Financier | Commitments |
---|---|
IDA Credit | 81.00 |
Borrower/Recipient | 10.50 |
P106216
Closed
Mokhlesur Rahman , Shiro Nakata
People's Republic of Bangladesh
April 17, 2008
(as of board presentation)
March 17, 2009
May 13, 2009
US$ 91.50 million
University Grants Commission,Ministry of Education
2009
US$ 81.00 million
B
September 6, 2022
December 31, 2018
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 81.00 |
Borrower/Recipient | 10.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 81.00 |
IBRD + IDA Commitment | 81.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 91.50 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 1, 2021 | IDA-45440 | Int Charges | 6,938.36 |
Aug 1, 2021 | IDA-45440 | Int Charges | 6,938.36 |
May 15, 2022 | IDA-53320 | Int Charges | 6,195.16 |
Feb 1, 2021 | IDA-45440 | Int Charges | 272,826.28 |
Feb 1, 2021 | IDA-45440 | Int Charges | 31,165.50 |
Feb 1, 2021 | IDA-45440 | Int Charges | 31,165.50 |
Feb 1, 2021 | IDA-45440 | Loan Repay | 769,239.70 |
Nov 15, 2020 | IDA-53320 | Int Charges | 5,452.24 |
May 15, 2021 | IDA-53320 | Int Charges | 940.74 |
May 15, 2021 | IDA-53320 | Int Charges | 417,036.90 |
May 15, 2021 | IDA-53320 | Int Charges | 417,036.90 |
May 15, 2021 | IDA-53320 | Int Charges | 940.74 |
Aug 1, 2020 | IDA-45440 | Int Charges | 247,117.88 |
Aug 1, 2020 | IDA-45440 | Int Charges | 247,117.88 |
Aug 1, 2020 | IDA-45440 | Int Charges | 1,106.73 |
Aug 1, 2020 | IDA-45440 | Int Charges | 1,106.73 |
Aug 1, 2020 | IDA-45440 | Loan Repay | 755,746.00 |
Oct 13, 2019 | IDA-53320 | Loan Disb | -0.01 |
Oct 13, 2019 | IDA-53320 | Loan Disb | 0.01 |
Oct 13, 2019 | IDA-53320 | Loan Cancel | 4,998,235.00 |
Oct 13, 2019 | IDA-45440 | Loan Cancel | 1,053,858.80 |
Feb 1, 2020 | IDA-45440 | Loan Repay | 741,256.75 |
Feb 1, 2020 | IDA-45440 | Int Charges | 273,649.72 |
Feb 1, 2020 | IDA-45440 | Int Charges | 273,649.72 |
Feb 1, 2020 | IDA-45440 | Loan Repay | 5,975.23 |
Oct 13, 2019 | IDA-45440 | Loan Disb | -855,172.50 |
May 15, 2020 | IDA-53320 | Int Charges | -601.79 |
May 15, 2020 | IDA-53320 | Int Charges | 400.08 |
May 15, 2020 | IDA-53320 | Int Charges | 400.08 |
May 15, 2020 | IDA-53320 | Int Charges | 394,470.47 |
May 15, 2020 | IDA-53320 | Int Charges | 394,470.47 |
May 15, 2020 | IDA-53320 | Int Charges | 601.79 |
Aug 1, 2019 | IDA-45440 | Int Charges | 3,025.36 |
Aug 1, 2019 | IDA-45440 | Int Charges | 3,025.36 |
Aug 1, 2019 | IDA-45440 | Loan Repay | 743,259.60 |
Aug 1, 2019 | IDA-45440 | Int Charges | 277,977.75 |
Aug 1, 2019 | IDA-45440 | Int Charges | 277,977.75 |
May 15, 2019 | IDA-53320 | Int Charges | 5,949.84 |
May 15, 2019 | IDA-53320 | Int Charges | 5,949.84 |
May 15, 2019 | IDA-53320 | Int Charges | 411,361.53 |
May 15, 2019 | IDA-53320 | Int Charges | 411,361.53 |
Oct 13, 2019 | IDA-53320 | Loan Disb | -3,633,108.00 |
Nov 15, 2019 | IDA-53320 | Int Charges | 3,027.94 |
Nov 15, 2019 | IDA-53320 | Int Charges | 3,027.94 |
Nov 15, 2019 | IDA-53320 | Int Charges | 411,518.12 |
Nov 15, 2019 | IDA-53320 | Int Charges | 411,518.12 |
May 15, 2018 | IDA-53320 | Int Charges | 2,883.83 |
May 15, 2018 | IDA-53320 | Int Charges | 2,883.83 |
May 15, 2018 | IDA-53320 | Int Charges | 380,937.72 |
May 15, 2018 | IDA-53320 | Int Charges | 380,937.72 |
Aug 28, 2018 | IDA-53320 | Loan Disb | 12,398,120.00 |
Aug 1, 2018 | IDA-45440 | Int Charges | 7,353.37 |
Aug 1, 2018 | IDA-45440 | Int Charges | 7,353.37 |
Aug 1, 2018 | IDA-45440 | Int Charges | 284,770.75 |
Aug 1, 2018 | IDA-45440 | Int Charges | 284,770.75 |
Nov 15, 2018 | IDA-53320 | Int Charges | 6,737.34 |
Nov 15, 2018 | IDA-53320 | Int Charges | 6,737.34 |
Feb 1, 2019 | IDA-45440 | Int Charges | 3,020.97 |
Feb 1, 2019 | IDA-45440 | Int Charges | 3,020.97 |
Feb 1, 2019 | IDA-45440 | Int Charges | 61,365.75 |
May 15, 2024 | IDA-53320 | Int Charges | 2,241.69 |
May 15, 2024 | IDA-53320 | Loan Repay | 1,030,245.90 |
May 15, 2024 | IDA-53320 | Int Charges | 4,204.54 |
May 15, 2024 | IDA-53320 | Int Charges | 4,204.54 |
Mar 17, 2009 | IDA-45440 | Loan Commitment | 81,000,000.00 |
Dec 3, 2013 | IDA-53320 | Loan Commitment | 125,000,000.00 |
Feb 1, 2024 | IDA-45440 | Int Charges | 242,536.56 |
Feb 1, 2024 | IDA-45440 | Int Charges | 242,536.56 |
Feb 1, 2024 | IDA-45440 | Int Charges | 7,100.74 |
Feb 1, 2024 | IDA-45440 | Int Charges | 7,100.74 |
Feb 1, 2024 | IDA-45440 | Loan Repay | 710,729.75 |
Aug 1, 2024 | IDA-45440 | Loan Repay | 2,428.19 |
Aug 1, 2024 | IDA-45440 | Loan Repay | 706,584.75 |
Aug 1, 2024 | IDA-45440 | Int Charges | 237,753.90 |
Aug 1, 2024 | IDA-45440 | Int Charges | 237,753.90 |
May 15, 2024 | IDA-53320 | Int Charges | 382,137.66 |
May 15, 2024 | IDA-53320 | Int Charges | 382,137.66 |
May 15, 2024 | IDA-53320 | Int Charges | 2,241.69 |
Nov 15, 2023 | IDA-53320 | Int Charges | 3,346.26 |
Nov 15, 2023 | IDA-53320 | Int Charges | 3,346.26 |
Nov 15, 2023 | IDA-53320 | Int Charges | 384,980.00 |
Nov 15, 2023 | IDA-53320 | Int Charges | 384,980.00 |
Aug 1, 2023 | IDA-45440 | Int Charges | 21,937.19 |
Aug 1, 2023 | IDA-45440 | Loan Repay | 716,511.20 |
Aug 1, 2023 | IDA-45440 | Int Charges | 240,037.84 |
Aug 1, 2023 | IDA-45440 | Int Charges | 240,037.84 |
Aug 1, 2023 | IDA-45440 | Int Charges | 21,937.19 |
Feb 1, 2023 | IDA-45440 | Loan Repay | 17,642.54 |
Feb 1, 2023 | IDA-45440 | Loan Repay | 705,195.60 |
Feb 1, 2023 | IDA-45440 | Int Charges | 229,958.94 |
Feb 1, 2023 | IDA-45440 | Int Charges | 229,958.94 |
May 15, 2023 | IDA-53320 | Int Charges | 23,091.87 |
May 15, 2023 | IDA-53320 | Int Charges | 23,091.87 |
May 15, 2023 | IDA-53320 | Int Charges | 6,273.15 |
May 15, 2023 | IDA-53320 | Int Charges | 6,273.15 |
May 15, 2023 | IDA-53320 | Int Charges | 365,509.22 |
May 15, 2023 | IDA-53320 | Int Charges | 365,509.22 |
Aug 1, 2022 | IDA-45440 | Loan Repay | 707,393.20 |
Aug 1, 2022 | IDA-45440 | Int Charges | 0.01 |
Aug 1, 2022 | IDA-45440 | Int Charges | 0.01 |
Aug 1, 2022 | IDA-45440 | Int Charges | 249,749.81 |
Aug 1, 2022 | IDA-45440 | Int Charges | 249,749.81 |
Aug 1, 2022 | IDA-45440 | Loan Repay | 1,117.06 |
Feb 1, 2022 | IDA-45440 | Loan Repay | 735,758.90 |
Feb 1, 2022 | IDA-45440 | Int Charges | 0.01 |
Feb 1, 2022 | IDA-45440 | Int Charges | 0.01 |
Feb 1, 2022 | IDA-45440 | Int Charges | 266,355.60 |
Feb 1, 2022 | IDA-45440 | Int Charges | 266,355.60 |
Feb 1, 2022 | IDA-45440 | Loan Repay | 11,905.89 |
Nov 15, 2022 | IDA-53320 | Int Charges | 14,177.05 |
Nov 15, 2022 | IDA-53320 | Int Charges | 14,177.05 |
Nov 15, 2022 | IDA-53320 | Int Charges | 363,870.88 |
Nov 15, 2022 | IDA-53320 | Int Charges | 363,870.88 |
Aug 1, 2021 | IDA-45440 | Loan Repay | 278,301.06 |
Aug 1, 2021 | IDA-45440 | Loan Repay | 485,841.72 |
Aug 1, 2021 | IDA-45440 | Int Charges | 275,091.44 |
Aug 1, 2021 | IDA-45440 | Int Charges | 275,091.44 |
Nov 15, 2021 | IDA-53320 | Int Charges | 2,920.22 |
Nov 15, 2021 | IDA-53320 | Int Charges | 2,920.22 |
Nov 15, 2021 | IDA-53320 | Int Charges | 410,168.20 |
Nov 15, 2021 | IDA-53320 | Int Charges | 410,168.20 |
Aug 1, 2014 | IDA-45440 | Int Charges | 291,990.10 |
Jul 27, 2014 | IDA-45440 | Loan Cancel | 46,005.96 |
Feb 1, 2015 | IDA-45440 | Int Charges | 806.08 |
Feb 1, 2015 | IDA-45440 | Int Charges | 806.08 |
Feb 1, 2015 | IDA-45440 | Int Charges | 281,601.40 |
Feb 1, 2015 | IDA-45440 | Int Charges | 281,601.40 |
May 15, 2015 | IDA-53320 | Int Charges | 47,411.44 |
May 15, 2015 | IDA-53320 | Int Charges | 980.37 |
May 15, 2015 | IDA-53320 | Int Charges | 980.37 |
May 15, 2015 | IDA-53320 | Int Charges | 47,411.44 |
Jun 25, 2014 | IDA-45440 | Loan Disb | 3,573,620.80 |
Jun 19, 2014 | IDA-53320 | Loan Disb | 13,963,674.00 |
Aug 1, 2014 | IDA-45440 | Int Charges | 199.13 |
Aug 1, 2014 | IDA-45440 | Int Charges | 199.13 |
Aug 1, 2014 | IDA-45440 | Int Charges | 291,990.10 |
Feb 1, 2014 | IDA-45440 | Int Charges | 285,443.12 |
Feb 1, 2014 | IDA-45440 | Int Charges | 285,443.12 |
Feb 1, 2014 | IDA-45440 | Int Charges | 17,038.95 |
Feb 1, 2014 | IDA-45440 | Int Charges | 17,038.95 |
Mar 12, 2014 | IDA-45440 | Loan Disb | 1,936,886.00 |
Nov 15, 2014 | IDA-53320 | Int Charges | 40,273.61 |
Nov 15, 2014 | IDA-53320 | Int Charges | 40,273.61 |
Aug 1, 2013 | IDA-45440 | Int Charges | 5,057.49 |
Aug 1, 2013 | IDA-45440 | Int Charges | 5,057.49 |
Aug 1, 2013 | IDA-45440 | Int Charges | 204,443.66 |
Aug 1, 2013 | IDA-45440 | Int Charges | 204,443.66 |
Jan 8, 2015 | IDA-45440 | Loan Disb | 935,471.44 |
Jan 8, 2015 | IDA-53320 | Loan Disb | 746,984.06 |
Feb 1, 2019 | IDA-45440 | Int Charges | 61,365.75 |
Feb 1, 2019 | IDA-45440 | Int Charges | 216,351.27 |
Feb 1, 2019 | IDA-45440 | Int Charges | 216,351.27 |
Nov 15, 2018 | IDA-53320 | Int Charges | 384,166.75 |
Nov 15, 2018 | IDA-53320 | Int Charges | 384,166.75 |
Feb 1, 2018 | IDA-45440 | Int Charges | 5,718.65 |
Feb 1, 2018 | IDA-45440 | Int Charges | 5,718.65 |
Feb 1, 2018 | IDA-45440 | Int Charges | 287,775.80 |
Feb 1, 2018 | IDA-45440 | Int Charges | 287,775.80 |
Apr 12, 2017 | IDA-45440 | Loan Disb | -4,273.77 |
Aug 1, 2017 | IDA-45440 | Int Charges | 2,031.08 |
Aug 1, 2017 | IDA-45440 | Int Charges | 2,031.08 |
Aug 1, 2017 | IDA-45440 | Int Charges | 281,019.97 |
Aug 1, 2017 | IDA-45440 | Int Charges | 281,019.97 |
Nov 15, 2017 | IDA-53320 | Int Charges | 4,890.41 |
Nov 15, 2017 | IDA-53320 | Int Charges | 4,890.41 |
Nov 15, 2017 | IDA-53320 | Int Charges | 377,589.50 |
Nov 15, 2017 | IDA-53320 | Int Charges | 377,589.50 |
Sep 22, 2017 | IDA-53320 | Loan Disb | 53,097.34 |
Aug 1, 2016 | IDA-45440 | Int Charges | 809.38 |
Aug 1, 2016 | IDA-45440 | Int Charges | 809.38 |
Aug 1, 2016 | IDA-45440 | Int Charges | 283,795.84 |
Aug 1, 2016 | IDA-45440 | Int Charges | 283,795.84 |
Aug 1, 2016 | IDA-45440 | Int Charges | -309.22 |
Aug 1, 2016 | IDA-45440 | Int Charges | 309.22 |
May 15, 2017 | IDA-53320 | Int Charges | 236,773.72 |
May 15, 2017 | IDA-53320 | Int Charges | 236,773.72 |
Apr 13, 2017 | IDA-53320 | Loan Disb | 1,492,036.80 |
May 18, 2017 | IDA-53320 | Loan Disb | 31,055,900.00 |
May 15, 2017 | IDA-53320 | Int Charges | 6,345.10 |
May 15, 2017 | IDA-53320 | Int Charges | 6,345.10 |
Jun 15, 2016 | IDA-53320 | Loan Disb | 20,279,686.00 |
Apr 10, 2016 | IDA-45440 | Loan Disb | -143,347.23 |
May 15, 2016 | IDA-53320 | Int Charges | 2,342.37 |
May 15, 2016 | IDA-53320 | Int Charges | 2,342.37 |
May 15, 2016 | IDA-53320 | Int Charges | 166,642.05 |
May 15, 2016 | IDA-53320 | Int Charges | 166,642.05 |
Feb 1, 2017 | IDA-45440 | Int Charges | 1,195.93 |
Feb 1, 2017 | IDA-45440 | Int Charges | 1,195.93 |
Feb 1, 2017 | IDA-45440 | Int Charges | 273,489.60 |
Feb 1, 2017 | IDA-45440 | Int Charges | 273,489.60 |
Nov 15, 2016 | IDA-53320 | Int Charges | 2,018.86 |
Nov 15, 2016 | IDA-53320 | Int Charges | 2,018.86 |
Nov 15, 2016 | IDA-53320 | Int Charges | 233,341.48 |
Nov 15, 2016 | IDA-53320 | Int Charges | 233,341.48 |
Feb 1, 2016 | IDA-45440 | Int Charges | 1,697.36 |
Feb 1, 2016 | IDA-45440 | Int Charges | 1,697.36 |
Feb 1, 2016 | IDA-45440 | Int Charges | 279,535.60 |
Feb 1, 2016 | IDA-45440 | Int Charges | 279,535.60 |
Mar 15, 2015 | IDA-45440 | Loan Cancel | 141,029.62 |
Apr 7, 2016 | IDA-45440 | Loan Disb | -41,363.99 |
Jul 2, 2015 | IDA-53320 | Loan Disb | 7,201,355.50 |
May 27, 2015 | IDA-53320 | Loan Disb | 4,622,441.50 |
Jun 25, 2015 | IDA-45440 | Loan Disb | 588,936.94 |
Jun 17, 2015 | IDA-53320 | Loan Disb | 11,762,419.00 |
Aug 1, 2015 | IDA-45440 | Int Charges | 10,307.08 |
Aug 1, 2015 | IDA-45440 | Int Charges | 10,307.08 |
Aug 1, 2015 | IDA-45440 | Int Charges | 269,990.30 |
Aug 1, 2015 | IDA-45440 | Int Charges | 269,990.30 |
Nov 15, 2015 | IDA-53320 | Int Charges | 1,555.08 |
Nov 15, 2015 | IDA-53320 | Int Charges | 1,555.08 |
Nov 15, 2015 | IDA-53320 | Int Charges | 121,156.07 |
Nov 15, 2015 | IDA-53320 | Int Charges | 121,156.07 |
Dec 17, 2015 | IDA-53320 | Loan Disb | 9,989,113.00 |
May 15, 2022 | IDA-53320 | Int Charges | 6,195.16 |
May 15, 2022 | IDA-53320 | Int Charges | 382,322.10 |
May 15, 2022 | IDA-53320 | Int Charges | 382,322.10 |
Nov 15, 2020 | IDA-53320 | Int Charges | 5,452.24 |
Nov 15, 2020 | IDA-53320 | Int Charges | 408,134.70 |
Nov 15, 2020 | IDA-53320 | Int Charges | 408,134.70 |
Feb 1, 2021 | IDA-45440 | Int Charges | 272,826.28 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Satisfactory | 2018-09-10 |
Procurement | Moderately Satisfactory | 2018-09-10 |
Financial Management | Moderately Satisfactory | 2018-09-10 |
Counterpart Funding | Satisfactory | 2018-09-10 |
Progress towards achievement of PDO | Satisfactory | 2018-09-10 |
Project Management | Satisfactory | 2018-09-10 |
Monitoring and Evaluation | Satisfactory | 2018-09-10 |
Overall Implementation Progress (IP) | Satisfactory | 2018-09-10 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-14-2019 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 02-12-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Modest | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
All research and teaching and learning funds under UGC are distributed using an identified set of rules based on transparency and competition | Value | Funding is not competitive | Revamped competitive funding mechanism implemented | |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
Increased level of satisfaction of students and faculty staff regarding the quality of teaching and research environment, and of employers regarding the relevance of teaching and research programs | Value | Student- 3.3Faculty - 2.9Employer - 3.0 | Student - 3.7 (12%) Faculty - 4.0 (38%) Employer - | Student - 4.0 (21%) Faculty - 4.0 (38%) Employer - |
Date | March 31, 2009 | December 31, 2018 | December 31, 2018 | |
Comment |
Monthly average volume of inbound education/ research data traffic in BdREN | Value | 10 TB | 100 TB | |
Date | November 30, 2013 | December 31, 2018 | ||
Comment |
Number of IQAC established and produce self-assessment based on the established framework | Value | 0.00 | 15.00 | 0.00 |
Date | November 30, 2013 | December 31, 2018 | ||
Comment |
Direct project beneficiaries | Value | 30000.00 | 47000.00 | 360000.00 |
Date | November 30, 2013 | December 31, 2018 | December 31, 2018 | |
Comment |
Number of academic publications produced by beneficiaries of AIF subprojects | Value | 65.00 | 150.00 | 0.00 |
Date | November 30, 2013 | December 31, 2018 | ||
Comment |
Female beneficiaries | Value | 28.50 | 35.00 | 0.00 |
Date | November 30, 2013 | June 30, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Teaching and Learning Percentage of fund utilization by teaching and learning sub-projects (Window 1): (i) Round 1, (ii) Round 2, (iii)Round 3 | Value | Round 1: 0, Round 2:0, Round 3: 0 | Round 1: 100%Round 2: 100%Round 3: 100% | |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
National HEMIS is in place and operational at UGC | Value | National HEMIS does not exist. | Annual Statistical Report published | |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
Number of universities (public and private) connected to BdREN | Value | 0.00 | 60.00 | 0.00 |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
QA Unit is fully functional and operational | Value | No QA unit exists | QA Unit established, and draft Qualification Frame | |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
HEQEP Unit is fully functional and operational | Value | 0 | 1 | |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
Percentage of fund utilization by research sub-projects (Window 2): (i) Round 1, (ii) Round 2, (iii) Round 3 | Value | Round 1: 0, Round 2:0, Round 3: 0 | Round 1: 100%Round 2: 100%Round 3: 100% | |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
Proportion of institutions covered under awareness campaign [%] | Value | 0.00 | 100.00 | 0.00 |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
Number (‘000) of online journal title accessed and downloaded using UGC Digital Library on average per month) | Value | 0.00 | 37.00 | 0.00 |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
Completion of baseline survey, follow-up survey at mid-term and end-line survey | Value | 0.00 | 6.00 | 5.00 |
Date | March 31, 2009 | December 31, 2018 | December 31, 2018 | |
Comment |
Percentage increase (cumulative) in doctoral level enrollment [%] under AIF sub-projects | Value | 0.00 | 368.00 | 100.00 |
Date | March 31, 2009 | December 31, 2018 | December 31, 2018 | |
Comment |
Percentage of 39 eligible universities completed at least one self-assessment sub-project [%] | Value | 0.00 | 50.00 | 0.00 |
Date | March 31, 2009 | December 31, 2018 | ||
Comment |
The mechanism for university-industry collaboration piloted and evaluated | Value | The mechanism for university-industry collaboratio | Assessment study was conducted | |
Date | November 30, 2013 | December 31, 2018 | ||
Comment |