
Financial Management Satisfactory 2024-06-28
Monitoring and Evaluation Satisfactory 2024-06-28
Overall Implementation Progress (IP) Moderately Satisfactory 2024-06-28

CLASSIFICAÇÕES DAS CONCLUSÕES

Não há dados disponíveis

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

Não há dados disponíveis

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • People in existing settlements provided with improved urban living conditions (disaggregated by gender)Valor0.000.00100.00
    Data20 de setembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Number of people with leases signed for the new residential development, disaggregated by gender and incomeValor0.000.00130.00
    Data10 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • New subdivision lots approved according to disaster- and climate-risk informed urban and land management procedures as per the National Subdivision PolicyValor0.000.0090.00
    Data20 de setembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Infrastructure designs incorporating relevant climate and disaster resilience measuresValor0.000.00100.00
    Data20 de setembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Beneficiaries that feel that project investments reflected their needs (gender-disaggregated)Valor0.000.0070.00
    Data10 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Time taken for subdivision approval of already-zoned, registered land reducedValor54.000.0018.00
    Data10 de novembro de 20218 de dezembro de 202330 de julho de 2027
    Comentário
  • Site development (with resilient basic infrastructure and services) completed for new residential developmentValor0.000.0010.00
    Data10 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Roads constructed or rehabilitatedValor0.000.006.80
    Data10 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Integrated land, cadastral, and hazard mapping system for Greater Port Vila established, maintained, and publicly availableValorNoNoYes
    Data10 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • People provided with access to improved water sourcesValor0.000.00500.00
    Data10 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Short-term employment generated (gender disaggregated)Valor0.000.0078400.00
    Data10 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Reduction in costs of land registrationValor0.000.0025.00
    Data10 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Increase in land regularization titles, of which share of females holding secure occupancy rights (including co-tenancy with spouses)Valor0.000.0090.00
    Data8 de dezembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Five-year operational plan for informal settlement regularization completedValorNoNoYes
    Data10 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Citizens per settlement who have enhanced understanding of the climate and disaster risk reduction interventions as reflected in the survey assessment (disaggregated by gender)Valor0.000.0070.00
    Data23 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Women holding registered leases (including co-tenancy with spouses) in project areasValor0.000.0020.00
    Data24 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Share of short-term employment allocated to womenValor0.000.0015.00
    Data24 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário
  • Female beneficiaries that feel that project investments reflected their needsValor0.000.0070.00
    Data24 de novembro de 20218 de dezembro de 202330 de junho de 2027
    Comentário