Abstract*

The objective of the Second Phase of the Water Resources and Irrigation Sector Management Program Project for Indonesia is to assist the Borrower to improve its capacity for basin water resource and irrigation management and increase irrigated agriculture productivity in the project area. There are four components to the project, the first component being basin water resources management improvement. This component includes: improvement of operational...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

the Project Development Objective is to assist the Borrower to improve its capacity for basin water resource and irrigationmanagement and increase irrigated agriculture productivity in the Project area.

Key Details

Project Details

  • P114348

  • Closed

  • Jun Matsumoto

  • Ministry of Finance

  • Indonesia

  • November 23, 2010

  • (as of board presentation)

    March 22, 2011

  • November 14, 2011

  • US$ 202.56 million

  • Ministry of Public Works (DG Water Resources)

  • East Asia and Pacific

  • 2011

  • US$ 150.00 million

  • B

  • April 22, 2024

  • May 31, 2018

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 150.00
Borrower/Recipient 52.56

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 150.00
IDA Commitment N/A
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 202.56

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2020 IBRD-80270 Int Charges 816,942.90
Nov 15, 2020 IBRD-80270 Loan Repay 2,647,484.50
May 18, 2021 IBRD-80270 Loan Disb -3,732.55
May 15, 2021 IBRD-80270 Int Charges 544,607.25
Nov 15, 2021 IBRD-80270 Int Charges 523,347.97
Nov 15, 2021 IBRD-80270 Loan Repay 2,790,498.20
May 15, 2022 IBRD-80270 Int Charges 523,694.28
May 15, 2022 IBRD-80270 Loan Repay 2,861,832.00
Nov 23, 2021 IBRD-80270 Loan Disb -3,063.84
May 15, 2016 IBRD-80270 Int Charges 626.67
May 15, 2016 IBRD-80270 Int Charges 384,005.03
Nov 15, 2016 IBRD-80270 Int Charges 0.32
Nov 15, 2016 IBRD-80270 Int Charges 538,797.50
Sep 29, 2016 IBRD-80270 Loan Disb -4,241.38
Dec 12, 2016 IBRD-80270 Loan Disb 10,000,000.00
Sep 20, 2016 IBRD-80270 Loan Disb 7,000,000.00
Jun 14, 2016 IBRD-80270 Loan Disb 3,200,000.00
Mar 9, 2017 IBRD-80270 Loan Disb 6,000,000.00
May 15, 2017 IBRD-80270 Int Charges 16,107.35
May 15, 2017 IBRD-80270 Int Charges 841,233.90
Nov 15, 2017 IBRD-80270 Int Charges 1,036,472.40
Aug 23, 2017 IBRD-80270 Loan Disb 5,000,000.00
Jan 4, 2018 IBRD-80270 Loan Disb 15,000,000.00
Dec 28, 2017 IBRD-80270 Loan Disb -64,195.96
Dec 8, 2017 IBRD-80270 Loan Disb 10,000,000.00
May 15, 2018 IBRD-80270 Int Charges 1,367,367.80
Oct 22, 2018 IBRD-80270 Loan Disb -5,381,833.00
Oct 31, 2018 IBRD-80270 Loan Disb -11,202.00
Nov 20, 2014 IBRD-80270 Loan Disb 2,000,000.00
Nov 15, 2014 IBRD-80270 Int Charges 95,999.05
Sep 3, 2013 IBRD-80270 Loan Disb 1,460,000.00
Jan 21, 2014 IBRD-80270 Loan Disb 8,000,000.00
Nov 20, 2013 IBRD-80270 Loan Disb 4,000,000.00
Nov 15, 2013 IBRD-80270 Int Charges 36,751.56
May 15, 2014 IBRD-80270 Int Charges 74,648.35
Feb 17, 2015 IBRD-80270 Loan Disb 1,700,000.00
Jan 29, 2015 IBRD-80270 Loan Disb 7,000,000.00
Jan 6, 2015 IBRD-80270 Loan Disb 7,000,000.00
May 15, 2015 IBRD-80270 Int Charges 166,130.50
Nov 15, 2015 IBRD-80270 Int Charges 3,499.84
Nov 15, 2015 IBRD-80270 Int Charges 252,521.60
Nov 12, 2015 IBRD-80270 Loan Disb 8,000,000.00
Jan 11, 2016 IBRD-80270 Loan Disb 8,000,000.00
Apr 14, 2016 IBRD-80270 Loan Disb -315.96
Feb 19, 2016 IBRD-80270 Loan Disb -10,264.66
Dec 15, 2021 IBRD-80270 Loan Disb -5,181.82
Nov 15, 2022 IBRD-80270 Int Charges 1,682,689.50
Nov 15, 2022 IBRD-80270 Loan Repay 2,933,377.80
Dec 15, 2021 IBRD-80270 Loan Cancel 43,732.97
May 15, 2023 IBRD-80270 Loan Repay 3,004,923.50
May 15, 2023 IBRD-80270 Int Charges 148,159.73
May 15, 2023 IBRD-80270 Int Charges 2,655,160.80
Nov 15, 2023 IBRD-80270 Int Charges 3,097,506.20
Nov 15, 2023 IBRD-80270 Int Charges 61,528.87
Nov 15, 2023 IBRD-80270 Loan Repay 3,076,469.20
May 15, 2024 IBRD-80270 Int Charges 19,658.62
May 15, 2024 IBRD-80270 Int Charges 3,170,831.50
May 15, 2024 IBRD-80270 Loan Repay 3,148,015.20
Mar 22, 2011 IBRD-80270 Loan Commitment 150,000,000.00
Nov 15, 2018 IBRD-80270 Int Charges 2,021,393.90
Jan 16, 2019 IBRD-80270 Loan Cancel 30,712,052.00
May 15, 2019 IBRD-80270 Int Charges 2,117,664.00
May 15, 2019 IBRD-80270 Int Charges 11,460.24
Nov 15, 2019 IBRD-80270 Int Charges 2,005,726.10
Sep 5, 2019 IBRD-80270 Loan Disb -25,742.72
Jun 11, 2020 IBRD-80270 Loan Disb -6,012.04
May 15, 2020 IBRD-80270 Loan Repay 2,587,989.80
May 15, 2020 IBRD-80270 Int Charges 1,573,664.80
May 15, 2021 IBRD-80270 Loan Repay 2,719,038.20
Sep 2, 2014 IBRD-80270 Loan Disb 7,000,000.00
Apr 23, 2015 IBRD-80270 Loan Disb 6,900,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2017-12-06
Procurement Moderately Satisfactory 2017-12-06
Project Management Moderately Satisfactory 2017-12-06
Progress towards achievement of PDO Moderately Satisfactory 2017-12-06
Financial Management Moderately Satisfactory 2017-12-06
Monitoring and Evaluation Moderately Satisfactory 2017-12-06
Overall Implementation Progress (IP) Moderately Satisfactory 2017-12-06

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 11-25-2018
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 01-30-2019PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increase in irrigated areas with over 15% increase in agricultural productionValue0.00390000.00253915.00
    DateFebruary 25, 2011April 4, 2018April 4, 2018
    Comment
  • Area provided with irrigation and drainage services (ha)Value0.00360000.00450412.00
    DateFebruary 25, 2011December 28, 2015December 6, 2017
    Comment
  • Operational water user associations created and/or strengthened (number)Value1175.002030.002070.00
    DateFebruary 25, 2011May 31, 2017April 4, 2018
    Comment
  • Area provided with irrigation and drainage services - Improved (ha)Value0.00360000.00395450.00
    DateFebruary 25, 2011December 28, 2015December 8, 2017
    Comment
  • No. of national and provincial basin agencies fully functionalValue0.0012.0018.00
    DateFebruary 25, 2011April 4, 2018April 4, 2018
    Comment
  • No. of Irrigation Commissions fully functionalValue0.0045.0063.00
    DateFebruary 25, 2011April 4, 2018April 4, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1.2a. No. of river infrastructure O&M plans formulated and implementedValue0.0012.0015.00
    DateFebruary 25, 2011February 25, 2011April 4, 2018
    Comment
  • 1.2b. Percentage of river infrastructure established under the Project functionalValue0.00100.0093.00
    DateFebruary 25, 2011February 25, 2011April 4, 2018
    Comment
  • 2.1. No. of WUAFs duly constitutedValue1175.002995.003112.00
    DateFebruary 25, 2011December 28, 2015April 4, 2018
    Comment
  • 2.2. Command area with improved irrigation infrastructure and services (Component 2)Value0.0059649.00395450.00
    DateFebruary 25, 2011May 31, 2017April 4, 2018
    Comment
  • 3.1. Establishment of effective institutional mechanism for Jatiluhur system managementValueNo effective mechanisms established.Effective O&M mechanism in place.Role-sharing agreement under trial operation (Part
    DateFebruary 25, 2011May 31, 2018October 31, 2016
    Comment
  • 3.2. Command area with improved irrigation infrastructure and services (Component 3)Value0.0059649.0054936.00
    DateFebruary 25, 2011May 31, 2017April 4, 2018
    Comment
  • 4 Establishment of web-based Project management information system in project management and implementation unitsValueNot functionalFunctionalFunctional
    DateFebruary 25, 2011May 31, 2018May 15, 2017
    Comment
  • 1.1. No. of basin water allocation plans operationalValue0.0012.0014.00
    DateFebruary 25, 2011February 25, 2011April 4, 2018