Skip to Main Navigation

MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT

Development Objective

To improve social and economic recovery in targeted conflict-affected communities of Mindanao through activities which promote confidence-building, peace and demand-driven governance.

Key Details

Project Details

  • P095173

  • Closed

  • Matthew Stephens

  • Community and Family Services International,International Labour Organization,Mindanao Land Foundation

  • Philippines

  • July 20, 2005

  • (as of board presentation)

    July 20, 2005

  • March 30, 2006

  • US$ 8.26 million

  • Bangsamoro Development Agency,Office of the Presidential Adviser on the Peace Process

  • East Asia and Pacific

  • 2006

  • US$ 8.26 million

  • B

  • March 7, 2024

  • March 31, 2017

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Philippines - Multi-donor Trust Fund Program for Mindanao 8.26

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.26
Total Project Cost** 8.26

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Safeguards Rating Moderately Satisfactory 2017-03-31
Progress towards achievement of PDO Moderately Satisfactory 2017-03-31
Procurement Moderately Satisfactory 2017-03-31
Project Management Moderately Satisfactory 2017-03-31
Financial Management Moderately Satisfactory 2017-03-31
Monitoring and Evaluation Moderately Satisfactory 2017-03-31
Overall Implementation Progress (IP) Moderately Satisfactory 2017-03-31
Overall Safeguards Rating Moderately Satisfactory 2017-03-31

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-29-2018
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-28-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Communities report better access to basic services (time, distance and cost)Value0.0051.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Percentage of beneficiaries who receive entrepreneurship training and support who establish a new enterpriseValue0.0091.00
    DateDecember 11, 2012December 31, 2016
    Comment
  • Increase in number of community members reporting trust in other members/groups within their communityValue0.0016.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Increase in number of community members who think their opinion counts in what needs to be done in their communityValue0.000.0016.00
    DateJuly 1, 2012March 31, 2017March 31, 2017
    Comment
  • Increase in number of community members confident that the BDA/MILF and the government of the Philippines can work together for thebenefit of the communityValue0.000.0057.00
    DateJuly 1, 2012March 31, 2017March 31, 2017
    Comment
  • The economic internal rate of return for community sub-projects will be at or beyond 12%.Value0.000.0012.90
    DateApril 3, 2006March 31, 2017March 31, 2017
    Comment
  • Direct project beneficiariesValue0.000.00638000.00
    DateJanuary 1, 2006March 27, 2018March 31, 2017
    Comment
  • Female beneficiariesValue0.000.00330738.00
    DateJanuary 1, 2006March 27, 2018March 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Beneficiaries experiencing greater security in project areas (%)Value0.0015.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Increase in number of community members reporting communications with members of a different group (ethnic, religious or different sub-village)Value0.000.0015.00
    DateJuly 1, 2012March 31, 2017March 31, 2017
    Comment
  • Community-wide meetings achieve at least 60% participation of householdsValue0.000.000.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of community-wide meetings in which at least 50% of participants are womenValue0.000.009.62
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Communities with improved local infrastructure facilities and/or livelihood activities implemented by the projectValue0.000.00332.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Beneficiaries that feel project investments reflected their needs (percentage)Value0.000.0086.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Communities with sub-project investments that match one of top three identified prioritiesValue0.000.00100.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of people's organization members who are womenValue0.000.0045.74
    DateOctober 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of people's organizations with female officersValue0.000.0092.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Community members who reported participation in a collective effort and also reported improved well beingValue0.000.0038.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of project-facilitated meetings conducted without incidents of conflictValue0.000.00621.00
    DateOctober 1, 2006March 31, 2017March 31, 2017
    Comment
  • Local communities, poeple's organizations and local government units perceive BDA to be a credible development partnerValue0.000.0067.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of BDA and Sajahatra Bangsamoro Project Management Team staff participating in capacity-building sessionsValue0.000.00378.00
    DateJanuary 1, 2007March 31, 2017March 31, 2017
    Comment
  • Program partnerships forged by BDA with other organizationsValue0.000.0017.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Percentage of sub-projects with adequate workmanshipValue0.000.0082.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Regular monthly and quarterly reports delivered on time by BDAValue0.000.005.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Grievances registered related to delivery of project benefits addressed (%)Value0.000.0095.20
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Training sessions provided to people's organizationsValue0.000.002444.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Number of PO members trained in training sessionsValue0.000.005717.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Community members perceiving people's organizations as a functional organizationValue0.000.0084.70
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Bangsamoro Development Plan delivered with at least five community consultationsValue0.000.001.00
    DateNovember 14, 2013March 31, 2017March 31, 2017
    Comment
  • Number of people receiving entrepreneurship training and supportValue0.000.001178.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Increase in income for those who start a new enterpriseValue0.000.0025.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Number of people who receive employment skills trainingValue0.000.000.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Percentage of those who receive employment skills training who secure wage employmentValue0.000.000.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Increase in income for those who secure wage employmentValue0.000.000.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Number of common facilities constructed and being used by the communityValue0.000.008.00
    DateDecember 11, 2012December 30, 2016December 30, 2016
    Comment
  • Total beneficiaries - female (number)Value0.00330738.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Total beneficiaries - male (number)Value0.00307622.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Beneficiaries experiencing greater security in project areas – female (number)Value0.0049610.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Beneficiaries experiencing greater security in project areas – male (number)Value0.0046089.00
    DateJanuary 1, 2006March 31, 2017
    Comment
  • Beneficiaries that feel project inv. reflected their needs - female (number)Value0.000.00284435.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Total beneficiaries - female (number)Value0.000.00330738.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Total beneficiaries - male (number)Value0.000.00307262.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Beneficiaries that feel project inv. reflected their needs - male (number)Value0.000.00264245.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment
  • Grievances related to delivery of project benefits that are addressed (number)Value0.000.0021.00
    DateJanuary 1, 2006March 31, 2017March 31, 2017
    Comment