Community-Driven Development Project

Abstract*

The development objective forThe Community-Driven Development Project for Gambia is the following: Rural communities, in partnership with Local Government Authorities, plan, implement and maintain their priority social and economic investments. The project consists of the following components. Component 1: The Community Development Fund (CDF) will finance community-driven activities identified on the basis o f a participatory strategic planning process...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Rural communities, in partnership with Local Government Authorities, plan, implement and maintain their priority social and economic investments.

Key Details

Project Details

  • P082969

  • Closed

  • Soulemane Fofana

  • N/A

  • Gambia, The

  • January 26, 2005

  • (as of board presentation)

    August 31, 2006

  • November 2, 2007

  • US$ 16.80 million

  • B

  • Not Applicable

  • October 31, 2012

  • BANK APPROVED

  • June 17, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
JAPAN: Ministry of Finance - PHRD Grants 4.80
IDA Grant 12.00
Borrower/Recipient 2.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 12.00
IBRD + IDA Commitment 12.00
Lending Instrument
Grant Amount 4.80
Total Project Cost** 19.00

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 31, 2006 IDA-H2520 Loan Commitment 12,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2012-12-29
Counterpart Funding Satisfactory 2012-12-29
Project Management Satisfactory 2012-12-29
Progress towards achievement of PDO Satisfactory 2012-12-29
Procurement Satisfactory 2012-12-29
Monitoring and Evaluation Satisfactory 2012-12-29
Financial Management Moderately Satisfactory 2012-12-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 07-25-2013
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-14-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Economic and social Community Subproject results achieved (PDO)Value0.0099.0070.00
    DateOctober 31, 2012October 31, 2012
    Comment1420 subprojects completed over 1428 financed to-date, against an initial target of 1098
  • Satisfaction with the results of the Community Subprojects in targeted rural population (PDO)Value0.0098.6090.00
    DateOctober 31, 2012October 31, 2012
    CommentBased on community score card evaluation
  • Community Subprojects fully functional after 2 years from their completion (PDO)Value0.0092.0070.00
    DateOctober 31, 2012October 31, 2012
    CommentThis is based on the new subprojects that entered the completed ones.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Annually budgeted funds are disbursed (Component A)Value0.00101.00100.00
    DateOctober 31, 2012October 31, 2012
    CommentThe project's performance increased since last mission.
  • Average replenishment time by LGA, WDC and VDC is reduced compared to Year 1 (Component A)Value0.0020.0020.00
    DateOctober 31, 2012October 31, 2012
    CommentThis is based on actual measurements since last mission.
  • Citizens in villages know the use and the amount of funds disbursed through their VDC (Component A)Value0.0056.0080.00
    DateOctober 31, 2012October 31, 2012
    Comment
  • Citizens in wards know use and amount of funds disbursed through their WDC (Component A)Value0.0018.0060.00
    DateOctober 31, 2012October 31, 2012
    Comment
  • Funds are utilized in accordance with PIM Financial and Procurement guidelines Component A)Value0.00100.00100.00
    DateOctober 31, 2012October 31, 2012
    CommentThis remained unchanged.
  • Targeted villages and wards have development plans, developed in accordance with PIM (Component B)Value0.00100.00100.00
    DateOctober 31, 2012October 31, 2012
    CommentSDPs for 525 villages SDP and 88 wards developed
  • Villages and wards development plan activities implemented in accordance with PIM technical standards (Component B)Value0.00100.0095.00
    DateOctober 31, 2012October 31, 2012
    CommentBased on 2012 M&E data.
  • Satisfaction with quality of services provided in support of community-driven development increases in rural population (Component B)Value0.0084.0075.00
    DateOctober 31, 2012October 31, 2012
    CommentThis result is based on score card evaluation for 2011 and 2012.
  • Subprojects screened for environmental and social impact according to ESMF/PIM (Component B)Value0.00100.00100.00
    DateOctober 31, 2012October 31, 2012
    Comment1428 out of the 1428 completed
  • Regular and random technical, financial and procurement audits at PCT, LGA, ward and village level are unqualified (Component C)Value0.0090.0090.00
    DateOctober 31, 2012October 31, 2012
    CommentThis remained unchanged.