Cambodia Southeast Asia Disaster Risk Management Project 2

Resumo*

The proposed Cambodia South East Asia Disaster Risk Management 2 project (KH-SEADRM2) will support the Royal Government of Cambodia (RGC)’s efforts to increase disaster and climate resilience of the rural road network in target areas and improve the capacity of the government to prepare for and respond to emergencies. Following a request from RGC to rebuild rural roads and bridges damaged by the 2020 floods and other recurring floods, KH-SEADRM2 will...

* Os resumos dos projetos são tirados do PAD, SAR ou PGD e talvez não reflitam com exatidão a natureza atual do projeto

Ver mais

Objetivo de Desenvolvimento

The Project Development Objective (PDO) is to improve the disaster and climate resilience of flood-damaged rural roads in Target Areas, improve the capacity of the Government to prepare for and respond to emergencies, and provide immediate and effective response in case of an Eligible Crisis or Emergency.

Chave Detalhes

Projeto Detalhes

  • P177185

  • Active

  • Vica Bogaerts

  • Ministry of Economy and Finance,The Kingdom of Cambodia

  • Camboja

  • 13 de outubro de 2021

  • (conforme apresentação da Diretoria Executiva)

    25 de maio de 2022

  • 8 de setembro de 2022

  • US$ 171.85 milhões

  • Ministry of Rural Development (MRD)

  • Leste Asiático e Pacífico

  • 2022

  • US$ 169.85 milhões

  • N/A

  • 20 de fevereiro de 2024

  • 31 de agosto de 2027

  • Yes

  • BANK APPROVED

  • Notes

Finanças

Plano De Financiamento (US$ Milhões)

Não há dados disponíveis
Financiador Compromissos
Global Facility for Disaster Reduction and Recovery 0.45
IDA Credit 169.40
Borrower/Recipient 2.00

Financiamento total do projeto (US$ milhões)

Linha de produtos BIRD/AID
Compromisso do BIRD N/A
Compromissos da AID 169.40
Compromisso do BIRD + AID 169.40
Instrumento de empréstimo
Montante do subsídio 0.45
Custo total do projeto** 171.85

Resumo da situação do financiamento do Banco Mundial (em US$ milhões) em 28 de fevereiro de 2025

Baixar:
Não há dados disponíveis
Financiador Data Da Aprovação Data De Encerramento Principal Desembolsado Pagamentos Juros, Custos E Taxas

Atividade financeira detalhada em 28 de fevereiro de 2025

Baixar:
Não há dados disponíveis
Período Financiador Tipo De Transção Montante (US$)

Footnotes

Ratings

CLASSIFICAÇÕES DA IMPLEMENTAÇÃO

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-10-28
Monitoring and Evaluation Satisfactory 2024-10-28
Procurement Moderately Satisfactory 2024-10-28
Project Management Satisfactory 2024-10-28
Financial Management Satisfactory 2024-10-28
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-28

CLASSIFICAÇÕES DAS CONCLUSÕES

Não há dados disponíveis

CLASSIFICAÇÕES DA AVALIAÇÃO INDEPENDENTE

Não há dados disponíveis

Estrutura de Resultados

INDICADORES DO OBJETIVO DE DESENVOLVIMENTO DO PROJETO

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Length of rural roads rehabilitated or reconstructed with climate resilience considerationsValor0.000.00400.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Direct project beneficiaries from climate resilient rural roadsValor0.000.00400000.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Post-disaster response and recovery guideline for MRD endorsedValorNoNoYes
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • of which womenValor0.000.00200000.00
    Data10 de maio de 202229 de setembro de 202331 de agosto de 2027
    Comentário

INDICADORES DE RESULTADOS INTERMEDIÁRIOS

INDICADORLINHA DE REFERÊNCIAATUALALVO
  • Emergency Preparedness and Response (EP&R) diagnostics and response needs assessment conductedValorNoNoYes
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Beneficiaries expressing satisfaction with climate-resilient rural road conditionValor0.000.0065.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Grievances registered related to delivery of project benefits addressed in a timely mannerValor0.000.00100.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • The number of people trained in post-disaster damage & needs assessment (PDNA) capacity building activitiesValor0.000.0020.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • of which womenValor0.000.0050.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • The number of strategies, action plans, and/or policies with DRM and climate change adaptation principles enhancedValor0.000.002.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Project-financed roads included in maintenance plan of MRDValor0.000.00100.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Government staff trained on disaster risk management and climate change adaptation measuresValor0.000.00100.00
    Data15 de agosto de 202229 de setembro de 202330 de julho de 2027
    Comentário
  • Enhanced community engagement for road design pilotedValorNoNoYes
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Vulnerability mapping of MRD infrastructure assets in Target Areas conducted, incorporating latest climate-related disaster informationValorNoNoYes
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • People participating in road safety audit, community-based safety awareness campaign, and risk communication activities to address climate-related disaster riskValor0.000.00300.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Rural climate resilience investment options for Target Areas developed, incorporating latest climate-related disaster informationValorNoNoYes
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • of which womenValor0.000.00150.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Road segments for which safety audits have been conducted and recommendations reflected in road designValor0.000.00100.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Climate change adaptation and disaster risk management principles embedded into the Rural Road Asset Management (RRAM) SystemValorNoNoYes
    Data15 de agosto de 202229 de setembro de 202330 de julho de 2027
    Comentário
  • MRD employees and contractors receiving on-the-job capacity building to design and implement road rehabilitation or reconstruction with climate resilience considerationsValor0.000.0035.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • of which womenValor0.000.0010.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário
  • Gender-responsive physical design features identified and mainstreamed into MRD’s standard designValor0.000.002.00
    Data15 de agosto de 202229 de setembro de 202331 de agosto de 2027
    Comentário