Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
Borrower/Recipient | 52.56 |
P114348
Closed
Jun Matsumoto
Ministry of Finance
November 23, 2010
(as of board presentation)
March 22, 2011
November 14, 2011
US$ 202.56 million
Ministry of Public Works (DG Water Resources)
2011
US$ 150.00 million
B
April 22, 2024
May 31, 2018
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
Borrower/Recipient | 52.56 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 150.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 202.56 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 15, 2020 | IBRD-80270 | Int Charges | 816,942.90 |
Nov 15, 2020 | IBRD-80270 | Loan Repay | 2,647,484.50 |
May 18, 2021 | IBRD-80270 | Loan Disb | -3,732.55 |
May 15, 2021 | IBRD-80270 | Int Charges | 544,607.25 |
Nov 15, 2021 | IBRD-80270 | Int Charges | 523,347.97 |
Nov 15, 2021 | IBRD-80270 | Loan Repay | 2,790,498.20 |
May 15, 2022 | IBRD-80270 | Int Charges | 523,694.28 |
May 15, 2022 | IBRD-80270 | Loan Repay | 2,861,832.00 |
Nov 23, 2021 | IBRD-80270 | Loan Disb | -3,063.84 |
May 15, 2016 | IBRD-80270 | Int Charges | 626.67 |
May 15, 2016 | IBRD-80270 | Int Charges | 384,005.03 |
Nov 15, 2016 | IBRD-80270 | Int Charges | 0.32 |
Nov 15, 2016 | IBRD-80270 | Int Charges | 538,797.50 |
Sep 29, 2016 | IBRD-80270 | Loan Disb | -4,241.38 |
Dec 12, 2016 | IBRD-80270 | Loan Disb | 10,000,000.00 |
Sep 20, 2016 | IBRD-80270 | Loan Disb | 7,000,000.00 |
Jun 14, 2016 | IBRD-80270 | Loan Disb | 3,200,000.00 |
Mar 9, 2017 | IBRD-80270 | Loan Disb | 6,000,000.00 |
May 15, 2017 | IBRD-80270 | Int Charges | 16,107.35 |
May 15, 2017 | IBRD-80270 | Int Charges | 841,233.90 |
Nov 15, 2017 | IBRD-80270 | Int Charges | 1,036,472.40 |
Aug 23, 2017 | IBRD-80270 | Loan Disb | 5,000,000.00 |
Jan 4, 2018 | IBRD-80270 | Loan Disb | 15,000,000.00 |
Dec 28, 2017 | IBRD-80270 | Loan Disb | -64,195.96 |
Dec 8, 2017 | IBRD-80270 | Loan Disb | 10,000,000.00 |
May 15, 2018 | IBRD-80270 | Int Charges | 1,367,367.80 |
Oct 22, 2018 | IBRD-80270 | Loan Disb | -5,381,833.00 |
Oct 31, 2018 | IBRD-80270 | Loan Disb | -11,202.00 |
Nov 20, 2014 | IBRD-80270 | Loan Disb | 2,000,000.00 |
Nov 15, 2014 | IBRD-80270 | Int Charges | 95,999.05 |
Sep 3, 2013 | IBRD-80270 | Loan Disb | 1,460,000.00 |
Jan 21, 2014 | IBRD-80270 | Loan Disb | 8,000,000.00 |
Nov 20, 2013 | IBRD-80270 | Loan Disb | 4,000,000.00 |
Nov 15, 2013 | IBRD-80270 | Int Charges | 36,751.56 |
May 15, 2014 | IBRD-80270 | Int Charges | 74,648.35 |
Feb 17, 2015 | IBRD-80270 | Loan Disb | 1,700,000.00 |
Jan 29, 2015 | IBRD-80270 | Loan Disb | 7,000,000.00 |
Jan 6, 2015 | IBRD-80270 | Loan Disb | 7,000,000.00 |
May 15, 2015 | IBRD-80270 | Int Charges | 166,130.50 |
Nov 15, 2015 | IBRD-80270 | Int Charges | 3,499.84 |
Nov 15, 2015 | IBRD-80270 | Int Charges | 252,521.60 |
Nov 12, 2015 | IBRD-80270 | Loan Disb | 8,000,000.00 |
Jan 11, 2016 | IBRD-80270 | Loan Disb | 8,000,000.00 |
Apr 14, 2016 | IBRD-80270 | Loan Disb | -315.96 |
Feb 19, 2016 | IBRD-80270 | Loan Disb | -10,264.66 |
Dec 15, 2021 | IBRD-80270 | Loan Disb | -5,181.82 |
Nov 15, 2022 | IBRD-80270 | Int Charges | 1,682,689.50 |
Nov 15, 2022 | IBRD-80270 | Loan Repay | 2,933,377.80 |
Dec 15, 2021 | IBRD-80270 | Loan Cancel | 43,732.97 |
May 15, 2023 | IBRD-80270 | Loan Repay | 3,004,923.50 |
May 15, 2023 | IBRD-80270 | Int Charges | 148,159.73 |
May 15, 2023 | IBRD-80270 | Int Charges | 2,655,160.80 |
Nov 15, 2023 | IBRD-80270 | Int Charges | 3,097,506.20 |
Nov 15, 2023 | IBRD-80270 | Int Charges | 61,528.87 |
Nov 15, 2023 | IBRD-80270 | Loan Repay | 3,076,469.20 |
May 15, 2024 | IBRD-80270 | Int Charges | 19,658.62 |
May 15, 2024 | IBRD-80270 | Int Charges | 3,170,831.50 |
May 15, 2024 | IBRD-80270 | Loan Repay | 3,148,015.20 |
Mar 22, 2011 | IBRD-80270 | Loan Commitment | 150,000,000.00 |
Nov 15, 2018 | IBRD-80270 | Int Charges | 2,021,393.90 |
Jan 16, 2019 | IBRD-80270 | Loan Cancel | 30,712,052.00 |
May 15, 2019 | IBRD-80270 | Int Charges | 2,117,664.00 |
May 15, 2019 | IBRD-80270 | Int Charges | 11,460.24 |
Nov 15, 2019 | IBRD-80270 | Int Charges | 2,005,726.10 |
Sep 5, 2019 | IBRD-80270 | Loan Disb | -25,742.72 |
Jun 11, 2020 | IBRD-80270 | Loan Disb | -6,012.04 |
May 15, 2020 | IBRD-80270 | Loan Repay | 2,587,989.80 |
May 15, 2020 | IBRD-80270 | Int Charges | 1,573,664.80 |
May 15, 2021 | IBRD-80270 | Loan Repay | 2,719,038.20 |
Sep 2, 2014 | IBRD-80270 | Loan Disb | 7,000,000.00 |
Apr 23, 2015 | IBRD-80270 | Loan Disb | 6,900,000.00 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2017-12-06 |
Procurement | Moderately Satisfactory | 2017-12-06 |
Project Management | Moderately Satisfactory | 2017-12-06 |
Progress towards achievement of PDO | Moderately Satisfactory | 2017-12-06 |
Financial Management | Moderately Satisfactory | 2017-12-06 |
Monitoring and Evaluation | Moderately Satisfactory | 2017-12-06 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-12-06 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 11-25-2018 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 01-30-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in irrigated areas with over 15% increase in agricultural production | Value | 0.00 | 390000.00 | 253915.00 |
Date | February 25, 2011 | April 4, 2018 | April 4, 2018 | |
Comment |
Area provided with irrigation and drainage services (ha) | Value | 0.00 | 360000.00 | 450412.00 |
Date | February 25, 2011 | December 28, 2015 | December 6, 2017 | |
Comment |
Operational water user associations created and/or strengthened (number) | Value | 1175.00 | 2030.00 | 2070.00 |
Date | February 25, 2011 | May 31, 2017 | April 4, 2018 | |
Comment |
Area provided with irrigation and drainage services - Improved (ha) | Value | 0.00 | 360000.00 | 395450.00 |
Date | February 25, 2011 | December 28, 2015 | December 8, 2017 | |
Comment |
No. of national and provincial basin agencies fully functional | Value | 0.00 | 12.00 | 18.00 |
Date | February 25, 2011 | April 4, 2018 | April 4, 2018 | |
Comment |
No. of Irrigation Commissions fully functional | Value | 0.00 | 45.00 | 63.00 |
Date | February 25, 2011 | April 4, 2018 | April 4, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1.2a. No. of river infrastructure O&M plans formulated and implemented | Value | 0.00 | 12.00 | 15.00 |
Date | February 25, 2011 | February 25, 2011 | April 4, 2018 | |
Comment |
1.2b. Percentage of river infrastructure established under the Project functional | Value | 0.00 | 100.00 | 93.00 |
Date | February 25, 2011 | February 25, 2011 | April 4, 2018 | |
Comment |
2.1. No. of WUAFs duly constituted | Value | 1175.00 | 2995.00 | 3112.00 |
Date | February 25, 2011 | December 28, 2015 | April 4, 2018 | |
Comment |
2.2. Command area with improved irrigation infrastructure and services (Component 2) | Value | 0.00 | 59649.00 | 395450.00 |
Date | February 25, 2011 | May 31, 2017 | April 4, 2018 | |
Comment |
3.1. Establishment of effective institutional mechanism for Jatiluhur system management | Value | No effective mechanisms established. | Effective O&M mechanism in place. | Role-sharing agreement under trial operation (Part |
Date | February 25, 2011 | May 31, 2018 | October 31, 2016 | |
Comment |
3.2. Command area with improved irrigation infrastructure and services (Component 3) | Value | 0.00 | 59649.00 | 54936.00 |
Date | February 25, 2011 | May 31, 2017 | April 4, 2018 | |
Comment |
4 Establishment of web-based Project management information system in project management and implementation units | Value | Not functional | Functional | Functional |
Date | February 25, 2011 | May 31, 2018 | May 15, 2017 | |
Comment |
1.1. No. of basin water allocation plans operational | Value | 0.00 | 12.00 | 14.00 |
Date | February 25, 2011 | February 25, 2011 | April 4, 2018 | |
Comment |